Financier | Commitments |
---|---|
IDA Credit | 243.80 |
Borrower/Recipient | 11.20 |
P125590
Active
Aguiratou Savadogo-Tinto , Ivan Mwondha
REPUBLIC OF UGANDA
February 13, 2014
(as of board presentation)
April 30, 2014
July 1, 2015
US$ 255.00 million
Uganda National Roads Authority (UNRA)
2014
US$ 243.80 million
B
May 14, 2024
June 30, 2025
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 243.80 |
Borrower/Recipient | 11.20 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 243.80 |
IBRD + IDA Commitment | 243.80 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 255.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 23, 2023 | IDA-54340 | Loan Disb | 20,676,856.00 |
May 15, 2024 | IDA-54340 | Int Charges | 1,577.44 |
May 15, 2024 | IDA-54340 | Int Charges | 1,577.44 |
May 15, 2024 | IDA-54340 | Loan Repay | 2,085,552.40 |
May 15, 2024 | IDA-54340 | Int Charges | 517,569.47 |
May 15, 2024 | IDA-54340 | Int Charges | 517,569.47 |
Jan 23, 2024 | IDA-54340 | Loan Disb | 11,063,678.00 |
Jan 12, 2024 | IDA-54340 | Loan Disb | 48,272,612.00 |
Nov 15, 2023 | IDA-54340 | Int Charges | 1,758.38 |
Nov 15, 2023 | IDA-54340 | Int Charges | 1,758.38 |
Nov 15, 2023 | IDA-54340 | Int Charges | 271,501.25 |
Nov 15, 2023 | IDA-54340 | Int Charges | 271,501.25 |
Feb 15, 2018 | IDA-54340 | Loan Disb | 2,000,000.00 |
May 15, 2019 | IDA-54340 | Int Charges | 1,714.48 |
May 15, 2019 | IDA-54340 | Int Charges | 1,714.48 |
May 15, 2019 | IDA-54340 | Int Charges | 105,502.55 |
May 15, 2019 | IDA-54340 | Int Charges | 105,502.55 |
Nov 15, 2019 | IDA-54340 | Int Charges | 777.95 |
Nov 15, 2019 | IDA-54340 | Int Charges | 777.95 |
Nov 15, 2019 | IDA-54340 | Int Charges | 105,728.60 |
Nov 15, 2019 | IDA-54340 | Int Charges | 105,728.60 |
Nov 15, 2018 | IDA-54340 | Int Charges | 5,475.23 |
Nov 15, 2018 | IDA-54340 | Int Charges | 5,475.23 |
Nov 15, 2018 | IDA-54340 | Int Charges | 107,165.83 |
Nov 15, 2018 | IDA-54340 | Int Charges | 107,165.83 |
Oct 23, 2020 | IDA-54340 | Loan Disb | 3,170,000.00 |
May 15, 2020 | IDA-54340 | Int Charges | 105,437.74 |
May 15, 2020 | IDA-54340 | Int Charges | 105,437.74 |
May 15, 2020 | IDA-54340 | Int Charges | 102.80 |
May 15, 2020 | IDA-54340 | Int Charges | 102.80 |
Nov 15, 2020 | IDA-54340 | Int Charges | 108,420.93 |
Nov 15, 2020 | IDA-54340 | Int Charges | 108,420.93 |
Nov 15, 2020 | IDA-54340 | Int Charges | 1,457.27 |
Nov 15, 2020 | IDA-54340 | Int Charges | 1,457.27 |
May 18, 2021 | IDA-54340 | Int Charges | 1,728.88 |
May 18, 2021 | IDA-54340 | Int Charges | 1,728.88 |
May 18, 2021 | IDA-54340 | Int Charges | 122,739.58 |
May 18, 2021 | IDA-54340 | Int Charges | 122,739.58 |
Nov 16, 2016 | IDA-54340 | Int Charges | 6,376.65 |
Jun 6, 2016 | IDA-54340 | Loan Disb | 2,000,000.00 |
Nov 15, 2017 | IDA-54340 | Int Charges | 113.69 |
Nov 15, 2017 | IDA-54340 | Int Charges | 113.69 |
Nov 15, 2017 | IDA-54340 | Int Charges | 7,504.49 |
Nov 15, 2017 | IDA-54340 | Int Charges | 7,504.49 |
May 15, 2017 | IDA-54340 | Int Charges | 193.06 |
May 15, 2017 | IDA-54340 | Int Charges | 193.06 |
May 15, 2017 | IDA-54340 | Int Charges | 6,975.02 |
May 15, 2017 | IDA-54340 | Int Charges | 6,975.02 |
Nov 16, 2016 | IDA-54340 | Int Charges | 6,376.65 |
May 15, 2018 | IDA-54340 | Int Charges | 58.60 |
May 15, 2018 | IDA-54340 | Int Charges | 58.60 |
May 15, 2018 | IDA-54340 | Int Charges | 11,396.57 |
May 15, 2018 | IDA-54340 | Int Charges | 11,396.57 |
May 4, 2018 | IDA-54340 | Loan Disb | 25,610,000.00 |
Nov 21, 2023 | IDA-54340 | Loan Disb | 22,426,334.00 |
Apr 30, 2014 | IDA-54340 | Loan Commitment | 243,800,000.00 |
May 15, 2022 | IDA-54340 | Int Charges | 129,353.98 |
May 15, 2022 | IDA-54340 | Int Charges | 129,353.98 |
May 15, 2022 | IDA-54340 | Int Charges | 1,830.58 |
May 15, 2022 | IDA-54340 | Int Charges | 1,830.58 |
Jun 16, 2022 | IDA-54340 | Loan Disb | 11,300,000.00 |
Nov 15, 2021 | IDA-54340 | Int Charges | 1,326.62 |
Nov 15, 2021 | IDA-54340 | Int Charges | 1,326.62 |
Nov 15, 2021 | IDA-54340 | Int Charges | 120,734.51 |
Nov 15, 2021 | IDA-54340 | Int Charges | 120,734.51 |
Feb 27, 2023 | IDA-54340 | Loan Disb | 9,800,000.00 |
May 16, 2023 | IDA-54340 | Int Charges | 2,726.45 |
May 16, 2023 | IDA-54340 | Int Charges | 2,726.45 |
May 16, 2023 | IDA-54340 | Int Charges | 192,091.27 |
May 16, 2023 | IDA-54340 | Int Charges | 192,091.27 |
Nov 15, 2022 | IDA-54340 | Int Charges | 4,786.95 |
Nov 15, 2022 | IDA-54340 | Int Charges | 4,786.95 |
Nov 15, 2022 | IDA-54340 | Int Charges | 159,429.05 |
Nov 15, 2022 | IDA-54340 | Int Charges | 159,429.05 |
Dec 8, 2021 | IDA-54340 | Loan Disb | 5,400,000.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2024-12-06 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-12-06 |
Procurement | Moderately Satisfactory | 2024-12-06 |
Overall Safeguards Rating | Unsatisfactory | 2024-12-06 |
Project Management | Moderately Satisfactory | 2024-12-06 |
Financial Management | Satisfactory | 2024-12-06 |
Monitoring and Evaluation | Satisfactory | 2024-12-06 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Road sections in good, fair & poor condition as a share of total length of the Tororo- Kamdini road | Value | 89.00 | 90.00 | 100.00 |
Date | March 29, 2014 | November 25, 2022 | January 1, 2024 | |
Comment |
Good | Value | 89.00 | 89.00 | 100.00 |
Date | March 29, 2014 | October 25, 2016 | January 1, 2024 | |
Comment |
Fair | Value | 2.00 | 2.00 | 0.00 |
Date | March 29, 2014 | October 25, 2016 | January 1, 2024 | |
Comment |
Poor | Value | 9.00 | 9.00 | 0.00 |
Date | March 29, 2014 | October 25, 2016 | January 1, 2024 | |
Comment |
Vehicle Operating Cost Reductions | Value | 0.30 | 0.30 | 0.27 |
Date | June 2, 2014 | December 29, 2017 | December 30, 2022 | |
Comment |
Reductions in Road accident on the project road | Value | 0.00 | 0.00 | 50.00 |
Date | June 2, 2014 | October 25, 2016 | June 30, 2024 | |
Comment |
Reduction in travel time | Value | 6.00 | 6.45 | 4.20 |
Date | June 2, 2014 | September 28, 2018 | December 30, 2024 | |
Comment |
Direct project beneficiaries | Value | 2250.00 | 3200.00 | 5140.00 |
Date | June 2, 2014 | April 26, 2018 | June 28, 2024 | |
Comment |
Female beneficiaries | Value | 40.00 | 40.00 | 40.00 |
Date | June 2, 2014 | October 25, 2016 | June 30, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Roads Maintained | Value | 189.00 | 260.00 | 340.00 |
Date | June 30, 2014 | March 29, 2024 | June 30, 2024 | |
Comment |
No of people trained in asset management | Value | 0.00 | 11.00 | 28.00 |
Date | June 30, 2014 | March 29, 2024 | December 30, 2024 | |
Comment |
Reduced no of trucks overloaded | Value | 54.00 | 54.00 | 10.00 |
Date | June 30, 2014 | March 29, 2024 | December 30, 2024 | |
Comment |
Annual Road Inventory to update RMS | Value | No | Yes | Yes |
Date | June 2, 2014 | March 29, 2024 | June 30, 2024 | |
Comment |
Roads rehabilitated, Non-rural | Value | 151.00 | 240.00 | 340.00 |
Date | June 30, 2014 | March 29, 2024 | June 30, 2024 | |
Comment |
Road safety Audits carried out | Value | 0.00 | 1.00 | 3.00 |
Date | June 30, 2014 | March 29, 2024 | December 30, 2024 | |
Comment |