Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 100.00 |
IDA Credit | 100.00 |
P124174
Closed
Pedro Antmann
N/A
November 7, 2011
(as of board presentation)
March 22, 2012
August 9, 2012
US$ 200.00 million
ERAV (MOIT)
2012
US$ 200.00 million
N/A
Not Applicable
July 31, 2013
BANK APPROVED
August 1, 2017
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 100.00 |
IDA Credit | 100.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 100.00 |
IDA Commitment | 100.00 |
IBRD + IDA Commitment | 200.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 200.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Feb 15, 2016 | IDA-50820 | Int Charges | 1,255,728.40 |
Feb 15, 2024 | IDA-50820 | Loan Repay | 2,808,814.50 |
Feb 15, 2024 | IDA-50820 | Int Charges | 224,929.84 |
Feb 15, 2024 | IDA-50820 | Int Charges | 224,929.84 |
Feb 15, 2024 | IDA-50820 | Int Charges | 839,738.06 |
Mar 22, 2012 | IBRD-81470 | Loan Commitment | 100,000,000.00 |
Mar 22, 2012 | IDA-50820 | Loan Commitment | 100,000,000.00 |
Feb 15, 2023 | IDA-50820 | Int Charges | 248,755.17 |
Feb 15, 2023 | IDA-50820 | Int Charges | 248,755.17 |
Feb 15, 2023 | IDA-50820 | Int Charges | 908,917.50 |
Feb 15, 2023 | IDA-50820 | Loan Repay | 34,931.88 |
Feb 15, 2023 | IBRD-81470 | Loan Repay | 2,040,000.00 |
Feb 15, 2023 | IBRD-81470 | Int Charges | 131,838.34 |
Feb 15, 2023 | IBRD-81470 | Int Charges | 1,835,560.00 |
Aug 15, 2023 | IDA-50820 | Int Charges | 19,694.20 |
Aug 15, 2023 | IDA-50820 | Int Charges | 237,184.95 |
Aug 15, 2023 | IDA-50820 | Int Charges | 237,184.95 |
Aug 15, 2023 | IDA-50820 | Int Charges | 885,490.50 |
Aug 15, 2023 | IBRD-81470 | Int Charges | 83,466.40 |
Aug 15, 2023 | IBRD-81470 | Loan Repay | 2,040,000.00 |
Aug 15, 2023 | IBRD-81470 | Int Charges | 2,194,721.50 |
Aug 15, 2023 | IDA-50820 | Loan Repay | 2,835,907.00 |
Aug 15, 2024 | IBRD-81470 | Loan Repay | 2,040,000.00 |
Aug 15, 2024 | IDA-50820 | Int Charges | 749,186.10 |
Aug 15, 2024 | IDA-50820 | Loan Repay | 2,796,434.00 |
Aug 15, 2024 | IDA-50820 | Int Charges | 216,923.60 |
Aug 15, 2024 | IDA-50820 | Int Charges | 216,923.60 |
Aug 15, 2024 | IBRD-81470 | Int Charges | 13,878.96 |
Aug 15, 2024 | IBRD-81470 | Int Charges | 2,411,857.00 |
Aug 15, 2024 | IDA-50820 | Loan Repay | 52,712.26 |
Feb 15, 2024 | IDA-50820 | Loan Repay | 6,807.87 |
Feb 15, 2024 | IBRD-81470 | Int Charges | 22,553.73 |
Feb 15, 2024 | IBRD-81470 | Int Charges | 2,471,428.00 |
Feb 15, 2024 | IBRD-81470 | Loan Repay | 2,040,000.00 |
Aug 15, 2021 | IDA-50820 | Loan Repay | 3,023,215.00 |
Feb 15, 2022 | IDA-50820 | Int Charges | 1,042,977.10 |
Feb 15, 2022 | IDA-50820 | Loan Repay | 58,837.55 |
Feb 15, 2022 | IBRD-81470 | Int Charges | 380,651.03 |
Feb 15, 2022 | IBRD-81470 | Loan Repay | 2,040,000.00 |
Feb 15, 2022 | IDA-50820 | Loan Repay | 2,922,850.50 |
Feb 15, 2016 | IDA-50820 | Int Charges | 339,162.62 |
Feb 15, 2016 | IDA-50820 | Int Charges | 339,162.62 |
Aug 15, 2014 | IBRD-81470 | Int Charges | 402,222.22 |
Aug 15, 2014 | IDA-50820 | Int Charges | 7,074.35 |
Aug 15, 2014 | IDA-50820 | Int Charges | 369,838.97 |
Aug 15, 2014 | IDA-50820 | Int Charges | 369,838.97 |
Aug 15, 2014 | IDA-50820 | Int Charges | 1,380,732.10 |
Aug 15, 2015 | IDA-50820 | Int Charges | 1,267,486.90 |
Aug 15, 2015 | IBRD-81470 | Int Charges | 457,527.78 |
Aug 15, 2015 | IDA-50820 | Int Charges | 52,538.32 |
Aug 15, 2015 | IDA-50820 | Int Charges | 52,538.32 |
Aug 15, 2015 | IDA-50820 | Int Charges | 286,967.12 |
Aug 15, 2015 | IDA-50820 | Int Charges | 286,967.12 |
Feb 15, 2014 | IDA-50820 | Int Charges | 9,331.88 |
Feb 15, 2014 | IDA-50820 | Int Charges | 9,331.88 |
Feb 15, 2014 | IDA-50820 | Int Charges | 364,149.72 |
Feb 15, 2014 | IDA-50820 | Int Charges | 364,149.72 |
Feb 15, 2014 | IDA-50820 | Int Charges | 1,387,187.20 |
Feb 15, 2014 | IBRD-81470 | Int Charges | 444,666.66 |
Feb 15, 2015 | IDA-50820 | Int Charges | 12,035.27 |
Feb 15, 2015 | IDA-50820 | Int Charges | 330,338.78 |
Feb 15, 2015 | IDA-50820 | Int Charges | 330,338.78 |
Feb 15, 2015 | IDA-50820 | Int Charges | 1,278,196.50 |
Feb 15, 2015 | IDA-50820 | Int Charges | 12,035.27 |
Feb 15, 2015 | IBRD-81470 | Int Charges | 424,222.22 |
Aug 15, 2013 | IBRD-81470 | Int Charges | 184,648.33 |
Aug 15, 2013 | IBRD-81470 | Int Charges | 462,555.56 |
Aug 15, 2013 | IDA-50820 | Int Charges | 411,266.84 |
Aug 15, 2013 | IDA-50820 | Int Charges | 367,202.53 |
Aug 15, 2013 | IDA-50820 | Int Charges | 367,202.53 |
Aug 15, 2013 | IDA-50820 | Int Charges | 1,370,889.50 |
Aug 15, 2013 | IDA-50820 | Int Charges | 110,160.76 |
Aug 15, 2013 | IDA-50820 | Int Charges | 110,160.76 |
Aug 15, 2021 | IBRD-81470 | Int Charges | 400,812.44 |
Aug 15, 2021 | IBRD-81470 | Loan Repay | 2,040,000.00 |
Aug 15, 2021 | IDA-50820 | Int Charges | 298,198.94 |
Aug 15, 2021 | IDA-50820 | Int Charges | 298,198.94 |
Aug 15, 2021 | IDA-50820 | Int Charges | 1,113,276.00 |
Aug 15, 2021 | IDA-50820 | Int Charges | 5,794.69 |
Aug 15, 2019 | IBRD-81470 | Int Charges | 1,623,706.80 |
Aug 15, 2019 | IBRD-81470 | Loan Repay | 2,040,000.00 |
Aug 15, 2019 | IDA-50820 | Int Charges | 1,159,163.20 |
Aug 15, 2019 | IDA-50820 | Int Charges | 16,172.30 |
Aug 15, 2019 | IDA-50820 | Loan Repay | 1,462,694.50 |
Aug 15, 2019 | IDA-50820 | Int Charges | 0.01 |
Aug 15, 2019 | IDA-50820 | Int Charges | 0.01 |
Aug 15, 2019 | IDA-50820 | Int Charges | 310,490.12 |
Aug 15, 2019 | IDA-50820 | Int Charges | 310,490.12 |
Feb 15, 2020 | IBRD-81470 | Loan Repay | 2,040,000.00 |
Feb 15, 2020 | IDA-50820 | Loan Repay | 19,179.25 |
Feb 15, 2020 | IDA-50820 | Loan Repay | 1,436,193.20 |
Feb 15, 2020 | IDA-50820 | Int Charges | 303,478.25 |
Feb 15, 2020 | IDA-50820 | Int Charges | 303,478.25 |
Feb 15, 2020 | IDA-50820 | Int Charges | 1,132,985.50 |
Feb 15, 2020 | IBRD-81470 | Int Charges | 1,276,780.10 |
Feb 15, 2019 | IDA-50820 | Int Charges | 1,173,779.50 |
Feb 15, 2019 | IDA-50820 | Loan Repay | 61,964.77 |
Feb 15, 2019 | IDA-50820 | Loan Repay | 1,413,692.40 |
Feb 15, 2019 | IDA-50820 | Int Charges | 318,775.47 |
Feb 15, 2019 | IDA-50820 | Int Charges | 318,775.47 |
Feb 15, 2019 | IBRD-81470 | Int Charges | 1,563,922.20 |
Feb 15, 2019 | IBRD-81470 | Loan Repay | 2,040,000.00 |
Aug 15, 2018 | IBRD-81470 | Int Charges | 1,339,657.40 |
Aug 15, 2018 | IBRD-81470 | Loan Repay | 2,040,000.00 |
Aug 15, 2018 | IDA-50820 | Int Charges | 323,563.10 |
Aug 15, 2018 | IDA-50820 | Int Charges | 323,563.10 |
Aug 15, 2018 | IDA-50820 | Int Charges | 1,207,968.80 |
Aug 15, 2018 | IDA-50820 | Int Charges | 94,176.54 |
Aug 15, 2018 | IDA-50820 | Loan Repay | 1,472,262.10 |
Feb 15, 2018 | IDA-50820 | Loan Repay | 1,552,304.40 |
Feb 15, 2018 | IDA-50820 | Int Charges | 346,975.28 |
Feb 15, 2018 | IDA-50820 | Int Charges | 346,975.28 |
Feb 15, 2018 | IDA-50820 | Int Charges | 1,196,077.90 |
Feb 15, 2018 | IDA-50820 | Int Charges | 57,828.86 |
Feb 15, 2018 | IBRD-81470 | Int Charges | 1,078,444.50 |
Feb 15, 2018 | IBRD-81470 | Loan Repay | 2,040,000.00 |
Aug 15, 2017 | IDA-50820 | Int Charges | 12,091.15 |
Aug 15, 2017 | IDA-50820 | Int Charges | 1,215,048.40 |
Aug 15, 2017 | IDA-50820 | Loan Repay | 1,497,782.90 |
Aug 15, 2017 | IDA-50820 | Int Charges | 340,405.20 |
Aug 15, 2017 | IDA-50820 | Int Charges | 340,405.20 |
Aug 15, 2017 | IBRD-81470 | Int Charges | 995,500.00 |
Feb 15, 2017 | IDA-50820 | Int Charges | 314,224.12 |
Feb 15, 2017 | IDA-50820 | Int Charges | 314,224.12 |
Feb 15, 2017 | IBRD-81470 | Int Charges | 925,111.10 |
Feb 15, 2017 | IDA-50820 | Int Charges | 1,207,371.10 |
Feb 15, 2017 | IDA-50820 | Int Charges | 12,285.37 |
Feb 15, 2017 | IDA-50820 | Int Charges | 12,285.37 |
Aug 15, 2016 | IBRD-81470 | Int Charges | 722,944.44 |
Aug 15, 2016 | IDA-50820 | Int Charges | 13,626.97 |
Aug 15, 2016 | IDA-50820 | Int Charges | 337,553.50 |
Aug 15, 2016 | IDA-50820 | Int Charges | 337,553.50 |
Aug 15, 2016 | IDA-50820 | Int Charges | 1,260,199.80 |
Feb 15, 2016 | IBRD-81470 | Int Charges | 546,888.90 |
Feb 15, 2016 | IDA-50820 | Int Charges | 870.10 |
Feb 15, 2016 | IDA-50820 | Int Charges | 870.10 |
Feb 15, 2022 | IDA-50820 | Int Charges | 282,921.56 |
Feb 15, 2022 | IDA-50820 | Int Charges | 282,921.56 |
Aug 15, 2022 | IBRD-81470 | Int Charges | 563,591.80 |
Aug 15, 2022 | IBRD-81470 | Loan Repay | 2,040,000.00 |
Aug 15, 2022 | IDA-50820 | Int Charges | 12,501.53 |
Aug 15, 2022 | IDA-50820 | Loan Repay | 2,810,450.00 |
Aug 15, 2022 | IDA-50820 | Int Charges | 256,134.16 |
Aug 15, 2022 | IDA-50820 | Int Charges | 256,134.16 |
Aug 15, 2022 | IDA-50820 | Int Charges | 956,234.40 |
Feb 15, 2023 | IDA-50820 | Loan Repay | 2,811,681.50 |
Aug 15, 2020 | IDA-50820 | Int Charges | 1,083,354.80 |
Aug 15, 2020 | IDA-50820 | Loan Repay | 35,061.26 |
Aug 15, 2020 | IDA-50820 | Loan Repay | 1,465,190.60 |
Aug 15, 2020 | IDA-50820 | Int Charges | 307,210.66 |
Aug 15, 2020 | IDA-50820 | Int Charges | 307,210.66 |
Aug 15, 2020 | IDA-50820 | Int Charges | 0.01 |
Aug 15, 2020 | IBRD-81470 | Int Charges | 1,085,033.50 |
Aug 15, 2020 | IBRD-81470 | Loan Repay | 2,040,000.00 |
Feb 15, 2021 | IDA-50820 | Int Charges | 64,966.10 |
Feb 15, 2021 | IDA-50820 | Loan Repay | 1,533,318.20 |
Feb 15, 2021 | IDA-50820 | Int Charges | 308,231.84 |
Feb 15, 2021 | IDA-50820 | Int Charges | 308,231.84 |
Feb 15, 2021 | IDA-50820 | Int Charges | 1,144,854.10 |
Feb 15, 2021 | IBRD-81470 | Int Charges | 466,493.16 |
Feb 15, 2021 | IBRD-81470 | Loan Repay | 2,040,000.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2012-06-13 |
Monitoring and Evaluation | Satisfactory | 2012-06-13 |
Overall Implementation Progress (IP) | Satisfactory | 2012-06-13 |
Program Management | Satisfactory | 2012-06-13 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 07-25-2016 |
---|---|
Outcomes | |
Risk to Development Outcome | |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 10-24-2016 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | High | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Satisfactory | N/a |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Increase in generation availability due to market efficiency incentives improves reserve adequacy and supply security. Indicator: hourly operational reserve. | Value | No hourly operational reserve. | End of third operation in programmatic series:Ten | |
Date | December 31, 2008 | April 17, 2010 | December 31, 2012 | |
Comment |
Enhanced transparency in generation contracting and pricing, creating predictability for investors.Indicators: Single Buyer contracts coverage of generation and disclosure of spot market prices. | Value | No contract coverage.No spot market disclosure. | End of third operation in programmatic series:Con | |
Date | December 31, 2008 | April 17, 2010 | December 31, 2012 | |
Comment |
The independence and diversity of electricity generators increases, creating conditions that enable development of effective competition and allow the transition to wholesale competition.Indicator: | Value | Highest proportion of generation owned by a single | End of third operation in programmatic series:Hig | |
Date | December 31, 2008 | April 17, 2010 | December 31, 2012 | |
Comment |
The System and Market Operator provides efficient and non discriminatory services following VCGM rules, codes and regulations.Indicator: audit by independent consultant firm determines compliance of | Value | No audit (because there is no SMO). | End of third operation in programmatic series:Aud | |
Date | December 31, 2008 | April 17, 2010 | December 31, 2012 | |
Comment |
Annual tariff updates approved by MOIT up to 5 percent.Indicator: annual tariff adjustment is approved by March each year. | Value | No annual update. | End of third operation in programmatic series:Ann | |
Date | December 31, 2008 | April 17, 2010 | December 31, 2012 | |
Comment |
Phase out of cross subsidy between different tariff categories.Indicators: level of cross subsidy from industrial and commercial categories reduced at least 50 percent; and subsidies targeted to poo | Value | Cross subsidy of $370 million from industrial and | End of third operation in programmatic series:Cro | |
Date | December 31, 2007 | April 17, 2010 | December 31, 2012 | |
Comment |
Enhanced energy efficiency through legal framework, and adequate monitoring and enforcement mechanisms.Inidcator: energy efficiency target established by law, and MoIT and ERAV have capacity to enfo | Value | No Energy Efficiency Law, and no formal demand sid | End of third operation in programmatic series:Ene | |
Date | December 31, 2008 | April 17, 2010 | December 31, 2012 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Milestones for Policy Area A, Development of Competitive Market:ERAV completes draft Vietnam Competitive Generation Market (VCGM)Rules and submits to MoIT consultation and approval.MoIT issues Ci | Value | No VCGM Rules draft submitted or Grid Code circula | VCGM Rules draft submitted and Grid Code circular | |
Date | April 6, 2010 | April 17, 2010 | June 30, 2011 | |
Comment |
Milestones for Policy Area B, Power Sector Restructuring:EVN submits recommendations on independent generation companies to PrimeMinister.MoIT issues Circular on methodology and procedures to cal | Value | No recommendation on independent generation compan | Recommendation on independent generation companies | |
Date | April 6, 2010 | April 17, 2010 | June 30, 2011 | |
Comment |
Milestones for Policy Area C, Electricity Tariff Reform:Prime Minister Decision to promulgates Regulations on methodology to calculate and procedures for appraisal of market-based electricity prices | Value | No regulations on methodology for market based pri | Regulation on methodology for market based pricing | |
Date | April 6, 2010 | April 17, 2010 | June 30, 2011 | |
Comment |
Milestones for Policy Area D, Improving Demand Side Energy Efficiency:MoIT submits draft Energy Efficiency Law to Prime Minister.ERAV completes load research and drafts procedures for PCs' periodi | Value | Draft Energy Efficiency Law not submitted.Load re | Draft Energy Efficiency Law submitted by MoIT to P | |
Date | April 6, 2010 | April 17, 2010 | June 30, 2011 | |
Comment |