Financier | Commitments |
---|---|
MDTF for Crisi Affected Areas of NWFP/FATA/Balochistan | 7.00 |
P125414
Closed
Shahnaz Arshad
Economic Affairs Division
April 12, 2012
(as of board presentation)
April 12, 2012
April 12, 2012
US$ 7.00 million
FATA Secretariat
2012
US$ 7.00 million
B
Not Applicable
September 30, 2015
BANK APPROVED
August 15, 2024
Financier | Commitments |
---|---|
MDTF for Crisi Affected Areas of NWFP/FATA/Balochistan | 7.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 7.00 |
Total Project Cost** | 7.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2015-10-07 |
Project Management | Moderately Satisfactory | 2015-10-07 |
Procurement | Satisfactory | 2015-10-07 |
Financial Management | Satisfactory | 2015-10-07 |
Monitoring and Evaluation | Satisfactory | 2015-10-07 |
Overall Implementation Progress (IP) | Satisfactory | 2015-10-07 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 04-24-2016 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Substantial |
Bank Performance | Substantial |
Borrower Performance | Substantial |
Government Performance | Moderately Satisfactory |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 03-16-2017 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | Substantial | N/a |
Bank Performance | Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Satisfactory | N/a |
Icr Quality | High | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of project beneficiaries satisfied with quality of project provided priority urban services. | Value | 0.00 | 0.00 | 60.00 |
Date | April 12, 2012 | September 30, 2015 | June 30, 2015 | |
Comment |
Percentage of Khar population who perceive that delivery of priority urban services is being improved through the project. | Value | 0.00 | 0.00 | 30.00 |
Date | April 12, 2012 | September 30, 2015 | June 30, 2015 | |
Comment |
Framework for improved urban spatial planning, investment decision-making, and service improvement planning, developed for FATA, and piloted in selected towns. | Value | Weak spatial and investments planning, and service | Urban structure plans, service coverage maps, and | Urban structure plans, service coverage maps, and |
Date | April 12, 2012 | September 30, 2015 | June 30, 2015 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
New (or restored) piped household water connections that are resulting from the project intervention. | Value | 0.00 | 2200.00 | 900.00 |
Date | April 12, 2012 | September 30, 2015 | June 30, 2015 | |
Comment |
Urban roads rehabilitated under the project | Value | 0.00 | 4.35 | 2.30 |
Date | April 12, 2012 | September 30, 2015 | June 30, 2015 | |
Comment |
Number of street lights installed/restored in Khar. | Value | 0.00 | 522.00 | 450.00 |
Date | April 12, 2012 | September 30, 2015 | June 30, 2015 | |
Comment |
Number of people in urban areas provided with access to regular solid waste collection under the project | Value | 0.00 | 30000.00 | 1000.00 |
Date | April 12, 2012 | September 30, 2015 | June 30, 2015 | |
Comment |
Direct project beneficiaries | Value | 0.00 | 40000.00 | 20000.00 |
Date | April 12, 2012 | September 30, 2015 | June 30, 2015 | |
Comment |
Number of urban centers in FATA with structure plans developed under the project. | Value | 0.00 | 5.00 | 3.00 |
Date | April 12, 2012 | September 30, 2015 | June 30, 2015 | |
Comment |
Number of urban centers in FATA with existing service delivery coverage and physical infrastructure mapped under the project. | Value | 0.00 | 5.00 | 3.00 |
Date | April 12, 2012 | September 30, 2015 | June 30, 2015 | |
Comment |
Number of urban centers in FATA with demand-based priority investments for service delivery improvement identified under the project. | Value | 0.00 | 5.00 | 3.00 |
Date | April 12, 2012 | September 30, 2015 | June 30, 2015 | |
Comment |
Female beneficiaries | Value | 0.00 | 50.00 | 50.00 |
Date | April 12, 2012 | September 30, 2015 | June 30, 2015 | |
Comment |