Skip to Main Navigation

LA-Poverty Reduction Fund II

Abstract*

The objective of the Second Poverty Reduction Fund Project (PRF II) for Lao People's Democratic Republic is to improve the access to and the utilization of basic infrastructure and services for the project's targeted poor communities in a sustainable manner through inclusive community and local development processes. There are three components to the project. The first component is community development grants (US$40.9 million, 72 percent of project...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

Help improve the access to and the utilization of basic infrastructure and services for the Project's targeted poor communities. The PDO would be achieved through inclusive community and local development processes with emphasis on ensuring sustainability.

Key Details

Project Details

  • P123480

  • Closed

  • Erik Johnson

  • Lao People's Democratic Republic

  • US$ 57.00 million

  • Poverty Reduction Fund,Lao Poverty Reduction Fund,Poverty Reduction Fund

  • East Asia and Pacific

  • 2011

  • US$ 47.00 million

  • B

  • September 8, 2022

  • December 31, 2016

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 10.00
IDA Grant 25.00
SWITZERLAND: Swiss Agency for Dev. & Coop. (SDC) 10.00
Lao PDR - Free-standing Trust Fund Program 12.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 25.00
IBRD + IDA Commitment 25.00
Lending Instrument
Grant Amount 22.00
Total Project Cost** 57.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 30, 2020 IDA-56770 Int Charges 43,507.20
Nov 15, 2020 IDA-56770 Int Charges 585.73
Nov 15, 2020 IDA-56770 Int Charges 585.73
Nov 9, 2016 IDA-56770 Loan Disb 653,122.50
Sep 22, 2016 IDA-56770 Loan Disb 1,410,432.80
Jun 14, 2016 IDA-56770 Loan Disb 1,834,634.00
Nov 7, 2016 IDA-56770 Loan Disb 988,957.10
Dec 9, 2016 IDA-56770 Loan Disb 636,853.44
May 15, 2017 IDA-56770 Int Charges 41,307.54
May 15, 2017 IDA-56770 Int Charges 41,307.54
May 15, 2017 IDA-56770 Int Charges 1,492.69
May 15, 2017 IDA-56770 Int Charges 1,492.69
Nov 15, 2017 IDA-56770 Int Charges 43,977.76
Nov 15, 2017 IDA-56770 Int Charges 43,977.76
Nov 15, 2017 IDA-56770 Int Charges 678.82
Nov 15, 2017 IDA-56770 Int Charges 678.82
May 15, 2018 IDA-56770 Int Charges 343.54
May 15, 2018 IDA-56770 Int Charges 343.54
May 15, 2018 IDA-56770 Int Charges 44,109.80
May 15, 2018 IDA-56770 Int Charges 44,109.80
Jan 20, 2016 IDA-H6850 Loan Disb 384,287.66
Dec 15, 2015 IDA-H6850 Loan Disb 192,849.84
Sep 22, 2015 IDA-H6850 Loan Disb 828,446.70
Mar 15, 2016 IDA-56770 Loan Disb 2,500,000.00
Feb 11, 2016 IDA-H6850 Loan Disb 327,223.22
Apr 12, 2016 IDA-56770 Loan Disb 1,969,895.40
Mar 21, 2016 IDA-H6850 Loan Disb 6,029.08
Aug 2, 2016 IDA-H6850 Loan Disb 103.53
Dec 15, 2016 IDA-56770 Loan Disb 11,697.12
Dec 7, 2016 IDA-56770 Loan Disb 768,895.06
Nov 15, 2016 IDA-56770 Int Charges 4,363.95
Nov 15, 2016 IDA-56770 Int Charges 4,363.95
Oct 18, 2016 IDA-56770 Loan Disb 779,549.80
Nov 15, 2016 IDA-56770 Int Charges 22,603.70
Nov 15, 2016 IDA-56770 Int Charges 22,603.70
Aug 29, 2013 IDA-H6850 Loan Disb 1,484,306.10
Jul 17, 2013 IDA-H6850 Loan Disb 857,750.90
Nov 25, 2014 IDA-H6850 Loan Disb 1,002,517.50
Feb 26, 2014 IDA-H6850 Loan Disb 558,542.90
Sep 11, 2013 IDA-H6850 Loan Disb 816,362.30
Oct 30, 2013 IDA-H6850 Loan Disb 551,622.94
Jul 10, 2013 IDA-H6850 Loan Disb 271,816.94
Nov 12, 2013 IDA-H6850 Loan Disb 712,242.60
Feb 6, 2014 IDA-H6850 Loan Disb 639,150.44
Dec 26, 2013 IDA-H6850 Loan Disb 378,350.25
Apr 28, 2014 IDA-H6850 Loan Disb 399,221.38
Jul 8, 2014 IDA-H6850 Loan Disb 446,012.50
Apr 21, 2014 IDA-H6850 Loan Disb 324,468.22
Mar 11, 2015 IDA-H6850 Loan Disb 515,249.97
Aug 28, 2014 IDA-H6850 Loan Disb 1,947,090.60
Jan 28, 2015 IDA-H6850 Loan Disb 1,052,988.20
Nov 15, 2023 IDA-56770 Int Charges 37,479.10
Nov 15, 2023 IDA-56770 Int Charges 37,479.10
Nov 15, 2023 IDA-56770 Loan Repay 2,934.96
Nov 15, 2023 IDA-56770 Int Charges 3.58
Nov 15, 2023 IDA-56770 Int Charges 3.58
Nov 15, 2023 IDA-56770 Int Charges 1,945.44
Nov 15, 2023 IDA-56770 Loan Repay 169,076.06
Nov 15, 2023 IDA-56770 Int Charges 1,945.44
May 15, 2024 IDA-56770 Int Charges 1,220.58
May 15, 2024 IDA-56770 Int Charges 1,220.58
May 15, 2024 IDA-56770 Loan Repay 171,471.30
May 15, 2024 IDA-56770 Loan Repay 146.77
May 15, 2024 IDA-56770 Int Charges 37,970.52
May 15, 2024 IDA-56770 Int Charges 37,970.52
Jun 23, 2015 IDA-56770 Loan Commitment 11,600,000.00
Jun 9, 2011 IDA-H6850 Loan Commitment 25,000,000.00
May 26, 2021 IDA-56770 Int Charges 44,452.39
May 26, 2021 IDA-56770 Int Charges 44,452.39
May 26, 2021 IDA-56770 Int Charges 730.13
May 26, 2021 IDA-56770 Int Charges 730.13
Nov 29, 2021 IDA-56770 Loan Repay 136,913.10
Nov 29, 2021 IDA-56770 Loan Repay 44,395.21
Nov 29, 2021 IDA-56770 Int Charges 43,514.00
Nov 29, 2021 IDA-56770 Int Charges 43,514.00
Nov 29, 2021 IDA-56770 Int Charges 548.16
Nov 29, 2021 IDA-56770 Int Charges 548.16
May 17, 2022 IDA-56770 Int Charges 31,316.70
May 15, 2022 IDA-56770 Loan Repay 4,507.28
May 17, 2022 IDA-56770 Loan Repay 169,121.45
May 17, 2022 IDA-56770 Int Charges 50.66
May 17, 2022 IDA-56770 Int Charges 50.66
May 17, 2022 IDA-56770 Int Charges 9,709.74
May 17, 2022 IDA-56770 Int Charges 9,709.74
May 17, 2022 IDA-56770 Int Charges 31,316.70
Nov 15, 2022 IDA-56770 Loan Repay 6,489.07
Nov 15, 2022 IDA-56770 Int Charges 6.92
Nov 15, 2022 IDA-56770 Int Charges 6.92
Nov 15, 2022 IDA-56770 Int Charges 36,313.23
Nov 15, 2022 IDA-56770 Int Charges 36,313.23
Nov 15, 2022 IDA-56770 Loan Repay 32,562.30
Nov 15, 2022 IDA-56770 Loan Repay 131,613.48
May 16, 2023 IDA-56770 Loan Repay 169,208.66
May 16, 2023 IDA-56770 Loan Repay 5,014.83
May 16, 2023 IDA-56770 Int Charges 3,436.54
May 16, 2023 IDA-56770 Int Charges 3,436.54
May 16, 2023 IDA-56770 Int Charges 37,883.19
May 16, 2023 IDA-56770 Int Charges 37,883.19
Nov 15, 2018 IDA-56770 Int Charges 780.31
Nov 15, 2018 IDA-56770 Int Charges 780.31
Nov 15, 2018 IDA-56770 Int Charges 42,224.17
Nov 15, 2018 IDA-56770 Int Charges 42,224.17
May 15, 2019 IDA-56770 Int Charges 651.56
May 15, 2019 IDA-56770 Int Charges 651.56
May 15, 2019 IDA-56770 Int Charges 42,373.46
May 15, 2019 IDA-56770 Int Charges 42,373.46
Nov 15, 2019 IDA-56770 Int Charges 312.19
Nov 15, 2019 IDA-56770 Int Charges 312.19
Nov 21, 2019 IDA-56770 Int Charges 42,427.73
Nov 21, 2019 IDA-56770 Int Charges 42,427.73
May 15, 2020 IDA-56770 Int Charges 109.51
May 15, 2020 IDA-56770 Int Charges 109.51
May 15, 2020 IDA-56770 Int Charges 42,311.01
May 15, 2020 IDA-56770 Int Charges 42,311.01
Dec 30, 2020 IDA-56770 Int Charges 43,507.20

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Satisfactory 2016-09-06
Progress towards achievement of PDO Satisfactory 2016-09-06
Procurement Satisfactory 2016-09-06
Financial Management Satisfactory 2016-09-06
Counterpart Funding Satisfactory 2016-09-06
Monitoring and Evaluation Satisfactory 2016-09-06
Overall Implementation Progress (IP) Satisfactory 2016-09-06

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-27-2017
OutcomesSubstantial
Risk to Development OutcomeModest
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Satisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 01-24-2018PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeModestN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualityModestN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Greater than 75% satisfaction levels reported by beneficiaries in targeted villages regarding improved services and local development planningValue0.0099.0080.00
    DateJune 9, 2011October 31, 2015December 31, 2016
    Comment
  • Improved access to and utilization of basic economic and social services in kum bans supported by PRF (Text, Custom)Value0See belowThe supplementary school enrollment indicator has
    DateOctober 31, 2012July 1, 2016December 31, 2016
    Comment
  • Direct project beneficiariesValue0.00946084.00700000.00
    DateJune 9, 2011July 21, 2016December 31, 2016
    Comment
  • Decision-making on allocation of PRF resources involve at least 40% womenValue0.0048.2040.00
    DateJune 9, 2011July 21, 2016December 31, 2016
    Comment
  • Lowest two quintiles benefit from above servicesValueNoYesYes
    DateOctober 31, 2012July 1, 2016December 31, 2016
    Comment
  • % of HHs with access to and utilization of health services (Percentage, Custom Supplement)Value36.00943
    DateOctober 31, 2012July 1, 2016December 31, 2016
    Comment
  • % of HHs with improved access to and utilization of safe water resources (Percentage, Custom Supplement)Value75.00684
    DateOctober 31, 2012July 1, 2016December 31, 2016
    Comment
  • % of HHs with access to all weather roads (percentage, Custom Supplement)Value30.001638
    DateOctober 31, 2012July 1, 2016December 31, 2016
    Comment
  • Female beneficiariesValue0.0049.0050.00
    DateJune 9, 2011July 21, 2016December 31, 2016
    Comment
  • Ethnic beneficiariesValue0.0075.0070.00
    DateJune 9, 2011July 21, 2016December 31, 2016
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Sub-projects with post-project community engagement or O&M arrangements (%)Value0.0095.0090.00
    DateJune 9, 2011July 21, 2016December 31, 2016
    Comment
  • Grievances registered related to delivery of project benefits addressed (%)Value0.00100.0090.00
    DateJune 9, 2011July 21, 2016December 31, 2016
    Comment
  • Community contribution in the total project costs (%)Value0.009.390.00
    DateJune 9, 2011July 21, 2016December 31, 2016
    Comment
  • % PRF kum ban plans used by government and/or other development actors for planning and fundingValue0.0048.0035.00
    DateJune 9, 2011July 21, 2016December 31, 2016
    Comment
  • % of districts where district officials provide technical assistance and supervision to communitiesValue0.00100.0085.00
    DateJune 9, 2011July 21, 2016December 31, 2016
    Comment
  • # of communities able to plan, implement and monitor their activitiesValue0.001349.001300.00
    DateJune 9, 2011July 21, 2016December 31, 2016
    Comment
  • x% of sub-project activities are of high technical qualityValue0.0030.0085.00
    DateJune 9, 2011July 1, 2015December 31, 2016
    Comment
  • #/type of sub-project activities implementedValue0.001930.001600.00
    DateJune 9, 2011July 21, 2016December 31, 2016
    Comment
  • Improvement in dietary diversity among pregnant/ lactating women and children aged 6-24 monthsValue0LN endline survey under way30.00
    DateSeptember 1, 2015December 31, 2016
    Comment
  • No. and type of livelihood activities supported by seed grantValue1675.003755.002400.00
    DateSeptember 1, 2015July 21, 2016December 31, 2016
    Comment
  • % of beneficiary communities that successfully achieved Open Defecation Free (ODF) statusValue0.000.0030.00
    DateSeptember 1, 2015July 21, 2016December 31, 2016
    Comment