MDTF KP Emergency Roads Recovery Project

Development Objective

The Project Development Objective (PDO) is to enable the population along the Project corridor to benefit from year round improved access and mobility through reconstruction of priority damaged roads and bridges in the conflict hit areas.

Key Details

Project Details

  • P125584

  • Closed

  • Zafar Iqbal Raja

  • KHYBER PAKHTUNKHWA HIGHWAYS AUTHORITY

  • Pakistan

  • June 15, 2011

  • (as of board presentation)

    July 16, 2011

  • October 17, 2011

  • US$ 8.00 million

  • B

  • Not Applicable

  • December 12, 2015

  • BANK APPROVED

  • August 1, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
MDTF for Crisi Affected Areas of NWFP/FATA/Balochistan 8.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 8.00
Total Project Cost** 8.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Monitoring and Evaluation Satisfactory 2015-07-20
Progress towards achievement of PDO Satisfactory 2015-07-20
Procurement Satisfactory 2015-07-20
Project Management Satisfactory 2015-07-20
Financial Management Satisfactory 2015-07-20
Overall Implementation Progress (IP) Highly Satisfactory 2015-07-20

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 07-26-2016
OutcomesModerately Satisfactory
Risk to Development OutcomeSubstantial
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Satisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 02-28-2017PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeSubstantialN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • 50% Increase in Operating Speeds of Commercial TrafficValue20 Km/Hour15 Km/Hour30 Km/Hour
    DateJuly 1, 2011May 31, 2015October 31, 2015
    Comment
  • 34%, 26% and 5% Decrease in Vehicle Operating Costs of 2-axle Truck, 3-axle Truck and Passenger BusesValueRs 23.89, Rs 24.76 and Rs 12.09To be measured at the completion of construction. Rs 15.84, Rs 18.33 and Rs 11.47
    DateJuly 1, 2011May 31, 2015October 31, 2015
    Comment
  • Level of Customer Satisfaction (High = 4.0, Low = 1.0)ValueLow = 1.02..0High = 4.0
    DateMay 31, 2015October 31, 2015
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Component 1: About 10.5 km of the provincial highway S-3B from Sharif Abad (Km 30+424) to Kanju (Km 40+924) constructed and operationalValue0.0 km40.4 km50.2 km (includes additional 9.3 km).
    DateNovember 3, 2011May 31, 2015October 31, 2015
    Comment
  • Component 2: Project ManagementValueNot ApplicableSatisfactorySatisfactory performance of construction supervisi
    DateNovember 3, 2011May 31, 2015October 31, 2015
    Comment