Financier | Commitments |
---|---|
Education for All - Fast Track Initiative | 41.70 |
P123503
Closed
Adama Ouedraogo
Government of Mali
May 22, 2013
(as of board presentation)
May 22, 2013
July 10, 2013
US$ 41.70 million
Ministry of Education
2013
US$ 41.70 million
B
Not Applicable
December 31, 2017
Yes
BANK APPROVED
July 17, 2024
Financier | Commitments |
---|---|
Education for All - Fast Track Initiative | 41.70 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 41.70 |
Total Project Cost** | 41.70 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2017-12-29 |
Project Management | Moderately Satisfactory | 2017-12-29 |
Financial Management | Satisfactory | 2017-12-29 |
Monitoring and Evaluation | Satisfactory | 2017-12-29 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2017-12-29 |
Procurement | Moderately Satisfactory | 2017-12-29 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-29-2018 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 12-18-2018 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of additional classrooms built or rehabilitated at the primary level resulting from project interventions. | Value | 0.00 | 960.00 | 960.00 |
Date | August 26, 2013 | December 29, 2017 | December 27, 2017 | |
Comment |
Number of additional students enrolled in targeted areas | Value | 0.00 | 50000.00 | 52500.00 |
Date | August 26, 2013 | December 29, 2017 | December 27, 2017 | |
Comment |
Number of classrooms rehabilitated as a result of project interventions | Value | 0.00 | 200.00 | 202.00 |
Date | August 26, 2013 | December 29, 2017 | December 27, 2017 | |
Comment |
Number of children benefiting from school canteen as a result of project intervention (by gender) | Value | 0.00 | 150000.00 | 168434.00 |
Date | August 26, 2013 | December 29, 2017 | December 27, 2017 | |
Comment |
Number of additional classrooms resulting from project intervention at lower secondary (F2) | Value | 0.00 | 81.00 | 81.00 |
Date | August 26, 2013 | December 29, 2017 | December 27, 2017 | |
Comment |
Number of additional classrooms resulting from project intervention at secondary education | Value | 0.00 | 9.00 | 9.00 |
Date | August 26, 2013 | December 29, 2017 | December 27, 2017 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of COGES set up and trained | Value | 0.00 | 1000.00 | 1332.00 |
Date | July 1, 2013 | December 29, 2017 | December 27, 2017 | |
Comment |
Number of students benefiting from remedial classes as a result of project intervention (by gender) | Value | 0.00 | 20000.00 | 39981.00 |
Date | July 1, 2013 | December 29, 2017 | December 27, 2017 | |
Comment |
Number of additional qualified primary teachers resulting from project interventions. | Value | 0.00 | 2000.00 | 4833.00 |
Date | July 1, 2014 | December 29, 2017 | December 27, 2017 | |
Comment |
Number of additional blocs of latrines resulting from project intervention | Value | 0.00 | 100.00 | 100.00 |
Date | July 1, 2013 | December 29, 2017 | December 27, 2017 | |
Comment |
Number of girls receiving incentives | Value | 0.00 | 15000.00 | 19581.00 |
Date | July 1, 2013 | December 29, 2017 | December 27, 2017 | |
Comment |
Number of additional wells resulting from project intervention | Value | 0.00 | 200.00 | 200.00 |
Date | July 1, 2013 | December 29, 2017 | December 27, 2017 | |
Comment |
Number of students receiving kits as a result of project intervention (by gender) | Value | 0.00 | 30000.00 | 30925.00 |
Date | July 1, 2013 | December 29, 2017 | December 27, 2017 | |
Comment |
Availability of audit report on school infrastructures | Value | No | Yes | Yes |
Date | July 1, 2013 | December 29, 2017 | December 27, 2017 | |
Comment |
EMIS system in place and functioning in targeted areas | Value | No | Yes | Yes |
Date | July 1, 2013 | December 29, 2017 | December 27, 2017 | |
Comment |
Availability of project audit report | Value | No | Yes | Yes |
Date | July 1, 2013 | December 29, 2017 | December 27, 2017 | |
Comment |