Financier | Commitments |
---|---|
Clean Technology Fund | 250.00 |
Foreign Multilateral Institutions (unidentified) | 100.00 |
Bilateral Agencies (unidentified) | 390.00 |
Borrower/Recipient | 488.00 |
P122329
Closed
Miarintsoa Rakotondramanana
Eskom Holdings SOC Limited
October 6, 2011
(as of board presentation)
October 27, 2011
July 25, 2012
US$ 1228.00 million
ESKOM Holdings SOC Limited
2012
US$ 740.00 million
A
Not Applicable
December 31, 2023
BANK APPROVED
June 27, 2024
Financier | Commitments |
---|---|
Clean Technology Fund | 250.00 |
Foreign Multilateral Institutions (unidentified) | 100.00 |
Bilateral Agencies (unidentified) | 390.00 |
Borrower/Recipient | 488.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 740.00 |
Total Project Cost** | 1228.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Oct 27, 2011 | TF-10690 | Loan Commitment | 250,000,000.00 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Satisfactory | 2023-12-18 |
Monitoring and Evaluation | Satisfactory | 2023-12-18 |
Progress towards achievement of PDO | Moderately Satisfactory | 2023-12-18 |
Project Management | Moderately Satisfactory | 2023-12-18 |
Procurement | Moderately Satisfactory | 2023-12-18 |
Financial Management | Satisfactory | 2023-12-18 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2023-12-18 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-26-2024 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 10-29-2024 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
GHG emissions avoided | Value | 0.00 | 271000.00 | 199000.00 |
Date | June 30, 2011 | December 31, 2023 | November 30, 2018 | |
Comment |
Generation Capacity of Renewable Energy (other than hydropower) constructed | Value | 0.00 | 168.00 | 0.00 |
Date | June 30, 2011 | December 31, 2023 | ||
Comment |
CTF leverage | Value | 0.00 | 1778000000.00 | 1200000000.00 |
Date | June 30, 2011 | December 31, 2023 | June 30, 2011 | |
Comment |
Generation Capacity of Renewable Energy constructed – Wind | Value | 0.00 | 100.00 | 0.00 |
Date | June 30, 2011 | December 31, 2023 | ||
Comment |
Battery Storage Capacity Constructed | Value | 0.00 | 68.00 | 0.00 |
Date | June 30, 2011 | December 31, 2023 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Component 1: Sere Wind Farm construction progress | Value | 0.00 | 100.00 | 0.00 |
Date | June 30, 2011 | December 31, 2023 | ||
Comment |
Component 2: Battery storage capacity | Value | 0.00 | 68.00 | 0.00 |
Date | November 30, 2018 | December 31, 2023 | ||
Comment |
Investments in clean generation as % of investments in electricity generation (CTF Catalytic Replication Outcome) | Value | 0.00 | 10.00 | 0.00 |
Date | June 30, 2011 | December 31, 2023 | ||
Comment |
% of clean energy supply in the overall electricity consumption (CTF Catalytic Replication Outcome) | Value | 0.00 | 3.50 | 0.00 |
Date | June 30, 2011 | December 31, 2023 | ||
Comment |
Investments in clean energy generation (CTF Catalytic Replication Outcome) | Value | 0.00 | 14882000000.00 | 0.00 |
Date | June 30, 2011 | December 31, 2023 | ||
Comment |
Number of jobs created | Value | 0.00 | 572.00 | 0.00 |
Date | June 30, 2011 | December 31, 2023 | ||
Comment |