Emergency Monrovia Urban Sanitation Project (EMUS) - Additional Financing

Development Objective

To increase access to solid waste collection service in Monrovia

Key Details

Project Details

  • P124664

  • Closed

  • Kwabena Amankwah-Ayeh

  • N/A

  • Liberia

  • April 6, 2011

  • (as of board presentation)

    April 7, 2011

  • N/A

  • US$ 4.00 million

  • B

  • Not Applicable

  • December 30, 2016

  • BANK APPROVED

  • P115664

  • August 5, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 4.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 4.00
IBRD + IDA Commitment 4.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 4.00

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Satisfactory 2013-12-02
Monitoring and Evaluation Satisfactory 2013-12-02
Counterpart Funding Satisfactory 2013-12-02
Overall Implementation Progress (IP) Satisfactory 2013-12-02
Progress towards achievement of PDO Satisfactory 2013-12-02
Procurement Satisfactory 2013-12-02
Project Management Satisfactory 2013-12-02

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Female beneficiariesValue0.00152619.00180000.00
    DateMarch 31, 2013December 31, 2013
    Comment
  • Number of people in urban areas provided with access to regular solid waste collection under the projectValue0.00305238.00360000.00
    DateMarch 31, 2013December 31, 2013
    CommentBased on 0.63 kg per capital per day production. This production may have been over estimated since the target of householdsserviced has been exceeded
  • Direct project beneficiariesValue0.00305238.00360000.00
    DateMarch 31, 2013December 31, 2013
    CommentBased on 0.63 kg per capital per day production. This production may have been over estimated since the target of householdsserviced has been exceeded

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • MCC staff trained in financial management i.e. revenue administration, budgeting, accounting (% of relevant staff)Value0.0095.0080.00
    DateMarch 31, 2013December 31, 2013
    CommentTraining in Tally and Bank Reconciliation on-going
  • Landfill disposal cell volumeValue0.00540000.00500000.00
    DateMarch 31, 2013December 31, 2013
    CommentLandfill cells completed and formally handed over by Zoomlion
  • Volume of waste collected, percent of total waste produced (tons, %)Value0.00192.30330.00
    DateMarch 31, 2013December 31, 2013
    CommentCollection data reflects the volume of waste collected daily over the period with the exception of Sundays. As indicated above, theproduction may have been over estimated since the target of households serviced has been exceeded
  • Vehicle turn-around timeValue0.000.501.00
    DateMarch 31, 2013December 31, 2013
    CommentData from SE
  • Targeted households which dump domestic waste in non-designated areasValue0.0045.0040.00
    DateMarch 31, 2013December 31, 2013
    CommentReport for Year II Survey not yet submitted by firm
  • Transfer stations builtValue0.002.002.00
    DateMarch 31, 2013December 31, 2013
    CommentFiamah and Stockton Creek TSs completed;
  • SMEs provided with trainingValue0.0033.0010.00
    DateMarch 31, 2013December 31, 2013
    CommentCBEs trained in Report writing, small business management, Record Keeping, Waste Auditing and Analysis
  • People reached by awareness campaignsValue0.0062.5060.00
    DateMarch 31, 2013December 31, 2013
    CommentYear 2 Survey Report yet to be submitted
  • Households with access to door to door solid waste collectionValue0.0016943.0010000.00
    DateMarch 31, 2013December 31, 2013
    CommentCBEs keeping up with contract conditions in terms of timeliness of reporting
  • Special Municipal Solid Waste account for revenue from solid waste established (yes/noValueNoYesYes
    DateMarch 31, 2013December 31, 2013
    CommentTotal Deposit of $226,431.60 USD and $25,291,839.36 LRD in Solid Waste Transitory Account as of March 29,2013