Skip to Main Navigation

Economic Revitalization of Khyber Pakhtunkhwa Project

Development Objective

To support the Government of Pakistan in creating sustainable employment opportunities and developing the selected economic sectors in Khyber Pakhtunkhwa province.

Key Details

Project Details

  • P124268

  • Closed

  • Kiran Afzal

  • Government of Pakistan

  • Pakistan

  • January 1, 2011

  • (as of board presentation)

    August 22, 2011

  • October 11, 2011

  • US$ 20.00 million

  • Department of Industries, Commerce and Technical Education,Project Management Unit,Small and Medium Enterprise Development Authority (SMEDA)

  • South Asia

  • 2012

  • US$ 39.00 million

  • B

  • N/A

  • June 30, 2022

  • BANK APPROVED

  • June 7, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
MDTF for Crisi Affected Areas of NWFP/FATA/Balochistan 39.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 39.00
Total Project Cost** 20.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Satisfactory 2021-12-23
Overall Implementation Progress (IP) Satisfactory 2021-12-23
Progress towards achievement of PDO Satisfactory 2021-12-23
Project Management Satisfactory 2021-12-23
Financial Management Satisfactory 2021-12-23
Monitoring and Evaluation Satisfactory 2021-12-23

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-07-2024
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 10-23-2024PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Direct jobs restored and created by the enterprises supported through the Project.Value0.008000.000.00
    DateOctober 11, 2011December 31, 2021
    Comment
  • Direct jobs restored and created for women through the ProjectValue0.00138.000.00
    DateOctober 11, 2011January 31, 2013
    Comment
  • Matching grants beneficiaries operational and productive at the completion of the Project.Value0.0060.000.00
    DateOctober 11, 2011December 31, 2021
    Comment
  • SME beneficiaries of the MGs, of which at least 5 percent are owned/managed by women entrepreneurs.Value0.00850.000.00
    DateOctober 11, 2011December 31, 2021
    Comment
  • Tourist facilities and sites supported through the projectValue0.000.000.00
    DateOctober 11, 2011December 31, 2021
    Comment
  • Investment promotion authorities supported in KP provinceValue2.000.005.00
    DateFebruary 28, 2020December 31, 2021February 28, 2020
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • SME Rehabilitation Support provided through the MGs.Value0.002386.002200.00
    DateOctober 11, 2011June 30, 2022December 31, 2021
    Comment
  • Re-connect Pakistan (web tools for Diaspora) operationalValue0.0042683.0010000.00
    DateOctober 11, 2011June 30, 2022December 31, 2021
    Comment
  • Officials of the Government of KP attend training and study tours in technical areas, including (i) trade and commerce, (ii) tourism and destination management and (iii) project managementValue0.00104.0070.00
    DateOctober 11, 2011June 30, 2022December 31, 2021
    Comment
  • Micro-enterprises, workers (including women) and SMEs trained through the ProjectValue0.002935.001000.00
    DateOctober 11, 2011June 30, 2022December 31, 2021
    Comment
  • SME beneficiaries of the up-gradation MGs.Value0.00561.00450.00
    DateOctober 11, 2011June 30, 2022December 31, 2021
    Comment
  • Diaspora outreach program implemented through investment mobilization eventsValue0.009.007.00
    DateOctober 11, 2011June 30, 2022December 31, 2021
    Comment
  • Scalable projects and activities identified in the competitive sectors of KPValue0.007.006.00
    DateOctober 11, 2011June 30, 2022December 31, 2021
    Comment
  • Machinery pools/common facilities supported by the Project.Value0.006.006.00
    DateOctober 11, 2011June 30, 2022December 31, 2021
    Comment
  • SME beneficiaries satisfied with the processing of the MGs under the AF of Project.Value0.0080.0080.00
    DateOctober 11, 2011June 30, 2022December 31, 2021
    Comment
  • Medical equipment and supplies for COVID-19 pandemic response provided to Health Department of KPValue150.001530.00200.00
    DateMarch 2, 2020June 30, 2022December 31, 2021
    Comment