Skip to Main Navigation

Mineral Governance Support Project

Abstract*

The development objective of the Mining Sector Governance Support Project for Guinea is to strengthen the capacity and governance systems of key institutions for managing the minerals sector in Guinea. There are three components to the project. The first component is facilitating access to mineral resources. This component will focus on supporting the Government of Guinea (GoG) in developing the capacities and systems to facilitate negotiation and...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The proposed PDO is to strengthen the capacity and governance systems of key institutions for managing the minerals sector in Guinea.

Key Details

Project Details

  • P122916

  • Closed

  • Boubacar Bocoum

  • Ministry of Finance

  • Guinea

  • January 12, 2012

  • (as of board presentation)

    September 25, 2012

  • April 19, 2013

  • US$ 20.00 million

  • B

  • October 16, 2023

  • November 30, 2020

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 20.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 20.00
IBRD + IDA Commitment 20.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 20.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Sep 26, 2016 IDA-H8040 Loan Disb 155,011.31
Jan 17, 2017 IDA-H8040 Loan Disb 149,688.94
May 18, 2016 IDA-H8040 Loan Disb 291,857.44
Jan 19, 2016 IDA-H8040 Loan Disb 208,129.38
Apr 22, 2015 IDA-H8040 Loan Disb 124,071.20
May 22, 2015 IDA-H8040 Loan Disb 83,693.86
Jul 10, 2015 IDA-H8040 Loan Disb 327,241.20
Jun 10, 2015 IDA-H8040 Loan Disb 113,503.67
Sep 17, 2014 IDA-H8040 Loan Disb 278,070.30
Jul 23, 2014 IDA-H8040 Loan Disb 105,912.26
Mar 6, 2015 IDA-H8040 Loan Disb 238,656.86
Aug 27, 2014 IDA-H8040 Loan Disb 375,423.84
Feb 12, 2015 IDA-H8040 Loan Disb 120,745.61
Apr 19, 2016 IDA-H8040 Loan Disb 275,308.84
Feb 29, 2016 IDA-H8040 Loan Disb 59,216.64
Mar 15, 2016 IDA-H8040 Loan Disb 155,757.31
Jan 13, 2014 IDA-H8040 Loan Disb 39,936.04
Nov 13, 2013 IDA-H8040 Loan Disb 78,249.82
Aug 21, 2013 IDA-H8040 Loan Disb 102,958.60
Jul 25, 2013 IDA-H8040 Loan Disb 275,963.30
Jul 19, 2013 IDA-H8040 Loan Disb 700,000.00
Dec 1, 2014 IDA-H8040 Loan Disb 676,985.20
Jan 15, 2015 IDA-H8040 Loan Disb 74,048.08
Oct 16, 2014 IDA-H8040 Loan Disb 136,755.34
Dec 12, 2014 IDA-H8040 Loan Disb 71,458.28
Jun 16, 2014 IDA-H8040 Loan Disb 676,985.70
May 16, 2014 IDA-H8040 Loan Disb 119,063.73
Mar 14, 2014 IDA-H8040 Loan Disb 89,649.26
Apr 16, 2014 IDA-H8040 Loan Disb 522,513.78
Feb 20, 2014 IDA-H8040 Loan Disb 71,965.69
Oct 18, 2013 IDA-H8040 Loan Disb 74,584.05
Sep 27, 2013 IDA-H8040 Loan Disb 23,569.66
Dec 19, 2013 IDA-H8040 Loan Disb 45,372.55
Sep 25, 2012 IDA-H8040 Loan Commitment 20,000,000.00
Oct 23, 2019 IDA-H8040 Loan Disb 189,817.40
Jun 25, 2021 IDA-H8040 Loan Cancel 90,877.98
May 3, 2021 IDA-H8040 Loan Disb -91,183.89
Jun 22, 2018 IDA-H8040 Loan Disb 143,700.61
Aug 1, 2018 IDA-H8040 Loan Disb 534,806.94
Aug 6, 2018 IDA-H8040 Loan Disb 122,664.24
May 31, 2018 IDA-H8040 Loan Disb 434,986.47
Dec 27, 2017 IDA-H8040 Loan Disb 327,871.88
Apr 6, 2018 IDA-H8040 Loan Disb 261,733.73
Feb 7, 2018 IDA-H8040 Loan Disb 188,639.19
Dec 7, 2017 IDA-H8040 Loan Disb 128,838.06
Nov 26, 2019 IDA-H8040 Loan Disb 56,760.11
Aug 21, 2019 IDA-H8040 Loan Disb 168,769.40
Jun 3, 2019 IDA-H8040 Loan Disb 406,164.25
Apr 1, 2019 IDA-H8040 Loan Disb 83,086.14
May 23, 2019 IDA-H8040 Loan Disb 178,663.80
Jun 19, 2019 IDA-H8040 Loan Disb 306,463.22
Jul 11, 2019 IDA-H8040 Loan Disb 349,331.40
Feb 26, 2019 IDA-H8040 Loan Disb 172,511.86
Oct 18, 2018 IDA-H8040 Loan Disb 562,514.10
Mar 12, 2018 IDA-H8040 Loan Disb 85,633.74
Nov 7, 2017 IDA-H8040 Loan Disb 114,528.84
Sep 25, 2017 IDA-H8040 Loan Disb 158,484.05
Sep 25, 2017 IDA-H8040 Loan Disb 176,028.28
Oct 10, 2017 IDA-H8040 Loan Disb 200,431.05
Mar 2, 2017 IDA-H8040 Loan Disb 113,770.68
Jul 7, 2017 IDA-H8040 Loan Disb 225,259.81
Jun 20, 2017 IDA-H8040 Loan Disb 157,850.23
May 18, 2017 IDA-H8040 Loan Disb 253,749.58
May 8, 2017 IDA-H8040 Loan Disb 164,382.16
Oct 30, 2018 IDA-H8040 Loan Disb 475,479.84
Nov 30, 2018 IDA-H8040 Loan Disb 350,112.34
Dec 20, 2018 IDA-H8040 Loan Disb 331,059.53
May 7, 2018 IDA-H8040 Loan Disb 232,493.60
Dec 15, 2015 IDA-H8040 Loan Disb 647,449.20
Nov 23, 2015 IDA-H8040 Loan Disb 76,005.74
Oct 21, 2015 IDA-H8040 Loan Disb 67,935.03
Sep 11, 2015 IDA-H8040 Loan Disb 255,260.88
Sep 11, 2015 IDA-H8040 Loan Disb 278,525.34
Mar 10, 2017 IDA-H8040 Loan Disb 713,448.90
Jun 10, 2016 IDA-H8040 Loan Disb 176,080.95
Jun 27, 2016 IDA-H8040 Loan Disb 601,956.00
Nov 2, 2016 IDA-H8040 Loan Disb 84,424.01
Sep 23, 2016 IDA-H8040 Loan Disb 200,829.27
Nov 8, 2016 IDA-H8040 Loan Disb 360,809.62
Jan 17, 2017 IDA-H8040 Loan Disb 341,800.75

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2020-11-18
Financial Management Satisfactory 2020-11-18
Monitoring and Evaluation Satisfactory 2020-11-18
Overall Implementation Progress (IP) Satisfactory 2020-11-18
Procurement Satisfactory 2020-11-18
Project Management Satisfactory 2020-11-18

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-23-2021
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Direct project beneficiariesValue0.0056454.0025000.00
    DateSeptember 1, 2012November 11, 2020December 31, 2018
    Comment
  • Decree adopted to clarify institutional relationship, responsibilities, and mandate of SOUGAPAMI vis a vis the Ministries in charge of Mines, Finance, and TransportValueNoYesYes
    DateSeptember 1, 2012November 11, 2020December 31, 2018
    Comment
  • Model build-operate-transfer (BOT) convention for mining ancillary infrastructure developed and adopted.ValueNoYesYes
    DateSeptember 1, 2012November 11, 2020December 31, 2018
    Comment
  • Female beneficiariesValue0.0027.0025.00
    DateSeptember 1, 2012July 21, 2018December 31, 2018
    Comment
  • Mines subjected to annual technical inspections in line with established standardsValue0.008.000.00
    DateSeptember 1, 2012November 11, 2020December 31, 2018
    Comment
  • Mines subjected to fiscal controls per year in line with established standardsValue0.005.000.00
    DateSeptember 1, 2012November 11, 2020December 31, 2018
    Comment
  • Publication of the amount of social investment and government revenues transferred to local communities at national and local levelsValueNoYes
    DateSeptember 1, 2012November 11, 2020
    Comment
  • Percentage of environmental monitoring inspections of mining activities carried out per year by Ministry of Environment with cooperation of the Prefectural Environmental Monitoring CommitteeValue0.00100.00100.00
    DateSeptember 1, 2012November 11, 2020December 31, 2018
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Members of mining communities who are aware of amount of social investment and government revenues supposed to be transferred to local communities and actual transferValue0.0050.000.00
    DateSeptember 1, 2012November 11, 2020
    Comment
  • SOGUIPAMI Governance structure established and adoptedValueNoYesYes
    DateSeptember 1, 2012November 11, 2020December 31, 2018
    Comment
  • Updated and modernized mining cadastre with information accessible on-lineValueNoYesYes
    DateSeptember 1, 2012November 11, 2020December 31, 2018
    Comment
  • Time to issue mining license (after reform)Value0.000.000.00
    DateSeptember 1, 2012November 11, 2020
    Comment
  • Exploration licensesValue0.0025.0030.00
    DateSeptember 1, 2012November 11, 2020December 31, 2018
    Comment
  • Exploitation licensesValue180.0059.00120.00
    DateSeptember 1, 2012November 11, 2020December 31, 2018
    Comment
  • Number of artisanal and small scale miners who have participated in sensitizationValue0.0043367.0015000.00
    DateSeptember 1, 2012November 11, 2020December 31, 2018
    Comment
  • Female ASMs who have participated in sensitizationValue0.005310.003000.00
    DateSeptember 1, 2012November 11, 2020December 31, 2018
    Comment
  • People trained in the updated environmental legislation related to mining operations (Inspectors, Mining communities, CBOs)Value0.005150.005000.00
    DateSeptember 1, 2012November 11, 2020December 31, 2018
    Comment
  • Females trained in environmental legislationValue0.001303.001000.00
    DateSeptember 1, 2012November 11, 2020December 31, 2018
    Comment
  • Mineral revenue collection administration procedures adoptedValueNoYes
    DateSeptember 1, 2012November 11, 2020December 31, 2018
    Comment
  • Operational manual on mining ancillary infrastructure inspection adoptedValueNoYes
    DateSeptember 1, 2012November 11, 2020December 31, 2018
    Comment
  • People trained on technical, financial, control and monitoring of mining ancillary infrastructure in the Ministries in charge of Mines, Transport and SOGUIPAMI.Value0.00100.00100.00
    DateSeptember 1, 2012November 11, 2020December 31, 2018
    Comment
  • Female participants in trainingsValue0.0016.0010.00
    DateSeptember 1, 2012November 11, 2020December 31, 2018
    Comment
  • Number of mining communities that have established a Prefectural Environmental Monitoring CommitteeValue1.0016.009.00
    DateSeptember 1, 2012November 11, 2020December 29, 2018
    Comment
  • Mining ancillary infrastructure related regulations, standards updatedValueNoYes
    DateSeptember 1, 2012November 11, 2020
    Comment
  • Regional development plans developed in at least one key mining regionValue1.001.000.00
    DateAugust 31, 2012November 11, 2020
    Comment
  • Completion of geochemical map on 3 degreesValueNoYesYes
    DateSeptember 1, 2012November 11, 2020December 31, 2018
    Comment
  • Mining regulatory framework, standards updatedValueNoYes
    DateSeptember 1, 2012November 11, 2020
    Comment