Rio de Janeiro Metropolitan Urban and Housing Development

Abstract*

The objective of the Rio de Janeiro Metropolitan Urban and Housing Development Program is to support the State Government of Rio de Janeiro (GORJ) to strengthen its policies for planning and managing territorial growth in the Rio de Janeiro Metropolitan Region, promoting the provision of affordable housing, and creating integrated social development programs targeted at the urban poor. The State of Rio de Janeiro (RJ) is the third largest in Brazil...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective of the proposed operation is to support the state government of Rio de Janeiro (GORJ) to strengthen its policies for planning and managing territorial growth in the Rio de Janeiro Metropolitan Region (Regiao Metropolitana de Rio de Janeiro, RMRJ), promoting the provision of affordable housing, and creating integrated social development programs targeted at the urban poor. The proposed operation is fully consistent with and closely linked to the objectives of the Brazil CPS, 2008-2011. In particular, through its prior actions, the DPL will strengthen local governance at the metropolitan level; boost competitiveness by supporting mechanisms that facilitate infrastructure development; improve environmental sustainability by protecting natural resources and assets; andincrease equity by reaching out to the most vulnerable.

Key Details

Project Details

  • P122391

  • Closed

  • Alessandra Campanaro

  • N/A

  • Brazil

  • December 6, 2010

  • (as of board presentation)

    March 15, 2011

  • September 1, 2011

  • US$ 485.00 million

  • N/A

  • June 10, 2014

  • December 31, 2012

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 485.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 485.00
IDA Commitment N/A
IBRD + IDA Commitment 485.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 485.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Nov 27, 2018 IBRD-80110 Int Charges 14,027.49
Nov 27, 2018 IBRD-80110 Int Charges 7,262,391.00
Nov 27, 2018 IBRD-80110 Loan Repay 9,894,000.00
Dec 7, 2017 IBRD-80110 Int Charges 17,232.05
Dec 7, 2017 IBRD-80110 Int Charges 4,969,498.00
Dec 7, 2017 IBRD-80110 Loan Repay 9,894,000.00
Dec 13, 2016 IBRD-80110 Int Charges 3,668,755.50
Dec 13, 2016 IBRD-80110 Loan Repay 9,894,000.00
Jun 14, 2017 IBRD-80110 Int Charges 14,390.27
Jun 14, 2017 IBRD-80110 Int Charges 4,466,920.00
Jun 14, 2017 IBRD-80110 Loan Repay 9,894,000.00
Jun 13, 2016 IBRD-80110 Int Charges 2,819,736.00
May 15, 2015 IBRD-80110 Int Charges 2,023,932.00
May 28, 2020 IBRD-80110 Int Charges 10,042.41
May 28, 2020 IBRD-80110 Int Charges 5,485,715.50
May 28, 2020 IBRD-80110 Loan Repay 9,894,000.00
May 24, 2019 IBRD-80110 Int Charges 11,707.90
May 24, 2019 IBRD-80110 Int Charges 7,773,605.50
May 24, 2019 IBRD-80110 Loan Repay 9,894,000.00
Nov 29, 2019 IBRD-80110 Int Charges 8,137.82
Nov 29, 2019 IBRD-80110 Int Charges 7,157,306.00
Nov 29, 2019 IBRD-80110 Loan Repay 9,894,000.00
May 31, 2018 IBRD-80110 Int Charges 13,785.64
May 31, 2018 IBRD-80110 Int Charges 5,219,462.00
May 31, 2018 IBRD-80110 Loan Repay 9,894,000.00
Nov 26, 2021 IBRD-80110 Int Charges 2,781.31
Nov 26, 2021 IBRD-80110 Int Charges 1,815,339.90
Nov 26, 2021 IBRD-80110 Loan Repay 9,894,000.00
Jun 10, 2022 IBRD-80110 Int Charges 2,902.24
Jun 10, 2022 IBRD-80110 Int Charges 1,815,627.90
Jun 10, 2022 IBRD-80110 Loan Repay 9,894,000.00
Nov 27, 2020 IBRD-80110 Int Charges 4,894.78
Nov 27, 2020 IBRD-80110 Int Charges 2,841,838.00
Nov 27, 2020 IBRD-80110 Loan Repay 9,894,000.00
May 26, 2021 IBRD-80110 Int Charges 3,133.10
May 26, 2021 IBRD-80110 Int Charges 1,891,230.20
May 26, 2021 IBRD-80110 Loan Repay 9,894,000.00
May 15, 2024 IBRD-80110 Int Charges 68,319.56
Nov 15, 2015 IBRD-80110 Int Charges 2,330,155.50
Nov 15, 2022 IBRD-80110 Loan Repay 9,894,000.00
May 15, 2014 IBRD-80110 Int Charges 2,023,932.00
Nov 15, 2014 IBRD-80110 Int Charges 1,958,322.20
May 15, 2024 IBRD-80110 Int Charges 11,045,761.00
Mar 15, 2011 IBRD-80110 Loan Commitment 485,000,000.00
May 15, 2024 IBRD-80110 Loan Repay 9,894,000.00
May 15, 2023 IBRD-80110 Int Charges 513,707.94
May 15, 2023 IBRD-80110 Int Charges 9,213,282.00
May 15, 2023 IBRD-80110 Loan Repay 9,894,000.00
Nov 15, 2023 IBRD-80110 Int Charges 213,502.28
Nov 15, 2023 IBRD-80110 Int Charges 10,764,758.00
Nov 15, 2023 IBRD-80110 Loan Repay 9,894,000.00
Nov 15, 2022 IBRD-80110 Int Charges 14,663.83
Nov 15, 2022 IBRD-80110 Int Charges 5,834,318.50
Nov 15, 2013 IBRD-80110 Int Charges 2,206,211.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Program Management Moderately Unsatisfactory 2013-02-10
Overall Implementation Progress (IP) Moderately Unsatisfactory 2013-02-10
Progress towards achievement of PDO Moderately Unsatisfactory 2013-02-10
Monitoring and Evaluation Moderately Unsatisfactory 2013-02-10

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-28-2013
OutcomesModerately Unsatisfactory
Risk to Development OutcomeModest
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Unsatisfactory
Government PerformanceModerately Satisfactory
Implementing AgencyModerately Unsatisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 07-09-2014PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Unsatisfactory N/a
Risk To Development OutcomeModerateN/a
Bank PerformanceModerately UnsatisfactoryN/a
Borrower PerformanceModerately UnsatisfactoryN/a
Government PerformanceModerately UnsatisfactoryN/a
Implementing AgencyModerately UnsatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Metropolitan-wide plans for RMRJ in effectValue0.001.003.00
    DateDecember 31, 2009November 27, 2012December 31, 2012
    Comment
  • Change in formatting of Plan (PPA) taking into account the Integrated Program for RMRJValueNoYesYes
    DateDecember 31, 2009September 21, 2012December 31, 2012
    Comment
  • Number of passengers using smart-card with integrated fareValue0.00520000.00550000.00
    DateDecember 31, 2009December 12, 2012December 31, 2012
    Comment
  • INEA has increased number of watershed management organizations fully operationalized by contracting an Executive Branch (delegataria)Value75.0078.00100.00
    DateMarch 15, 2011November 28, 2012December 31, 2012
    CommentThe baseline was 6 of 8 operationalized in 2010. An additional watershed was added with an operationalized watershed managementorganization, making the indicator 6 of 9 in 2011 7 of 9 in November 2012. One more is expected to be operationalized by December31. The final one (Guanabara) chose to create a civil society organization to operationalize the organization instead of use anexisting one like the others, which is why it is taking longer than expected. It is expected to be operationalized in January 2013.
  • State level geological landslide susceptibility map covering at least 75% of the municipalities in the RMRJValue10.0084.2075.00
    DateDecember 31, 2009November 28, 2012December 31, 2012
    CommentSixteen of 19 municipalities have been mapped.
  • Signature of 5 donation contracts of state owned land to FAR/CAIXA, benefiting approximately 5,000 families totalValueNoNoYes
    DateMarch 15, 2011November 27, 2012December 31, 2012
    Comment
  • Implementation of at least one model of residents ownership in social housing at Complexo Batan (15,000 residents)Value0.000.001.00
    DateDecember 31, 2009November 27, 2012December 31, 2012
    Comment
  • Increase of land titling program for slum dwellersValue1500.005933.0010000.00
    DateDecember 31, 2009November 27, 2012December 31, 2012
    CommentAccording to ITERJ, an additional 2,182 titles are anticipated through the end of December, reaching a total of 8,115 titles.
  • Number of feasibility studies for identification of adequate areas to implement large scale developments for low income housingValue0.000.003.00
    DateDecember 31, 2009November 27, 2012December 31, 2012
    CommentClient initially pursued COMPERJ area, but recently changed focus to Manguinhos, which has been expropriated by the State.Feasibility studies are underway for Manguinhos, but none have been completed.
  • Number of favela territories benefiting from the UPP Social ProgramsValue0.0030.0020.00
    DateDecember 31, 2009November 29, 2012December 31, 2012
    CommentUPP Social is operating in 30 territories. Territórios de Paz operating in 18 favela territories.
  • Number of social development programs with M&E system establishedValue0.003.0015.00
    DateDecember 31, 2009January 17, 2013December 31, 2012
    CommentAn M&E unit was created and currently has 3 staff. Three programs have rigorous impact evaluations in design or implementation. AnM&E plan is being finalized and all programs and actions are currently being monitored.
  • Increase INEA’s direct annual investment budget (through State Environmental Funds: FECAM, FUNBIO, FUNDHRI), excluding operational cost)Value64.00480.00170.00
    DateDecember 31, 2009November 28, 2012December 31, 2012
    CommentAwaiting confirmation of data.
  • Population benefitting from Real time alarm systemValue2.904.974.90
    DateDecember 31, 2009November 28, 2012December 31, 2012
    Comment(millions of people)Data updated according to 2010 Census (IBGE).
  • Social rental program budgeted and, where applicable, disbursed within 30 days of disasterValueNoYesYes
    DateDecember 31, 2009September 21, 2012December 31, 2012
    Comment
  • Develop an integrated housing development model for about 10 to 15 thousand familiesValueNoNoYes
    DateDecember 31, 2009November 27, 2012December 31, 2012
    CommentClient is in the process of defining a model for Manguinhos, recently expropriated by the Governor.
  • Issuing a public recruitment announcement to hire at least 20% more technical staff for ITERJValueNoYesYes
    DateDecember 31, 2009September 21, 2012December 31, 2012
    CommentFinalists selected in June 2012. ITERJ waiting for budgetary credit to hire approved candidates.
  • Identification of exposure to landslide risk in 10 prioritized areasValue0.0012.0010.00
    DateDecember 31, 2009November 28, 2012December 31, 2012
    Comment
  • Approval of new organization chart of Secretariat of Social Assistance by December 2012ValueNoNoYes
    DateDecember 31, 2009January 17, 2013December 31, 2012
    CommentA proposal for the new structure has been discussed and approved internally but its publication was derailed by the reorganizationof the social area in the State government that transferred some of the SEASDH functions to newly created Secretariats.