Skip to Main Navigation

Ningbo Municipal Solid Waste Minimization and Recycling Project

Abstract*

The development objective of the Ningbo Municipal Solid Waste Minimization and Recycling Project for China is to assist selected districts in Ningbo Municipality to increase the volume and proportion of municipal solid waste recycled with processes for waste separation at source and recycling. The project has four components. The first component is municipal solid waste separation, collection, sorting and transportation. This component will help in...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objective (PDO) is to assist selected districts in Ningbo Municipality to increase the volume and proportion of municipal solid waste recycled with processes for waste separation at source and recycling.

Key Details

Project Details

  • P123323

  • Closed

  • Frank Van Woerden

  • People's Republic of China

  • China

  • June 16, 2011

  • (as of board presentation)

    May 31, 2013

  • September 3, 2013

  • US$ 246.16 million

  • Ningbo Municipal PMO,Ningbo Capital Kitchen Waste Treatment Co., Ltd.

  • East Asia and Pacific

  • 2013

  • US$ 80.00 million

  • B

  • Not Applicable

  • March 31, 2020

  • Yes

  • BANK APPROVED

  • July 12, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 80.00
Borrower/Recipient 166.16

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 80.00
IDA Commitment N/A
IBRD + IDA Commitment 80.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 246.16

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Nov 15, 2015 IBRD-82500 Int Charges 17,738.79
Dec 29, 2015 IBRD-82500 Loan Disb 2,000,000.00
May 15, 2014 IBRD-82500 Int Charges 6,002.62
Nov 25, 2014 IBRD-82500 Loan Disb 1,500,000.00
Nov 15, 2014 IBRD-82500 Int Charges 6,864.22
Sep 3, 2013 IBRD-82500 Loan Disb 200,000.00
Sep 3, 2013 IBRD-82500 Fee Charges 200,000.00
Dec 27, 2013 IBRD-82500 Loan Disb 1,500,000.00
May 31, 2013 IBRD-82500 Loan Commitment 80,000,000.00
Nov 15, 2023 IBRD-82500 Int Charges 39,855.80
Nov 15, 2023 IBRD-82500 Int Charges 2,016,510.90
Nov 15, 2023 IBRD-82500 Loan Repay 1,622,088.20
May 15, 2024 IBRD-82500 Loan Repay 1,622,088.20
May 15, 2024 IBRD-82500 Int Charges 2,076,740.60
May 15, 2024 IBRD-82500 Int Charges 12,797.97
Nov 15, 2022 IBRD-82500 Int Charges 1,085,546.10
Nov 15, 2022 IBRD-82500 Loan Repay 1,622,088.20
May 15, 2023 IBRD-82500 Int Charges 95,581.63
May 15, 2023 IBRD-82500 Int Charges 1,719,900.40
May 15, 2023 IBRD-82500 Loan Repay 1,622,088.20
Nov 15, 2021 IBRD-82500 Int Charges 335,708.38
Nov 15, 2021 IBRD-82500 Loan Repay 1,622,088.20
May 15, 2022 IBRD-82500 Int Charges 336,763.60
May 15, 2022 IBRD-82500 Loan Repay 1,622,088.20
Nov 15, 2020 IBRD-82500 Int Charges 16,279.79
Nov 15, 2020 IBRD-82500 Int Charges 522,629.97
Nov 15, 2020 IBRD-82500 Loan Repay 1,622,088.20
May 15, 2021 IBRD-82500 Int Charges 348,751.10
May 15, 2021 IBRD-82500 Loan Repay 1,622,088.20
May 15, 2020 IBRD-82500 Int Charges 937,780.70
May 15, 2020 IBRD-82500 Loan Repay 1,522,645.40
Mar 5, 2019 IBRD-82500 Loan Disb 1,946,009.40
Nov 15, 2019 IBRD-82500 Int Charges 1,134,480.80
Nov 15, 2019 IBRD-82500 Loan Repay 1,463,106.50
Sep 9, 2019 IBRD-82500 Loan Disb 3,177,473.00
Dec 18, 2019 IBRD-82500 Loan Disb 2,795,253.00
Mar 27, 2020 IBRD-82500 Loan Disb 4,582,625.00
May 15, 2018 IBRD-82500 Int Charges 3,013.45
May 15, 2018 IBRD-82500 Int Charges 437,104.30
Nov 1, 2018 IBRD-82500 Loan Disb 3,313,859.50
Jan 28, 2019 IBRD-82500 Loan Disb 958,082.80
Nov 15, 2018 IBRD-82500 Int Charges 828,133.25
Nov 15, 2018 IBRD-82500 Loan Repay 1,064,941.50
Dec 19, 2018 IBRD-82500 Loan Disb 2,256,377.20
Jan 22, 2019 IBRD-82500 Loan Disb 1,941,374.40
Oct 17, 2018 IBRD-82500 Loan Disb 1,674,379.20
May 15, 2019 IBRD-82500 Int Charges 8,413.72
May 15, 2019 IBRD-82500 Int Charges 1,098,486.50
May 15, 2019 IBRD-82500 Loan Repay 1,311,579.20
Jun 18, 2019 IBRD-82500 Loan Disb 4,107,491.50
Dec 26, 2017 IBRD-82500 Loan Disb 4,831,971.50
Dec 18, 2017 IBRD-82500 Loan Disb 2,282,099.00
Nov 15, 2017 IBRD-82500 Int Charges 1,874.39
Nov 15, 2017 IBRD-82500 Int Charges 280,031.25
Dec 21, 2017 IBRD-82500 Loan Disb 2,500,000.00
Jun 5, 2018 IBRD-82500 Loan Disb 3,198,437.80
Jun 26, 2018 IBRD-82500 Loan Disb 3,582,949.20
Jun 21, 2018 IBRD-82500 Loan Disb 3,579,809.20
Jun 21, 2018 IBRD-82500 Loan Disb 2,747,385.50
May 3, 2017 IBRD-82500 Loan Disb 3,007,032.00
Jun 13, 2017 IBRD-82500 Loan Disb 1,858,606.50
Jun 19, 2017 IBRD-82500 Loan Disb 4,061,900.50
Oct 30, 2017 IBRD-82500 Loan Disb 3,244,145.50
Jun 23, 2016 IBRD-82500 Loan Disb 1,194,922.90
May 11, 2016 IBRD-82500 Loan Disb 4,265,742.00
Nov 15, 2016 IBRD-82500 Int Charges 545.07
Nov 15, 2016 IBRD-82500 Int Charges 108,031.16
Jun 17, 2016 IBRD-82500 Loan Disb 3,494,599.50
Dec 23, 2016 IBRD-82500 Loan Disb 3,191,275.80
May 15, 2017 IBRD-82500 Int Charges 166,252.20
May 15, 2016 IBRD-82500 Int Charges 33,271.03
May 15, 2015 IBRD-82500 Int Charges 13,007.94
Aug 17, 2015 IBRD-82500 Loan Disb 1,006,197.50

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Satisfactory 2020-02-26
Monitoring and Evaluation Moderately Satisfactory 2020-02-26
Overall Implementation Progress (IP) Moderately Satisfactory 2020-02-26
Progress towards achievement of PDO Satisfactory 2020-02-26
Financial Management Satisfactory 2020-02-26
Counterpart Funding Satisfactory 2020-02-26
Project Management Satisfactory 2020-02-26

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-17-2020
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-03-2021PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Proportion of residential waste separatedValue0.0017.540.00
    DateDecember 31, 2013March 31, 2020September 30, 2019
    Comment
  • Total amount of separated kitchen waste collectedValue0.00193200.0075000.00
    DateDecember 31, 2013March 30, 2020March 31, 2019
    Comment
  • Total amount of recycling materials separated at sorting centersValue0.0071600.0011000.00
    DateDecember 31, 2013March 30, 2020March 31, 2019
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of households practising waste separation at sourceValue0.00905000.00636000.00
    DateDecember 31, 2013March 31, 2020March 31, 2019
    Comment
  • Amount of biogas produced at kitchen waste treatment facilitiesValue0.0029000.000.00
    DateDecember 31, 2013March 31, 2020
    Comment
  • Level of residents' satisfaction with separate waste collection services: (i) overall; (ii) women; (iii) menValue0.0094.3090.00
    DateDecember 31, 2013March 31, 2020September 30, 2018
    Comment
  • Number of separated waste containers and collection points deployed: separate waste bins residencesValue0.00955700.00636000.00
    DateDecember 31, 2013March 31, 2020March 31, 2019
    Comment
  • Kitchen waste treatment facility is operatingValueNoYes
    DateDecember 31, 2013March 31, 2020
    Comment
  • Cumulative persons per time exposed to media and education campaignsValue0.003000000.002000000.00
    DateDecember 31, 2013March 31, 2020March 31, 2019
    Comment
  • Number of separated waste containers and collection points deployed: 120-240L separate bins public placesValue0.00104800.000.00
    DateMay 1, 2013March 31, 2020
    Comment
  • Number of separated waste containers and collection points deployed: recycling material collection pointsValue0.00868.000.00
    DateMay 1, 2013March 31, 2020
    Comment
  • Waste sorting center has entered operationValueNoYes
    DateDecember 31, 2013March 31, 2020
    Comment
  • Amount of hazardous waste delivered to hazardous waste processing facilitiesValue0.00187.00175.00
    DateDecember 31, 2013March 31, 2020March 31, 2019
    Comment