Sierra Leone Artisanal Mining Community Development and Sustainable Livelihoods

Development Objective

The development objectives of this project are to pilot community-driven capacity building, empowerment, and participatory decision-making in artisanal and small scale mining communities, enhance social accountability and promote closer cooperation on environmental and social challenges and increase the participation, and enhance the overall sustainable livelihoods of women and other vulnerable groups in artisanal communities. A parallel objective is to support the transition into alternative and more sustainable livelihoods, especially in the agriculture sector, for diamond ASM communities.

Key Details

Project Details

  • P123572

  • Closed

  • Daniele La Porta Arrobas

  • Ministry of Mines and Mineral Resources

  • Sierra Leone

  • July 28, 2011

  • (as of board presentation)

    July 28, 2011

  • July 28, 2011

  • US$ 2.89 million

  • B

  • Not Applicable

  • July 28, 2015

  • BANK APPROVED

  • October 16, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Japan Social Development Fund 2.89

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 2.89
Total Project Cost** 2.89

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Unsatisfactory 2015-07-14
Project Management Satisfactory 2015-07-14
Financial Management Moderately Satisfactory 2015-07-14
Progress towards achievement of PDO Satisfactory 2015-07-14
Monitoring and Evaluation Satisfactory 2015-07-14
Overall Implementation Progress (IP) Highly Satisfactory 2015-07-14

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Improved local governance of ASM sectorValue0.009000.0010000.00
    DateSeptember 7, 2009June 18, 2013June 13, 2014
    Comment
  • Improved community level capacity for inclusive development planningValue0.00100.00150.00
    DateSeptember 7, 2009June 18, 2013June 13, 2014
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Access to oportunities to develop alternative livelihoodsValue0.00100.00150.00
    DateSeptember 7, 2009June 18, 2013June 13, 2014
    Comment
  • Improved community capacity to manage block grantsValue0.00100.00150.00
    DateSeptember 7, 2009June 18, 2013June 13, 2014
    Comment