Financier | Commitments |
---|---|
Inter-American Development Bank | 67.70 |
International Bank for Reconstruction and Development | 66.00 |
Borrower/Recipient | 283.50 |
Fund for the Development fo the Plata River Basin | 92.80 |
P125803
Closed
Gregoire Gauthier
Ministry of Economy and Finances (MEF)
November 23, 2011
(as of board presentation)
November 13, 2012
April 16, 2013
US$ 510.00 million
Ministry of Transport and Public Works
2013
US$ 226.50 million
N/A
November 1, 2023
June 30, 2020
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Inter-American Development Bank | 67.70 |
International Bank for Reconstruction and Development | 66.00 |
Borrower/Recipient | 283.50 |
Fund for the Development fo the Plata River Basin | 92.80 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 66.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 66.00 |
Lending Instrument | |
---|---|
Grant Amount | 160.50 |
Total Project Cost** | 510.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Aug 15, 2024 | IBRD-87330 | Int Charges | 11,159.03 |
Aug 15, 2024 | IBRD-87330 | Int Charges | 1,902,439.20 |
Aug 15, 2024 | IBRD-87330 | Loan Repay | 2,760,000.00 |
Aug 15, 2024 | IBRD-82050 | Int Charges | 11,844.66 |
Aug 15, 2024 | IBRD-82050 | Int Charges | 2,115,488.50 |
Feb 15, 2024 | IBRD-82050 | Int Charges | 18,741.70 |
Feb 15, 2024 | IBRD-87330 | Int Charges | 18,459.39 |
Feb 15, 2024 | IBRD-87330 | Int Charges | 1,987,090.90 |
Feb 15, 2024 | IBRD-87330 | Loan Repay | 2,760,000.00 |
Feb 15, 2024 | IBRD-82050 | Int Charges | 2,109,183.00 |
Mar 24, 2017 | IBRD-87330 | Loan Commitment | 70,000,000.00 |
Nov 13, 2012 | IBRD-82050 | Loan Commitment | 66,000,000.00 |
Feb 15, 2021 | IBRD-87330 | Int Charges | 366,773.34 |
Feb 15, 2021 | IBRD-87330 | Int Charges | 5,864.07 |
Feb 15, 2021 | IBRD-87330 | Int Charges | 51,130.81 |
Feb 15, 2021 | IBRD-87330 | Int Charges | 942.63 |
Feb 15, 2021 | IBRD-82050 | Int Charges | 342,591.78 |
Dec 31, 2020 | IBRD-87330 | Loan Cancel | 1,000,000.00 |
Aug 15, 2021 | IBRD-87330 | Int Charges | 322,317.44 |
Aug 15, 2021 | IBRD-87330 | Int Charges | 315.05 |
Aug 15, 2021 | IBRD-82050 | Int Charges | 301,361.12 |
Feb 15, 2022 | IBRD-87330 | Int Charges | 313,873.34 |
Feb 15, 2022 | IBRD-82050 | Int Charges | 293,179.50 |
Aug 15, 2022 | IBRD-87330 | Int Charges | 476,333.12 |
Aug 15, 2022 | IBRD-87330 | Loan Repay | 2,760,000.00 |
Aug 15, 2022 | IBRD-82050 | Int Charges | 444,928.22 |
Aug 15, 2018 | IBRD-87330 | Int Charges | 86,780.81 |
Aug 15, 2018 | IBRD-82050 | Int Charges | 881,400.44 |
Feb 15, 2019 | IBRD-87330 | Int Charges | 88,219.16 |
Feb 15, 2019 | IBRD-82050 | Int Charges | 1,050,834.40 |
May 8, 2019 | IBRD-87330 | Loan Disb | 22,891,058.00 |
Sep 24, 2018 | IBRD-82050 | Loan Cancel | 1,549,207.00 |
Aug 15, 2019 | IBRD-87330 | Int Charges | 71,258.80 |
Aug 15, 2019 | IBRD-87330 | Int Charges | 216,549.40 |
Aug 15, 2019 | IBRD-82050 | Int Charges | 1,114,712.20 |
Dec 2, 2019 | IBRD-87330 | Loan Disb | 29,275,604.00 |
Feb 15, 2020 | IBRD-82050 | Int Charges | 896,009.25 |
Feb 15, 2020 | IBRD-87330 | Int Charges | 484,131.70 |
Feb 15, 2020 | IBRD-87330 | Int Charges | 44,316.30 |
Jun 25, 2020 | IBRD-87330 | Loan Disb | 16,833,338.00 |
Aug 15, 2020 | IBRD-87330 | Int Charges | 16,305.77 |
Aug 15, 2020 | IBRD-87330 | Int Charges | 630,318.20 |
Aug 15, 2020 | IBRD-82050 | Int Charges | 778,744.60 |
Aug 15, 2016 | IBRD-82050 | Int Charges | 298,726.75 |
Jun 30, 2016 | IBRD-82050 | Loan Disb | 18,129,946.00 |
Feb 15, 2017 | IBRD-82050 | Int Charges | 33,127.46 |
Feb 15, 2017 | IBRD-82050 | Int Charges | 549,985.90 |
Jun 27, 2017 | IBRD-82050 | Loan Disb | 5,000,000.00 |
Aug 15, 2017 | IBRD-82050 | Int Charges | 591,832.60 |
Feb 15, 2018 | IBRD-82050 | Int Charges | 13,474.99 |
Feb 15, 2018 | IBRD-82050 | Int Charges | 695,066.00 |
Feb 15, 2018 | IBRD-87330 | Int Charges | 78,630.13 |
Dec 8, 2017 | IBRD-87330 | Fee Charges | 175,000.00 |
Feb 15, 2015 | IBRD-82050 | Int Charges | 15,266.44 |
Feb 15, 2015 | IBRD-82050 | Int Charges | 91,073.84 |
Jul 14, 2014 | IBRD-82050 | Loan Disb | 21,468,432.00 |
Aug 15, 2015 | IBRD-82050 | Int Charges | 98,224.04 |
Jul 20, 2015 | IBRD-82050 | Loan Disb | 19,852,416.00 |
Feb 15, 2016 | IBRD-82050 | Int Charges | 13,047.45 |
Feb 15, 2016 | IBRD-82050 | Int Charges | 225,979.12 |
Feb 15, 2023 | IBRD-87330 | Int Charges | 111,426.33 |
Feb 15, 2023 | IBRD-87330 | Int Charges | 1,527,481.10 |
Feb 15, 2023 | IBRD-87330 | Loan Repay | 2,760,000.00 |
Feb 15, 2023 | IBRD-82050 | Int Charges | 104,079.96 |
Feb 15, 2023 | IBRD-82050 | Int Charges | 1,486,222.40 |
Aug 15, 2023 | IBRD-87330 | Loan Repay | 2,760,000.00 |
Aug 15, 2023 | IBRD-82050 | Int Charges | 67,581.35 |
Aug 15, 2023 | IBRD-82050 | Int Charges | 1,823,769.20 |
Aug 15, 2023 | IBRD-87330 | Int Charges | 69,457.47 |
Aug 15, 2023 | IBRD-87330 | Int Charges | 1,796,298.60 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2020-06-29 |
Monitoring and Evaluation | Moderately Satisfactory | 2020-06-29 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2020-06-29 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 01-11-2021 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 04-19-2021 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of the Uruguay National Road network in good or very good condition | Value | 40.00 | 55.00 | 0.00 |
Date | March 3, 2017 | December 31, 2019 | ||
Comment |
2 - Percentage of Program Action Plan actions completed (cumulative) | Value | 0.00 | 100.00 | 0.00 |
Date | October 12, 2012 | June 30, 2020 | ||
Comment |
1 - At least 35 percent of the Uruguay National Road Network are in good or very good condition | Value | Yes | Yes | |
Date | November 13, 2012 | December 30, 2016 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
1 - Cumulative number of km rehabilitated on the National Road Network, at a minimum rating of 85, as measured by the IES. | Value | 0.00 | 1854.00 | 1414.00 |
Date | November 13, 2012 | December 31, 2019 | December 31, 2019 | |
Comment |
3 - (DLR 3-1): the multimodal plan for the Montevideo seaport has been approved | Value | No | Yes | |
Date | November 13, 2012 | December 30, 2016 | ||
Comment |
3 - (DLR 3-3): DNV environmental manual has been updated and at least 75% of DNV's technical staff with responsibilities related toworks supervision has been trained. | Value | No | Yes | |
Date | November 13, 2012 | December 30, 2016 | ||
Comment |
NEW DLR#3.2: (a) a study to assess which areas of the National Road Network are subject to climatic risks has been completed | Value | No | Yes | |
Date | March 3, 2017 | June 30, 2020 | ||
Comment |
NEW DLR#3.1 (a): MTOP’s central laboratory for roadworks quality assurance has carried out at least 5% of the asphalt, pavement andsoil tests required by the work contracts in execution in calendar y | Value | No | Yes | |
Date | March 3, 2017 | April 22, 2019 | ||
Comment |
3 - (DLR 3-4): The Guidelines for expropriation and social management processes have been approved and an international workshop onroadworks social management best practices has been carried out. | Value | No | Yes | |
Date | November 13, 2012 | December 30, 2016 | ||
Comment |
2 - Number of km of the National Road Network maintained through performance-based contracts. | Value | 3000.00 | 3637.00 | 3000.00 |
Date | November 13, 2012 | December 31, 2019 | December 31, 2019 | |
Comment |
3 - (DLR 3-2): The catalogue for technical solutions of pavement rehabilitation has been approved. | Value | No | Yes | |
Date | November 13, 2012 | December 30, 2016 | ||
Comment |
NEW DLR #3.2 (b): at least 20 selected bridges have been diagnosed against climatic risks | Value | 0.00 | 20.00 | 0.00 |
Date | March 3, 2017 | June 30, 2020 | ||
Comment |
NEW DLR#3.1 (b): MTOP’s central laboratory for roadworks quality assurance has carried out at least 5% of the asphalt, pavement andsoil tests required by the works contracts in execution in calendar | Value | No | Yes | |
Date | March 3, 2017 | April 22, 2019 | ||
Comment |
NEW DLR#3.2 (c) a contingency plan for catastrophic climate related events has been developed. | Value | No | Yes | |
Date | March 3, 2017 | June 30, 2020 | ||
Comment |
NEW DLR#3.1 (c): MTOP’s central laboratory for roadworks quality assurance has carried out at least 5% of the asphalt, pavement andsoil tests required by the works contracts in execution in calendar | Value | No | Yes | |
Date | March 3, 2017 | December 31, 2019 | ||
Comment |