Environmental Land Management and Rural Livelihoods Project

Abstract*

The objective of the Environmental Land Management and Rural Livelihoods Project for Tajikistan is to enable rural people to increase their productive assets in ways that improve natural resource management and resilience to climate change in selected climate vulnerable sites. The project has 3 components. (1) Rural production and land resource management investments component will provide financing in the form of small grants for subcomponents: 1.1...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The overall Project Development Objective (PDO) and Global Environmental Objective (GEO) is to enable rural people to increase their productive assets in ways that improve natural resource management and resilience to climate change in selected climate vulnerablesites

Key Details

Project Details

  • P122694

  • Closed

  • Drite Dade

  • Ministry of Finance

  • Tajikistan

  • December 23, 2012

  • (as of board presentation)

    March 29, 2013

  • October 3, 2013

  • US$ 21.11 million

  • Committee on Environmental Protection

  • Europe and Central Asia

  • 2013

  • US$ 18.65 million

  • B

  • July 31, 2023

  • May 31, 2018

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA recommitted as a Grant 1.80
Local Communities 2.46
Global Environment Facility (GEF) 5.40
Strategic Climate Fund Grant 11.45

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 1.80
IBRD + IDA Commitment 1.80
Lending Instrument
Grant Amount 16.85
Total Project Cost** 21.11

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Nov 9, 2016 IDA-D0850 Loan Disb 200,000.00
Dec 19, 2016 IDA-D0850 Loan Disb 151,158.98
Jan 22, 2016 IDA-D0850 Loan Cancel 965,440.00
Jun 30, 2015 IDA-D0850 Loan Commitment 1,800,000.00
May 25, 2017 IDA-D0850 Loan Disb 193,855.03
Sep 1, 2017 IDA-D0850 Loan Disb 132,002.55
Jan 17, 2017 IDA-D0850 Loan Disb 147,928.97
Sep 30, 2018 IDA-D0850 Loan Cancel 365.90

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Satisfactory 2018-05-29
Summary Global Objective Rating Satisfactory 2018-05-29
Monitoring and Evaluation Satisfactory 2018-05-29
Procurement Satisfactory 2018-05-29
Financial Management Satisfactory 2018-05-29
Overall Implementation Progress (IP) Satisfactory 2018-05-29

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 11-21-2018
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 05-16-2019PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualityHighN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Female beneficiariesValue0.000.0048.00
    DateMarch 29, 2013April 24, 2017May 31, 2018
    Comment
  • Number of households supported [in project area] that have adopted climate change and sustainable land management practicesValue0.0040500.0053390.00
    DateMarch 29, 2013April 24, 2017May 31, 2018
    Comment
  • Land users adopting sustainable land mgt. practices as a result of the projectValue0.0023100.0022582.00
    DateMarch 29, 2013April 24, 2017May 31, 2018
    Comment
  • Proportion of population by household in target villages reporting at least 20% increase in well-being or household/livelihood assetsValue0.0050.0053.00
    DateMarch 29, 2013March 29, 2013May 31, 2018
    Comment
  • Number of hectares in project area covered by effective agricultural, land and water management practices suited to local agro-ecological conditions and climate change resilienceValue0.0041500.0044235.00
    DateMarch 29, 2013April 24, 2017May 31, 2018
    Comment
  • Direct project beneficiariesValue0.00243000.00323393.00
    DateMarch 29, 2013April 24, 2017May 31, 2018
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Total value in USD m of rural production and land resource management investments (including at least 25% beneficiary match) in villages where project is operationalValue0.0010940000.0011320000.00
    DateMarch 29, 2013April 24, 2017May 31, 2018
    Comment
  • Number of pasture management plans under implementation by Pasture User GroupsValue0.008.008.00
    DateMarch 29, 2013March 29, 2013May 31, 2018
    Comment
  • Number of on-farm water management plans under implementation by Water User Associations in lowland areasValue0.0016.0016.00
    DateMarch 29, 2013April 24, 2017May 31, 2018
    Comment
  • Hectares in which local communities have adopted management practices in land use and land use change, resulting in restoration andenhancement of carbon stocks.Value0.0039125.0043675.00
    DateMarch 29, 2013April 24, 2017May 31, 2018
    Comment
  • Degree to which villages have integrated climate change adaptation and environmental appraisals into community action plans and areimplementing appropriate investmentsValue0.0075.0080.00
    DateMarch 29, 2013March 29, 2013May 31, 2018
    Comment
  • Number of client days of training provided in organizational and technical topicsValue0.0042000.0038620.00
    DateMarch 29, 2013March 29, 2013May 31, 2018
    Comment
  • Instructional good practice short videos producedValue0.0050.00102.00
    DateJune 30, 2015June 30, 2015May 31, 2018
    Comment
  • Feedback/grievances resolved within the stipulated service standards for response times (100%)Value0.00100.00100.00
    DateJune 30, 2015June 30, 2015May 31, 2018
    Comment