Financier | Commitments |
---|---|
GLOBAL ENVIRONMENT - Associated IDA Fund | 50.30 |
Global Environment Facility (GEF) | 3.50 |
P124812
Closed
Berengere Prince , Nyaneba Nkrumah, Jingjie Chu
N/A
March 24, 2011
(as of board presentation)
July 14, 2011
June 12, 2012
US$ 53.80 million
N/A
2012
US$ 3.50 million
B
October 16, 2023
September 28, 2018
BANK APPROVED
Financier | Commitments |
---|---|
GLOBAL ENVIRONMENT - Associated IDA Fund | 50.30 |
Global Environment Facility (GEF) | 3.50 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 3.50 |
Total Project Cost** | 53.80 |
Name | Review | Date |
---|---|---|
Project Management | Moderately Unsatisfactory | 2018-11-02 |
Procurement | Moderately Unsatisfactory | 2018-11-02 |
Financial Management | Moderately Unsatisfactory | 2018-11-02 |
Monitoring and Evaluation | Moderately Satisfactory | 2018-11-02 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2018-11-02 |