Financier | Commitments |
---|---|
Global Food Crisis Response Program | 15.00 |
P123567
Closed
Amadou Ba
Ministry of State for Planning, Regional Development, and Community Development
December 17, 2010
(as of board presentation)
January 25, 2011
June 14, 2011
US$ 15.00 million
PRODEX
2011
US$ 15.00 million
B
Not Applicable
November 30, 2014
BANK APPROVED
May 26, 2015
Financier | Commitments |
---|---|
Global Food Crisis Response Program | 15.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 15.00 |
Total Project Cost** | 15.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2014-11-26 |
Procurement | Satisfactory | 2014-11-26 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2014-11-26 |
Project Management | Satisfactory | 2014-11-26 |
Financial Management | Satisfactory | 2014-11-26 |
Monitoring and Evaluation | Satisfactory | 2014-11-26 |
Counterpart Funding | Satisfactory | 2014-11-26 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 05-29-2015 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Modest |
Bank Performance | Substantial |
Borrower Performance | Substantial |
Government Performance | Substantial |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 09-28-2015 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | Significant | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Direct project beneficiaries | Value | 0.00 | 200682.00 | 180000.00 |
Date | June 14, 2011 | September 30, 2014 | November 30, 2014 | |
Comment | Effectiveness date | 200682 of which 100,342 women. |
Rice yields of Project supported producers (tons/ha) | Value | 4.30 | 6.95 | 5.50 |
Date | June 14, 2011 | September 30, 2014 | November 30, 2014 | |
Comment | This is the average yield related to the Kourani-Baria irrigation schemes which have been rehabilitated and have functioned wellduring the two previous seasons (rainy season of 2013 ; irrigated season of 2013/2014 and 2014 rainy season ended in November2014. |
Incremental rice production in project intervention areas | Value | 55800.00 | 73679.00 | 85800.00 |
Date | June 14, 2011 | September 30, 2014 | November 30, 2014 | |
Comment | This an average production over three production campaigns. The 2013 rainy season's flooding had a negative impact on theexpectedproduction of the Kourani-Baria scheme preventing to attain the expected 100,000 tons |
Female beneficiaries | Value | 0.00 | 100342.00 | 54000.00 |
Date | June 14, 2011 | September 30, 2014 | November 30, 2014 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of small ruminants distributed | Value | 0.00 | 17000.00 | 17000.00 |
Date | June 14, 2011 | September 30, 2014 | May 31, 2014 | |
Comment | Most part of this activity was completed since August 2012 and has specifically targeted women. The remaining 200goats weredistributed from August 2013. This indicator was totally achieved. |
Creation of village lean banks and animal fodder banks in project intervention areas | Value | 0.00 | 45.00 | 50.00 |
Date | June 14, 2011 | September 30, 2014 | November 30, 2014 | |
Comment | The construction of the 45 cereal banks facilities and 5 animal fodder banks fully completed since July 2012. The whole quantitiesof cereals procured, distributed By July 2012. These banks have functioned well during the 2012 and 2013 lean seasons (Augustand September in 2012 and 2013). All stocks have been renewed after the 2012 and 2013 rainy seasons. After the 2012 test a newcycle started in the 2013 lean period from July 2013. | targets : Content of 45 village lean banks and 5 animal fodder banks has been renewed three times over the past 3 years. |
Area provided with improved irrigation and drainage services | Value | 0.00 | 693.00 | 1073.00 |
Date | June 14, 2011 | September 30, 2014 | November 30, 2014 | |
Comment | Rehabilitation works completed at Kourani baria 1&2 have permitted the 693 has to continue functioning quite well. Works stillongoing with huge delay for the second batch of SLK (381 ha) |
Areas cultivated with improved rice seeds | Value | 0.00 | 6356.00 | 8000.00 |
Date | June 14, 2011 | September 30, 2014 | November 30, 2014 | |
Comment | During the 2014 full irrigation season (February to May ) 7062 ha have been cultivated of which 90% were covered with improvedseeds. The project has The project has supported the production of 240 tons of foundation seeds at the seeds farm of Saadia |