Financier | Commitments |
---|---|
Borrower/Recipient | 72.80 |
Liberia Reconstruction Trust Fund | 108.90 |
IDA Credit | 67.70 |
P125574
Closed
Tojoarofenitra Ramanankirahina , Negede Lewi Teklemariam, Ajara Ceesay
Ministry Of Finance
March 21, 2011
(as of board presentation)
June 7, 2011
October 13, 2011
US$ 249.40 million
Infrastructure Implementation Unit
2011
US$ 176.60 million
B
Not Applicable
June 30, 2024
BANK APPROVED
February 12, 2024
Financier | Commitments |
---|---|
Borrower/Recipient | 72.80 |
Liberia Reconstruction Trust Fund | 108.90 |
IDA Credit | 67.70 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 67.70 |
IBRD + IDA Commitment | 67.70 |
Lending Instrument | |
---|---|
Grant Amount | 108.90 |
Total Project Cost** | 249.40 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Nov 15, 2014 | IDA-49500 | Int Charges | 388.51 |
Sep 17, 2013 | IDA-49500 | Loan Disb | 1,653,922.50 |
Nov 19, 2013 | IDA-49500 | Int Charges | 299.89 |
Nov 19, 2013 | IDA-49500 | Int Charges | 299.89 |
Nov 19, 2013 | IDA-49500 | Int Charges | 29,827.14 |
Nov 19, 2013 | IDA-49500 | Int Charges | 29,827.14 |
Oct 9, 2013 | IDA-49500 | Loan Disb | 622,499.50 |
Jun 20, 2014 | IDA-49500 | Loan Disb | 606,326.50 |
Jun 11, 2014 | IDA-49500 | Int Charges | 41,335.64 |
Jun 11, 2014 | IDA-49500 | Int Charges | 41,335.64 |
Jun 11, 2014 | IDA-49500 | Int Charges | 2,710.86 |
Jun 11, 2014 | IDA-49500 | Int Charges | 2,710.86 |
May 15, 2017 | IDA-51670 | Int Charges | 1,767.65 |
May 15, 2017 | IDA-51670 | Int Charges | 1,767.65 |
Apr 18, 2017 | IDA-51670 | Loan Disb | 304,320.84 |
Jun 1, 2017 | IDA-49500 | Int Charges | 161,754.38 |
Jun 1, 2017 | IDA-49500 | Int Charges | 161,754.38 |
Jun 1, 2017 | IDA-51670 | Int Charges | 76,229.92 |
Jun 1, 2017 | IDA-51670 | Int Charges | 76,229.92 |
Mar 9, 2017 | IDA-49500 | Loan Disb | 2,690,885.20 |
Sep 5, 2017 | IDA-49500 | Loan Disb | 1,000,000.00 |
Nov 16, 2017 | IDA-51670 | Int Charges | 2,227.40 |
Nov 16, 2017 | IDA-51670 | Int Charges | 2,227.40 |
Nov 16, 2017 | IDA-51670 | Int Charges | 88,588.29 |
Nov 16, 2017 | IDA-51670 | Int Charges | 88,588.29 |
Nov 16, 2017 | IDA-49500 | Int Charges | 4,425.09 |
Nov 16, 2017 | IDA-49500 | Int Charges | 4,425.09 |
Nov 16, 2017 | IDA-49500 | Int Charges | 185,356.12 |
Nov 16, 2017 | IDA-49500 | Int Charges | 185,356.12 |
Sep 5, 2017 | IDA-51670 | Loan Disb | 1,996,687.00 |
Sep 6, 2017 | IDA-51670 | Loan Disb | 304,320.84 |
Dec 7, 2016 | IDA-49500 | Loan Disb | 669,441.10 |
May 31, 2016 | IDA-51670 | Loan Disb | 747,001.94 |
May 15, 2016 | IDA-49500 | Int Charges | 107,424.93 |
May 15, 2016 | IDA-49500 | Int Charges | 107,424.93 |
May 15, 2016 | IDA-51670 | Int Charges | 22,595.47 |
May 15, 2016 | IDA-51670 | Int Charges | 22,595.47 |
May 31, 2016 | IDA-49500 | Loan Disb | 973,826.70 |
May 15, 2016 | IDA-49500 | Int Charges | 551.93 |
Nov 21, 2023 | IDA-51670 | Int Charges | 119,850.66 |
Dec 15, 2023 | IDA-60370 | Loan Repay | 0.01 |
Dec 15, 2023 | IDA-60370 | Loan Repay | 625,000.00 |
Dec 15, 2023 | IDA-60370 | Int Charges | 813.54 |
Dec 15, 2023 | IDA-60370 | Int Charges | 813.54 |
Dec 15, 2023 | IDA-60370 | Int Charges | 278,677.44 |
Dec 15, 2023 | IDA-60370 | Int Charges | 278,677.44 |
Jun 12, 2023 | IDA-51670 | Loan Repay | 439,830.60 |
Jun 10, 2024 | IDA-51670 | Loan Disb | 508,251.10 |
Nov 24, 2023 | IDA-49500 | Int Charges | 319.71 |
Nov 24, 2023 | IDA-49500 | Int Charges | 319.71 |
Nov 24, 2023 | IDA-51670 | Int Charges | 244.78 |
Nov 24, 2023 | IDA-51670 | Int Charges | 244.78 |
Jan 9, 2024 | IDA-51670 | Loan Disb | 1,600,382.10 |
Jan 9, 2024 | IDA-51670 | Loan Disb | 1,016,502.20 |
Jul 15, 2024 | IDA-51670 | Loan Disb | 1,389,715.40 |
Aug 14, 2024 | IDA-60370 | Int Charges | 274,239.90 |
Aug 14, 2024 | IDA-60370 | Int Charges | 274,239.90 |
Jan 9, 2020 | IDA-51670 | Int Charges | 116,119.57 |
Jan 9, 2020 | IDA-51670 | Int Charges | 116,119.57 |
Jan 9, 2020 | IDA-49500 | Int Charges | 206,791.84 |
Jan 9, 2020 | IDA-49500 | Int Charges | 206,791.84 |
Mar 31, 2020 | IDA-49500 | Loan Disb | 363,586.20 |
Dec 2, 2019 | IDA-60370 | Loan Disb | 1,499,291.80 |
Jan 30, 2020 | IDA-60370 | Loan Disb | 304,158.12 |
Jun 19, 2019 | IDA-49500 | Loan Disb | 1,000,000.00 |
Jun 19, 2019 | IDA-51670 | Loan Disb | 2,095,855.40 |
Jun 28, 2019 | IDA-60370 | Loan Disb | 7,329,567.00 |
Apr 9, 2019 | IDA-51670 | Loan Disb | 304,320.84 |
Apr 1, 2019 | IDA-49500 | Loan Disb | 609,686.94 |
May 29, 2019 | IDA-49500 | Int Charges | 200,740.10 |
May 29, 2019 | IDA-49500 | Int Charges | 200,740.10 |
May 29, 2019 | IDA-51670 | Int Charges | 106,375.35 |
May 29, 2019 | IDA-51670 | Int Charges | 106,375.35 |
May 21, 2019 | IDA-51670 | Loan Disb | 1,447,129.80 |
May 15, 2019 | IDA-51670 | Int Charges | 1,342.74 |
May 15, 2019 | IDA-51670 | Int Charges | 1,342.74 |
May 15, 2019 | IDA-49500 | Int Charges | 2,708.45 |
May 15, 2019 | IDA-49500 | Int Charges | 2,708.45 |
Sep 6, 2019 | IDA-60370 | Loan Disb | 1,089,038.50 |
Nov 7, 2019 | IDA-60370 | Loan Disb | 304,320.84 |
Nov 15, 2019 | IDA-51670 | Int Charges | 866.94 |
Sep 12, 2018 | IDA-49500 | Loan Disb | 2,000,000.00 |
Jun 25, 2018 | IDA-49500 | Loan Disb | 237,147.67 |
Jun 25, 2018 | IDA-51670 | Loan Disb | 304,320.84 |
May 15, 2018 | IDA-49500 | Int Charges | 1,960.77 |
May 15, 2018 | IDA-49500 | Int Charges | 1,960.77 |
May 24, 2018 | IDA-49500 | Int Charges | 188,219.98 |
May 24, 2018 | IDA-49500 | Int Charges | 188,219.98 |
May 24, 2018 | IDA-51670 | Int Charges | 94,581.93 |
May 24, 2018 | IDA-51670 | Int Charges | 94,581.93 |
May 15, 2018 | IDA-51670 | Int Charges | 938.28 |
May 15, 2018 | IDA-51670 | Int Charges | 938.28 |
Nov 15, 2018 | IDA-51670 | Int Charges | 2,302.03 |
Nov 15, 2018 | IDA-51670 | Int Charges | 2,302.03 |
Nov 15, 2018 | IDA-49500 | Int Charges | 3,690.39 |
Nov 15, 2018 | IDA-49500 | Int Charges | 3,690.39 |
Dec 6, 2018 | IDA-49500 | Int Charges | 191,826.05 |
Dec 6, 2018 | IDA-49500 | Int Charges | 191,826.05 |
Dec 6, 2018 | IDA-51670 | Int Charges | 98,274.52 |
Dec 6, 2018 | IDA-51670 | Int Charges | 98,274.52 |
Nov 7, 2018 | IDA-51670 | Loan Disb | 304,320.84 |
Feb 13, 2019 | IDA-49500 | Loan Disb | 466,730.75 |
Feb 14, 2019 | IDA-49500 | Loan Disb | 511,119.03 |
Feb 16, 2018 | IDA-49500 | Loan Disb | 202,482.83 |
Feb 22, 2018 | IDA-51670 | Loan Disb | 304,320.84 |
Feb 22, 2018 | IDA-51670 | Loan Disb | 304,320.84 |
Mar 23, 2018 | IDA-49500 | Loan Disb | 416,842.22 |
Mar 23, 2018 | IDA-49500 | Loan Disb | 392,658.62 |
Jun 29, 2018 | IDA-51670 | Loan Disb | 495,523.00 |
Jun 29, 2018 | IDA-49500 | Loan Disb | 342,120.00 |
Jun 13, 2018 | IDA-51670 | Loan Disb | 304,320.84 |
May 14, 2018 | IDA-49500 | Loan Disb | 400,366.38 |
May 14, 2018 | IDA-49500 | Loan Disb | 394,084.30 |
Sep 10, 2018 | IDA-51670 | Loan Disb | 2,261,355.50 |
Sep 6, 2018 | IDA-49500 | Loan Disb | 416,035.97 |
May 15, 2017 | IDA-49500 | Int Charges | 3,634.18 |
May 15, 2017 | IDA-49500 | Int Charges | 3,634.18 |
May 8, 2017 | IDA-49500 | Loan Disb | 511,125.00 |
May 15, 2022 | IDA-49500 | Int Charges | 705.02 |
May 15, 2022 | IDA-49500 | Int Charges | 705.02 |
May 15, 2022 | IDA-49500 | Int Charges | 212,931.08 |
May 15, 2022 | IDA-49500 | Int Charges | 212,931.08 |
May 15, 2022 | IDA-49500 | Loan Repay | 10,703.73 |
May 15, 2022 | IDA-49500 | Loan Repay | 562,858.10 |
May 15, 2022 | IDA-51670 | Int Charges | 1,555.99 |
May 15, 2022 | IDA-51670 | Int Charges | 116,120.71 |
Feb 16, 2021 | IDA-49500 | Loan Disb | 450,915.60 |
Feb 16, 2021 | IDA-51670 | Loan Disb | 334,018.97 |
Nov 15, 2020 | IDA-51670 | Int Charges | 118,656.64 |
Nov 15, 2020 | IDA-51670 | Int Charges | 118,656.64 |
Nov 15, 2020 | IDA-51670 | Int Charges | 1,041.42 |
Nov 15, 2020 | IDA-51670 | Int Charges | 1,041.42 |
Nov 15, 2020 | IDA-49500 | Int Charges | 216,402.31 |
Nov 15, 2020 | IDA-49500 | Int Charges | 216,402.31 |
Dec 21, 2020 | IDA-60370 | Loan Disb | 506,478.25 |
May 15, 2015 | IDA-49500 | Int Charges | 4,482.68 |
May 15, 2015 | IDA-49500 | Int Charges | 4,482.68 |
May 15, 2015 | IDA-49500 | Int Charges | 81,099.57 |
May 15, 2015 | IDA-49500 | Int Charges | 81,099.57 |
May 14, 2015 | IDA-49500 | Loan Disb | 1,281,138.10 |
Nov 15, 2015 | IDA-49500 | Int Charges | 93,891.30 |
Nov 15, 2015 | IDA-49500 | Int Charges | 93,891.30 |
Jul 13, 2015 | IDA-49500 | Loan Disb | 979,416.90 |
Nov 20, 2014 | IDA-49500 | Int Charges | 49,080.72 |
Nov 20, 2014 | IDA-49500 | Int Charges | 49,080.72 |
Oct 6, 2014 | IDA-49500 | Loan Disb | 4,488,350.50 |
Oct 8, 2014 | IDA-49500 | Loan Disb | 1,299,243.60 |
Sep 30, 2014 | IDA-49500 | Loan Disb | 1,212,653.00 |
Jul 22, 2013 | IDA-49500 | Loan Disb | 1,792,804.60 |
Jan 16, 2015 | IDA-49500 | Loan Disb | 1,569,878.80 |
Nov 15, 2014 | IDA-49500 | Int Charges | 388.51 |
May 15, 2021 | IDA-49500 | Int Charges | 183,035.95 |
May 15, 2021 | IDA-49500 | Int Charges | 495.55 |
May 15, 2021 | IDA-49500 | Int Charges | 495.55 |
May 15, 2021 | IDA-49500 | Int Charges | 37,465.34 |
May 15, 2021 | IDA-49500 | Int Charges | 37,465.34 |
May 15, 2021 | IDA-51670 | Int Charges | 272.26 |
May 15, 2021 | IDA-51670 | Int Charges | 272.26 |
May 15, 2021 | IDA-51670 | Int Charges | 121,309.13 |
May 15, 2021 | IDA-51670 | Int Charges | 121,309.13 |
Nov 15, 2020 | IDA-49500 | Int Charges | 1,454.70 |
Nov 15, 2020 | IDA-49500 | Int Charges | 1,454.70 |
May 15, 2021 | IDA-49500 | Int Charges | 183,035.95 |
Mar 26, 2021 | IDA-60370 | Loan Disb | 501,868.22 |
May 7, 2021 | IDA-49500 | Loan Disb | 471,878.40 |
May 4, 2021 | IDA-60370 | Loan Disb | 564,210.80 |
Jun 7, 2021 | IDA-49500 | Loan Disb | 585,694.10 |
Jan 16, 2020 | IDA-60370 | Loan Disb | 1,451,218.80 |
May 21, 2020 | IDA-49500 | Int Charges | 926.03 |
May 21, 2020 | IDA-49500 | Int Charges | 926.03 |
May 21, 2020 | IDA-49500 | Int Charges | 207,470.14 |
May 21, 2020 | IDA-49500 | Int Charges | 207,470.14 |
May 7, 2020 | IDA-49500 | Loan Disb | 433,509.00 |
May 21, 2020 | IDA-51670 | Int Charges | 520.01 |
May 21, 2020 | IDA-51670 | Int Charges | 115,409.97 |
May 21, 2020 | IDA-51670 | Int Charges | 115,409.97 |
May 21, 2020 | IDA-51670 | Int Charges | 520.01 |
Aug 3, 2020 | IDA-60370 | Loan Disb | 304,320.84 |
Jul 20, 2020 | IDA-60370 | Loan Disb | 494,430.97 |
Jul 20, 2020 | IDA-60370 | Loan Disb | 1,416,293.60 |
Jun 15, 2020 | IDA-60370 | Int Charges | 1,224.94 |
Jun 15, 2020 | IDA-60370 | Int Charges | 1,224.94 |
Jun 15, 2020 | IDA-60370 | Int Charges | 117,684.82 |
Jun 15, 2020 | IDA-60370 | Int Charges | 117,684.82 |
Oct 30, 2020 | IDA-60370 | Loan Disb | 1,795,925.60 |
Dec 15, 2020 | IDA-60370 | Int Charges | 106,213.48 |
Dec 15, 2020 | IDA-60370 | Int Charges | 106,213.48 |
Dec 15, 2020 | IDA-60370 | Int Charges | 26,298.53 |
Dec 15, 2020 | IDA-60370 | Int Charges | 26,298.53 |
Nov 15, 2019 | IDA-51670 | Int Charges | 866.94 |
Jun 18, 2024 | IDA-51670 | Int Charges | 54.35 |
Jun 18, 2024 | IDA-51670 | Int Charges | 54.35 |
Jun 18, 2024 | IDA-51670 | Int Charges | 132,186.50 |
Jun 18, 2024 | IDA-51670 | Int Charges | 132,186.50 |
Jun 18, 2024 | IDA-51670 | Int Charges | 6,158.75 |
Jun 18, 2024 | IDA-49500 | Int Charges | 70.97 |
Jun 18, 2024 | IDA-49500 | Int Charges | 70.97 |
Jun 18, 2024 | IDA-49500 | Int Charges | 202,296.92 |
Jun 18, 2024 | IDA-49500 | Int Charges | 202,296.92 |
May 22, 2024 | IDA-51670 | Loan Disb | 819,160.10 |
Jun 18, 2024 | IDA-49500 | Loan Repay | 567,851.10 |
May 6, 2024 | IDA-51670 | Loan Disb | 508,941.30 |
May 8, 2017 | IDA-60370 | Loan Commitment | 40,000,000.00 |
Jun 7, 2011 | IDA-49500 | Loan Commitment | 67,700,000.00 |
Sep 20, 2012 | IDA-51670 | Loan Commitment | 50,000,000.00 |
Jun 12, 2023 | IDA-51670 | Int Charges | 54.43 |
Jun 12, 2023 | IDA-51670 | Int Charges | 127,192.16 |
Jun 12, 2023 | IDA-51670 | Int Charges | 127,192.16 |
Jun 12, 2023 | IDA-49500 | Int Charges | 5,760.38 |
Jun 12, 2023 | IDA-49500 | Int Charges | 5,760.38 |
Jun 12, 2023 | IDA-49500 | Loan Repay | 574,445.44 |
Jun 12, 2023 | IDA-49500 | Int Charges | 68.40 |
Jun 12, 2023 | IDA-49500 | Int Charges | 68.40 |
Jun 12, 2023 | IDA-49500 | Int Charges | 207,950.56 |
Jun 12, 2023 | IDA-49500 | Int Charges | 207,950.56 |
Jun 12, 2023 | IDA-51670 | Int Charges | 5,346.73 |
Jun 12, 2023 | IDA-51670 | Int Charges | 5,346.73 |
Nov 21, 2023 | IDA-49500 | Int Charges | 1,004.32 |
Nov 21, 2023 | IDA-49500 | Int Charges | 1,004.32 |
Nov 21, 2023 | IDA-49500 | Loan Repay | 574,682.50 |
Nov 21, 2023 | IDA-49500 | Int Charges | 323.26 |
Nov 21, 2023 | IDA-49500 | Int Charges | 323.26 |
Nov 21, 2023 | IDA-49500 | Int Charges | 197,964.16 |
Nov 21, 2023 | IDA-49500 | Int Charges | 197,964.16 |
Nov 21, 2023 | IDA-51670 | Int Charges | 119,850.66 |
Nov 21, 2023 | IDA-51670 | Int Charges | 734.13 |
Nov 21, 2023 | IDA-51670 | Int Charges | 734.13 |
Nov 21, 2023 | IDA-51670 | Loan Repay | 440,012.10 |
Nov 21, 2023 | IDA-51670 | Int Charges | 247.50 |
Nov 21, 2023 | IDA-51670 | Int Charges | 247.50 |
May 15, 2016 | IDA-49500 | Int Charges | 551.93 |
Feb 14, 2017 | IDA-51670 | Loan Disb | 935,147.56 |
Feb 14, 2017 | IDA-49500 | Loan Disb | 669,441.10 |
Nov 28, 2016 | IDA-49500 | Loan Disb | 1,462,181.60 |
Nov 28, 2016 | IDA-49500 | Loan Disb | 1,861,471.60 |
Jul 29, 2016 | IDA-51670 | Loan Disb | 747,001.94 |
Jul 29, 2016 | IDA-51670 | Loan Disb | 303,940.44 |
Nov 22, 2016 | IDA-51670 | Loan Disb | 2,176,264.00 |
Aug 31, 2016 | IDA-49500 | Loan Disb | 2,760,498.80 |
Nov 15, 2016 | IDA-51670 | Int Charges | 1,062.45 |
Nov 15, 2016 | IDA-51670 | Int Charges | 1,062.45 |
Nov 15, 2016 | IDA-51670 | Int Charges | 64,505.53 |
Nov 15, 2016 | IDA-51670 | Int Charges | 64,505.53 |
Nov 15, 2016 | IDA-49500 | Int Charges | 2,494.41 |
Nov 15, 2016 | IDA-49500 | Int Charges | 2,494.41 |
Nov 21, 2016 | IDA-51670 | Loan Disb | 304,320.84 |
Jan 25, 2017 | IDA-51670 | Loan Disb | 304,320.84 |
Jun 6, 2016 | IDA-51670 | Loan Disb | 2,366,729.50 |
Nov 15, 2016 | IDA-49500 | Int Charges | 132,309.22 |
Nov 15, 2016 | IDA-49500 | Int Charges | 132,309.22 |
Nov 15, 2015 | IDA-49500 | Int Charges | 2,776.23 |
Nov 15, 2015 | IDA-49500 | Int Charges | 2,776.23 |
Jul 29, 2015 | IDA-49500 | Loan Disb | 445,189.50 |
Dec 2, 2015 | IDA-49500 | Loan Disb | 764,451.90 |
Sep 15, 2015 | IDA-49500 | Loan Disb | 1,150,798.00 |
Dec 2, 2015 | IDA-49500 | Loan Disb | 901,153.25 |
Sep 15, 2015 | IDA-49500 | Loan Disb | 766,782.50 |
Feb 17, 2016 | IDA-51670 | Loan Disb | 3,834,692.00 |
Apr 8, 2016 | IDA-49500 | Loan Disb | 1,613,813.60 |
Feb 16, 2016 | IDA-51670 | Loan Disb | 5,835,867.50 |
Feb 16, 2016 | IDA-51670 | Loan Disb | 2,662,560.80 |
Apr 28, 2016 | IDA-51670 | Loan Disb | 1,947,284.60 |
Aug 23, 2016 | IDA-49500 | Loan Disb | 2,089,362.90 |
Aug 2, 2016 | IDA-49500 | Loan Disb | 2,624,573.20 |
Jun 30, 2016 | IDA-49500 | Loan Disb | 1,582,787.10 |
Jul 22, 2014 | IDA-49500 | Loan Disb | 606,326.50 |
Aug 25, 2014 | IDA-49500 | Loan Disb | 3,636,201.80 |
Jul 29, 2019 | IDA-60370 | Loan Disb | 304,320.84 |
Jan 9, 2020 | IDA-60370 | Int Charges | 75,511.23 |
Jan 9, 2020 | IDA-60370 | Int Charges | 75,511.23 |
Nov 15, 2019 | IDA-49500 | Int Charges | 1,508.29 |
Nov 15, 2019 | IDA-49500 | Int Charges | 1,508.29 |
Aug 12, 2019 | IDA-49500 | Loan Disb | -466,730.75 |
Aug 12, 2019 | IDA-60370 | Loan Disb | 466,730.75 |
Aug 12, 2019 | IDA-51670 | Loan Disb | -1,447,129.80 |
Aug 12, 2019 | IDA-60370 | Loan Disb | 1,447,129.80 |
Aug 22, 2019 | IDA-60370 | Loan Disb | 1,870,747.90 |
Aug 22, 2019 | IDA-60370 | Loan Disb | 834,774.06 |
Aug 14, 2024 | IDA-60370 | Loan Repay | 625,000.00 |
Nov 15, 2022 | IDA-60370 | Loan Disb | 1,200,000.00 |
Nov 15, 2022 | IDA-49500 | Loan Repay | 26,863.05 |
Dec 15, 2022 | IDA-60370 | Int Charges | 4,163.18 |
Dec 15, 2022 | IDA-60370 | Int Charges | 4,163.18 |
Dec 15, 2022 | IDA-60370 | Int Charges | 271,516.90 |
Dec 15, 2022 | IDA-60370 | Int Charges | 271,516.90 |
Sep 26, 2022 | IDA-60370 | Loan Disb | 631,717.10 |
Jul 18, 2023 | IDA-60370 | Loan Repay | 625,000.00 |
Jul 18, 2023 | IDA-60370 | Int Charges | 1,420.00 |
Jul 18, 2023 | IDA-60370 | Int Charges | 1,420.00 |
Jul 18, 2023 | IDA-60370 | Int Charges | 283,114.90 |
Jul 18, 2023 | IDA-60370 | Int Charges | 283,114.90 |
Jun 12, 2023 | IDA-51670 | Int Charges | 54.43 |
Dec 6, 2021 | IDA-60370 | Loan Disb | 576,485.10 |
May 25, 2022 | IDA-60370 | Loan Disb | 964,516.40 |
May 25, 2022 | IDA-60370 | Loan Disb | 1,201,476.60 |
May 25, 2022 | IDA-60370 | Loan Disb | 1,553,665.90 |
May 25, 2022 | IDA-60370 | Loan Disb | 600,863.94 |
May 25, 2022 | IDA-60370 | Loan Disb | 956,755.44 |
Mar 10, 2022 | IDA-60370 | Loan Disb | 1,443,945.20 |
Mar 10, 2022 | IDA-60370 | Loan Disb | 1,553,665.90 |
May 25, 2022 | IDA-49500 | Loan Disb | 1,007.98 |
May 25, 2022 | IDA-51670 | Loan Disb | 1,200,000.00 |
May 15, 2022 | IDA-51670 | Int Charges | 116,120.71 |
May 15, 2022 | IDA-51670 | Int Charges | 1,555.99 |
Jan 13, 2022 | IDA-60370 | Int Charges | 912.45 |
Jan 13, 2022 | IDA-60370 | Int Charges | 912.45 |
Jan 13, 2022 | IDA-60370 | Int Charges | 163,576.84 |
Jan 13, 2022 | IDA-60370 | Int Charges | 163,576.84 |
Jun 22, 2022 | IDA-60370 | Loan Disb | 2,033,004.40 |
Jan 14, 2022 | IDA-51670 | Int Charges | 120,180.65 |
Jan 14, 2022 | IDA-51670 | Int Charges | 120,180.65 |
Jan 14, 2022 | IDA-49500 | Int Charges | 1,624.38 |
Jan 14, 2022 | IDA-49500 | Int Charges | 1,624.38 |
Jan 14, 2022 | IDA-49500 | Loan Repay | 606,804.90 |
Jan 14, 2022 | IDA-49500 | Int Charges | 224,155.11 |
Jan 14, 2022 | IDA-49500 | Int Charges | 224,155.11 |
Jan 14, 2022 | IDA-51670 | Int Charges | 851.22 |
Jan 14, 2022 | IDA-51670 | Int Charges | 851.22 |
Nov 15, 2022 | IDA-51670 | Loan Repay | 4,294.04 |
Oct 11, 2022 | IDA-51670 | Loan Disb | 1,844,488.50 |
Nov 21, 2022 | IDA-51670 | Int Charges | 115,574.66 |
Nov 21, 2022 | IDA-51670 | Int Charges | 115,574.66 |
Nov 21, 2022 | IDA-51670 | Loan Repay | 426,084.62 |
Nov 21, 2022 | IDA-49500 | Loan Repay | 535,429.94 |
Nov 21, 2022 | IDA-49500 | Int Charges | 200,917.05 |
Nov 21, 2022 | IDA-49500 | Int Charges | 200,917.05 |
Dec 21, 2021 | IDA-60370 | Loan Disb | 1,727,956.80 |
Aug 23, 2021 | IDA-49500 | Loan Disb | 564,231.20 |
Nov 12, 2021 | IDA-60370 | Loan Disb | 807,937.70 |
Nov 17, 2021 | IDA-51670 | Loan Disb | 1,156,903.00 |
Aug 31, 2021 | IDA-60370 | Loan Disb | 950,000.00 |
Nov 16, 2021 | IDA-60370 | Loan Disb | 582,520.80 |
Aug 31, 2021 | IDA-49500 | Loan Disb | 919,025.20 |
Jun 15, 2022 | IDA-60370 | Int Charges | 1,922.66 |
Jun 15, 2022 | IDA-60370 | Int Charges | 1,922.66 |
Jun 15, 2022 | IDA-60370 | Int Charges | 206,145.90 |
Jun 15, 2022 | IDA-60370 | Int Charges | 206,145.90 |
Jul 30, 2021 | IDA-60370 | Int Charges | 3,187.76 |
Jul 30, 2021 | IDA-60370 | Int Charges | 3,187.76 |
Jul 30, 2021 | IDA-60370 | Int Charges | 153,517.12 |
Jul 30, 2021 | IDA-60370 | Int Charges | 153,517.12 |
Feb 22, 2022 | IDA-60370 | Loan Disb | 606,003.70 |
Jun 10, 2024 | IDA-51670 | Loan Disb | 2,149,744.20 |
Jan 25, 2024 | IDA-51670 | Loan Disb | 936,255.70 |
Jun 18, 2024 | IDA-49500 | Int Charges | 8,498.99 |
Jun 18, 2024 | IDA-49500 | Int Charges | 8,498.99 |
Jun 18, 2024 | IDA-51670 | Int Charges | 6,158.75 |
Jun 18, 2024 | IDA-51670 | Loan Repay | 434,781.60 |
Name | Review | Date |
---|---|---|
Monitoring and Evaluation | Moderately Satisfactory | 2023-12-12 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2023-12-12 |
Progress towards achievement of PDO | Satisfactory | 2023-12-12 |
Procurement | Moderately Satisfactory | 2023-12-12 |
Financial Management | Moderately Satisfactory | 2023-12-12 |
Counterpart Funding | Unsatisfactory | 2023-12-12 |
Project Management | Moderately Satisfactory | 2023-12-12 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-23-2024 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 03-26-2025 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | Modest | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Transport Cost borne by road users including vehicle operating costs and monetary value of travel time (measured in terms of roughness reduction, IRI rate) | Value | 12 | < 3 | 3 |
Date | September 1, 2011 | May 30, 2023 | June 30, 2024 | |
Comment |
Roads in good and fair condition as a share of total classified roads | Value | 1.00 | 34.50 | 34.50 |
Date | September 1, 2011 | May 30, 2023 | June 30, 2024 | |
Comment |
Direct project beneficiaries | Value | 288000.00 | 362905.00 | 362905.00 |
Date | September 1, 2011 | May 30, 2023 | June 28, 2024 | |
Comment |
Size of the total classified network | Value | 746.00 | 746.00 | 746.00 |
Date | September 1, 2011 | September 29, 2017 | June 30, 2024 | |
Comment |
Share of rural population with access to an all-season road | Value | 0.00 | 11.00 | 10.00 |
Date | September 1, 2011 | May 30, 2023 | June 30, 2024 | |
Comment |
Number of rural people with access to an all-season road | Value | 288000.00 | 288000.00 | 362905.00 |
Date | September 1, 2011 | September 29, 2017 | June 30, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Roads rehabilitated, Rural | Value | 0.00 | 245.00 | 253.00 |
Date | September 1, 2011 | May 30, 2023 | June 30, 2024 | |
Comment |
Number of staff training hours by training program (P1-P3, see methodology column) | Value | 0.00 | 1000.00 | 1500.00 |
Date | September 1, 2011 | May 30, 2023 | June 30, 2024 | |
Comment |
RoW protection pillars installed along the project corridor | Value | No | No | Yes |
Date | March 13, 2017 | May 30, 2023 | June 30, 2024 | |
Comment |
RAP implemented before start of civil works for ELWA Junction to Coca Cola Factory | Value | No | Yes | Yes |
Date | March 13, 2017 | May 30, 2023 | June 30, 2024 | |
Comment |
Roads constructed, Rural | Value | 0.00 | 2.00 | 2.00 |
Date | September 1, 2011 | May 30, 2023 | June 30, 2024 | |
Comment |
On-the-job training provided by MC | Value | 0.00 | 300.00 | 500.00 |
Date | September 1, 2011 | May 30, 2023 | June 30, 2024 | |
Comment |
Number of staff trained in road safety | Value | 0.00 | 1109.00 | 50.00 |
Date | March 13, 2017 | May 30, 2023 | June 30, 2024 | |
Comment |
Number of women who have their livelihood and income restored | Value | 0.00 | 420.00 | 420.00 |
Date | March 13, 2017 | May 30, 2023 | June 30, 2024 | |
Comment |
Road maintained | Value | 0.00 | 247.00 | 253.00 |
Date | September 1, 2011 | May 30, 2023 | June 30, 2024 | |
Comment |
Increased share of qualified local staff in key competency areas | Value | 10.00 | 75.00 | 100.00 |
Date | September 1, 2011 | May 30, 2023 | June 30, 2024 | |
Comment |
Multi-modal Transport Plan together with Strategic Investment Plan | Value | No | Yes | Yes |
Date | August 23, 2012 | May 30, 2023 | June 30, 2024 | |
Comment |
Structures at Elwa Intersection (split level intersection) built | Value | No | No | Yes |
Date | August 23, 2012 | May 30, 2023 | June 30, 2024 | |
Comment |
Increased share of female staff in the IIU measured as yearly percentage of new hires | Value | 0.00 | 0.00 | 51.00 |
Date | March 13, 2017 | May 30, 2023 | June 30, 2024 | |
Comment |
Percentage of citizen complaints received through Argo platform addressed within seven days | Value | 0.00 | 0.00 | 85.00 |
Date | March 13, 2017 | May 30, 2023 | June 30, 2024 | |
Comment |