P125597
Active
Abdul Wali Ibrahimi
Islamic Republic of Afghanistan
March 20, 2013
(as of board presentation)
April 3, 2014
April 11, 2014
US$ 110.00 million
Kabul Municipality (KM)
2014
US$ 110.00 million
B
Not Applicable
June 30, 2026
TBD
Bank Approved
August 15, 2024
| Financier | Commitments |
|---|---|
| Afghanistan Resilience Trust Fund | 110.00 |
| Product Line | IBRD/IDA |
|---|---|
| IBRD Commitment | N/A |
| IDA Commitment | N/A |
| IBRD + IDA Commitment | N/A |
| Lending Instrument | |
|---|---|
| Grant Amount | 110.00 |
| Total Project Cost** | 110.00 |
| Name | Review | Date |
|---|---|---|
| Financial Management | Moderately Unsatisfactory | 2021-06-30 |
| Monitoring and Evaluation | Satisfactory | 2021-06-30 |
| Overall Implementation Progress (IP) | Moderately Satisfactory | 2021-06-30 |
| Procurement | Moderately Satisfactory | 2021-06-30 |
| Progress towards achievement of PDO | Moderately Unsatisfactory | 2021-06-30 |
| Project Management | Moderately Satisfactory | 2021-06-30 |
| INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-10-2021 |
|---|---|
| Outcomes | Moderately Satisfactory |
| Risk to Development Outcome | |
| Bank Performance | Moderately Satisfactory |
| Borrower Performance | |
| Government Performance | |
| Implementing Agency |
| INDICATOR | ICR REVIEW: 04-26-2022 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
|---|---|---|
| Outcome Rating | Moderately Satisfactory | N/a |
| Risk To Development Outcome | N/a | |
| Bank Performance | Moderately Satisfactory | N/a |
| Borrower Performance | N/a | |
| Government Performance | Not Rated | N/a |
| Implementing Agency | N/a | |
| Icr Quality | Substantial | N/a |
| M&e Quality | Modest | N/a |
| INDICATOR | BASELINE | CURRENT | TARGET |
|---|
| Number of beneficiaries from upgrading in both planned and unplanned areas that are upgraded. | Value | 0.00 | 1706901.00 | 1052660.00 |
| Date | February 14, 2014 | June 24, 2021 | November 13, 2017 | |
| Comment |
| Number of people in urban areas provided with access to all season roads within a 500 meter range under the project. | Value | 0.00 | 335000.00 | 0.00 |
| Date | February 14, 2014 | March 21, 2018 | ||
| Comment |
| Public access to key financial information, in particular, the expenditure by type of services | Value | Qatia accounts prepared reporting expenditures aga | This is partly achieved. KM can now produce financ | |
| Date | June 27, 2017 | June 24, 2021 | ||
| Comment |
| INDICATOR | BASELINE | CURRENT | TARGET |
|---|
| Area Upgraded | Value | 0.00 | 3641.43 | 3020.00 |
| Date | February 14, 2014 | June 24, 2021 | November 13, 2017 | |
| Comment |
| Implementation of Financial Management Information System (AFMS/FreeBalance) | Value | Payroll module implemented. | The indicator is partly achieved. Six modules were | |
| Date | September 30, 2017 | June 24, 2021 | ||
| Comment |
| KM Financial Management (FM) Framework | Value | MOF financial regulations used which are not speci | MoF requirements – including workflow, classificat | |
| Date | September 30, 2017 | November 15, 2020 | ||
| Comment |
| Kilometers of community drains lined | Value | 0.00 | 988.33 | 0.00 |
| Date | November 13, 2017 | June 24, 2021 | ||
| Comment |
| Kilometers of community roads paved | Value | 0.00 | 711.55 | 560.00 |
| Date | February 14, 2014 | June 24, 2021 | November 13, 2017 | |
| Comment |
| Kilometers of trunk drains lined | Value | 0.00 | 55.57 | 0.00 |
| Date | February 14, 2014 | June 24, 2021 | November 13, 2018 | |
| Comment |
| Kilometers of trunk road paved | Value | 0.00 | 62.96 | 37.00 |
| Date | February 14, 2014 | June 24, 2021 | November 13, 2017 | |
| Comment |