Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 40.00 |
Borrower/Recipient | 81.26 |
P123923
Closed
Gayane Minasyan
Russian Federation
April 19, 2011
(as of board presentation)
September 20, 2012
December 5, 2013
US$ 121.26 million
Federal Forestry Agency,Ministry of Natural Resources and Environment
2013
US$ 40.00 million
B
July 31, 2023
March 31, 2019
Yes
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 40.00 |
Borrower/Recipient | 81.26 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 40.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 40.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 121.26 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Aug 5, 2014 | IBRD-81970 | Loan Disb | 108,028.52 |
Aug 5, 2014 | IBRD-81970 | Loan Disb | 89,172.38 |
Aug 15, 2014 | IBRD-81970 | Int Charges | 186.11 |
Aug 15, 2014 | IBRD-81970 | Int Charges | 1,512.64 |
Mar 2, 2015 | IBRD-81970 | Loan Disb | 248,974.06 |
Dec 16, 2014 | IBRD-81970 | Loan Disb | 207,540.95 |
Dec 16, 2014 | IBRD-81970 | Loan Disb | 262,055.62 |
Feb 15, 2015 | IBRD-81970 | Int Charges | 47.17 |
Feb 15, 2015 | IBRD-81970 | Int Charges | 4,036.64 |
Dec 16, 2014 | IBRD-81970 | Loan Disb | 57,193.56 |
Aug 15, 2015 | IBRD-81970 | Int Charges | 2,514.09 |
Aug 15, 2015 | IBRD-81970 | Int Charges | 16,484.64 |
Sep 20, 2012 | IBRD-81970 | Loan Commitment | 40,000,000.00 |
Feb 15, 2022 | IBRD-81970 | Loan Repay | 537,312.10 |
Feb 15, 2022 | IBRD-81970 | Int Charges | 0.01 |
Feb 15, 2022 | IBRD-81970 | Int Charges | 34,060.42 |
Aug 15, 2022 | IBRD-81970 | Int Charges | 53,791.99 |
Aug 15, 2022 | IBRD-81970 | Loan Repay | 483,520.16 |
Aug 15, 2022 | IBRD-81970 | Loan Repay | 53,791.99 |
Dec 16, 2022 | IBRD-81970 | Int Charges | 14,728.71 |
Dec 16, 2022 | IBRD-81970 | Int Charges | 132,663.98 |
Dec 16, 2022 | IBRD-81970 | Int Charges | 119,502.11 |
Dec 16, 2022 | IBRD-81970 | Loan Repay | 8,583,338.00 |
Aug 15, 2020 | IBRD-81970 | Int Charges | 124,776.57 |
Aug 15, 2020 | IBRD-81970 | Loan Repay | 537,312.10 |
Feb 15, 2021 | IBRD-81970 | Loan Repay | 46,078.58 |
Feb 15, 2021 | IBRD-81970 | Int Charges | 46,078.58 |
Feb 15, 2021 | IBRD-81970 | Loan Repay | 491,233.56 |
Aug 15, 2021 | IBRD-81970 | Loan Repay | 37,419.50 |
Aug 15, 2021 | IBRD-81970 | Int Charges | 37,419.50 |
Aug 15, 2021 | IBRD-81970 | Loan Repay | 499,892.66 |
Jul 31, 2019 | IBRD-81970 | Loan Cancel | 1,946,334.10 |
Feb 15, 2020 | IBRD-81970 | Int Charges | 149,098.98 |
Feb 15, 2020 | IBRD-81970 | Loan Repay | 537,312.10 |
Feb 15, 2020 | IBRD-81970 | Int Charges | 2,977.89 |
Aug 15, 2019 | IBRD-81970 | Loan Repay | 231,263.02 |
Aug 15, 2019 | IBRD-81970 | Int Charges | 231,263.02 |
Aug 15, 2019 | IBRD-81970 | Loan Repay | 394,621.20 |
Jul 29, 2019 | IBRD-81970 | Loan Disb | -1,781,070.80 |
Jul 29, 2019 | IBRD-81970 | Loan Disb | -165,263.38 |
Feb 22, 2019 | IBRD-81970 | Loan Cancel | 23,756,380.00 |
Feb 15, 2019 | IBRD-81970 | Int Charges | 229,314.55 |
Feb 15, 2019 | IBRD-81970 | Loan Repay | 625,884.20 |
Aug 15, 2018 | IBRD-81970 | Int Charges | 910.60 |
Aug 15, 2018 | IBRD-81970 | Int Charges | 198,047.27 |
Aug 15, 2018 | IBRD-81970 | Loan Repay | 625,884.20 |
Dec 5, 2017 | IBRD-81970 | Loan Disb | 2,800,000.00 |
Dec 5, 2017 | IBRD-81970 | Loan Disb | 500,000.00 |
Feb 15, 2018 | IBRD-81970 | Int Charges | 133,317.03 |
Feb 15, 2018 | IBRD-81970 | Loan Repay | 479,105.84 |
Feb 15, 2018 | IBRD-81970 | Loan Repay | 133,317.03 |
Sep 19, 2017 | IBRD-81970 | Loan Disb | 500,000.00 |
Aug 15, 2017 | IBRD-81970 | Int Charges | 6,869.33 |
Aug 15, 2017 | IBRD-81970 | Int Charges | 99,636.61 |
Oct 18, 2017 | IBRD-81970 | Loan Disb | 410,384.16 |
Oct 18, 2017 | IBRD-81970 | Loan Disb | 11,835.84 |
Dec 26, 2017 | IBRD-81970 | Loan Disb | 336,533.44 |
Aug 15, 2016 | IBRD-81970 | Int Charges | 118.42 |
Aug 15, 2016 | IBRD-81970 | Int Charges | 33,072.02 |
Aug 25, 2016 | IBRD-81970 | Loan Disb | 212,582.84 |
Jun 29, 2016 | IBRD-81970 | Loan Disb | 565,487.94 |
Jun 29, 2016 | IBRD-81970 | Loan Disb | 91,754.80 |
Aug 18, 2016 | IBRD-81970 | Loan Disb | 200,000.00 |
May 5, 2017 | IBRD-81970 | Loan Disb | 862,044.06 |
May 5, 2017 | IBRD-81970 | Loan Disb | 401,731.62 |
Dec 29, 2016 | IBRD-81970 | Loan Disb | 2,600,000.00 |
Feb 15, 2016 | IBRD-81970 | Int Charges | 21,830.68 |
Dec 29, 2016 | IBRD-81970 | Loan Disb | 600,000.00 |
May 26, 2016 | IBRD-81970 | Loan Disb | 400,000.00 |
Jul 8, 2016 | IBRD-81970 | Loan Disb | 200,000.00 |
Nov 18, 2016 | IBRD-81970 | Loan Disb | 103,323.24 |
Nov 18, 2016 | IBRD-81970 | Loan Disb | 307,493.78 |
Feb 15, 2017 | IBRD-81970 | Int Charges | 1,315.09 |
Feb 15, 2017 | IBRD-81970 | Int Charges | 57,554.26 |
May 28, 2015 | IBRD-81970 | Loan Disb | 255,615.02 |
May 27, 2015 | IBRD-81970 | Loan Disb | 23,550.11 |
Dec 28, 2015 | IBRD-81970 | Loan Disb | 100,000.00 |
Nov 13, 2015 | IBRD-81970 | Loan Disb | 55,642.23 |
Nov 24, 2015 | IBRD-81970 | Loan Disb | 189,075.64 |
Dec 9, 2014 | IBRD-81970 | Loan Disb | 67,014.20 |
Nov 10, 2014 | IBRD-81970 | Loan Disb | 146,056.62 |
Dec 30, 2014 | IBRD-81970 | Loan Disb | 1,500,000.00 |
Dec 22, 2014 | IBRD-81970 | Loan Disb | 117,190.98 |
Dec 22, 2014 | IBRD-81970 | Loan Disb | 262,055.62 |
Dec 22, 2014 | IBRD-81970 | Loan Disb | 158,824.52 |
Dec 22, 2014 | IBRD-81970 | Loan Disb | 207,891.45 |
Oct 20, 2014 | IBRD-81970 | Loan Disb | 200,000.00 |
Oct 10, 2014 | IBRD-81970 | Loan Disb | 23,703.67 |
Oct 10, 2014 | IBRD-81970 | Loan Disb | 167,442.12 |
Dec 26, 2013 | IBRD-81970 | Fee Charges | 100,000.00 |
Jan 21, 2014 | IBRD-81970 | Loan Disb | 100,000.00 |
Jan 21, 2014 | IBRD-81970 | Loan Disb | 300,000.00 |
May 16, 2014 | IBRD-81970 | Loan Disb | 28,717.94 |
May 19, 2014 | IBRD-81970 | Loan Disb | 178,919.66 |
Aug 5, 2014 | IBRD-81970 | Loan Disb | 85,784.12 |
Name | Review | Date |
---|---|---|
Financial Management | Satisfactory | 2018-12-28 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2018-12-28 |
Monitoring and Evaluation | Moderately Unsatisfactory | 2018-12-28 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2018-12-28 |
Project Management | Moderately Unsatisfactory | 2018-12-28 |
Procurement | Moderately Unsatisfactory | 2018-12-28 |
Counterpart Funding | Satisfactory | 2018-12-28 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-06-2019 |
---|---|
Outcomes | Unsatisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 03-31-2020 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Unsatisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Negligible | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Increase in percentage of fires contained within 24 hours following detection in pilot region extensive forest and project PAs | Value | N/A | N/A | N/A |
Date | December 15, 2011 | March 31, 2019 | December 15, 2016 | |
Comment |
Increase in percentage of fires contained within 24 hours following detection in pilot region extensive forest | Value | 73.9 | 75.00 | 76.5 |
Date | December 15, 2011 | March 31, 2019 | December 15, 2016 | |
Comment |
Increase in percentage of fires contained within 24 hours following detection in project PAs | Value | 72 | 84.44 | 87 |
Date | December 15, 2011 | March 31, 2019 | December 15, 2016 | |
Comment |
Average area of fires at detection in project PAs | Value | 14 | 4.92 | 5 |
Date | November 17, 2015 | March 31, 2019 | December 15, 2016 | |
Comment |
Area covered by improved Forest Pest Monitoring System in Pilot Regions | Value | 0.00 | 0.00 | 10000000.00 |
Date | December 15, 2011 | March 31, 2019 | December 15, 2016 | |
Comment |
Area of improved forest regeneration based on modern technology in Pilot Regions | Value | 0.00 | 0.00 | 5.00 |
Date | December 15, 2011 | March 31, 2019 | December 15, 2016 | |
Comment |
Reach and acceptance of fire prevention messages among the PA target population in comparison to baseline | Value | N/A | N/A | N/A |
Date | December 15, 2011 | March 31, 2019 | December 15, 2016 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Development of a National Forest Fire Management Strategy for Federal PAs | Value | No | No | Yes |
Date | December 15, 2011 | March 31, 2019 | December 15, 2016 | |
Comment |
Protected Area fire brigades equipped and trained | Value | 0.00 | 13.00 | 25.00 |
Date | December 15, 2011 | December 25, 2018 | December 15, 2016 | |
Comment |
Proportion of large fires out of the total number of fires in Pilot Regions exentsive forest | Value | 8.00 | 0.00 | 7.10 |
Date | December 15, 2016 | December 25, 2018 | December 15, 2016 | |
Comment |
Pilot region fire brigades equipped | Value | 0.00 | 0.00 | 5.00 |
Date | December 15, 2011 | December 25, 2018 | December 15, 2016 | |
Comment |
Decrease in the number of fires in Project PAs in comparison to comparable PAs without project support | Value | N/A | N/A | |
Date | December 15, 2016 | December 25, 2018 | December 15, 2016 | |
Comment |
Reforms in forest policy, legislation or other regulations supported | Value | No | No | Yes |
Date | December 15, 2011 | December 25, 2018 | December 15, 2016 | |
Comment |
Updated fire danger rating and hazard index system trialed in targeted Protected Areas | Value | 0.00 | 0.00 | 18.00 |
Date | December 15, 2011 | December 25, 2018 | December 15, 2016 | |
Comment |
Forest information management systems in operation, with data generated by Protected Areas used to produce reporting on forest firerisks, hazards, response, and damage | Value | 0.00 | 0.00 | 1.00 |
Date | December 15, 2011 | December 25, 2018 | December 15, 2016 | |
Comment |
Landscape restoration programs developed in disturbed PA landscapes | Value | 0.00 | 0.00 | 3.00 |
Date | December 15, 2011 | December 25, 2018 | December 15, 2016 | |
Comment |
Number of PAs covered by fire management planning and implementation to protect biodiversity and habitat | Value | 0.00 | 2.00 | 6.00 |
Date | December 15, 2011 | December 25, 2018 | December 15, 2016 | |
Comment |