Skip to Main Navigation

Tajikistan Health Services Improvement Project (HSIP)

Abstract*

The objective of the Health Services Improvement Project for Tajikistan is to contribute to the improvement of the coverage and quality of basic primary health care (PHC) services in rural health facilities in selected districts. The project has three components. The first component is performance-based financing (PBF). This component will support a PBF pilot at the PHC level in eight rayons (or districts) in Khatlon and Sogd oblasts (regions). Under...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The revised PDO is to contribute to the improvement of the coverage and quality of basic primary health care (PHC) services in selected districts.

Key Details

Project Details

  • P126130

  • Closed

  • Mirja Sjoblom , Baktybek Zhumadil, Mutriba Latypova

  • Republic of Tajikistan

  • Tajikistan

  • January 10, 2012

  • (as of board presentation)

    July 30, 2013

  • December 11, 2013

  • US$ 33.00 million

  • Ministry of Health & Social Protection,Ministry of Health & Social Protection Project Coordination Group

  • Europe and Central Asia

  • 2014

  • US$ 29.80 million

  • B

  • March 28, 2024

  • June 30, 2023

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 5.50
IDA Grant 19.50
Health Results-based Financing 4.80
Borrower/Recipient 3.20

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 25.00
IBRD + IDA Commitment 25.00
Lending Instrument
Grant Amount 4.80
Total Project Cost** 33.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Oct 27, 2017 IDA-H8790 Loan Disb 566,500.06
Oct 27, 2017 IDA-56660 Loan Disb 231,522.70
Aug 23, 2017 IDA-56660 Loan Disb 178,065.06
Sep 6, 2017 IDA-56660 Loan Disb 63,620.06
Aug 23, 2017 IDA-56660 Loan Disb 99,999.99
Aug 23, 2017 IDA-56660 Loan Disb 18,753.03
Sep 25, 2017 IDA-H8790 Loan Disb 486,340.66
Aug 23, 2017 IDA-56660 Loan Disb 43,486.61
Aug 23, 2017 IDA-56660 Loan Disb 27,590.86
Sep 20, 2017 IDA-56660 Loan Disb 71,495.38
Mar 1, 2018 IDA-56660 Loan Disb 150,000.00
Apr 15, 2018 IDA-56660 Int Charges 511.29
Apr 15, 2018 IDA-56660 Int Charges 511.29
Dec 29, 2017 IDA-H8790 Loan Disb 734,796.60
Dec 8, 2017 IDA-56660 Loan Disb 236,803.22
Feb 6, 2018 IDA-56660 Loan Disb 216,820.67
Feb 6, 2018 IDA-D0700 Loan Disb 122,344.57
Apr 15, 2023 IDA-56660 Loan Repay 3,380.89
Jan 23, 2023 IDA-D5470 Loan Disb 670,261.60
Oct 15, 2023 IDA-56660 Int Charges 18,296.98
Oct 15, 2023 IDA-56660 Int Charges 18,296.98
Oct 15, 2023 IDA-56660 Int Charges 123.77
Oct 15, 2023 IDA-56660 Int Charges 123.77
Oct 15, 2023 IDA-56660 Int Charges 1,278.09
Oct 15, 2023 IDA-56660 Int Charges 1,278.09
Oct 15, 2023 IDA-56660 Loan Repay 81,870.00
Apr 15, 2024 IDA-56660 Loan Repay 1,739.17
Apr 15, 2024 IDA-56660 Loan Repay 80,533.95
Apr 15, 2024 IDA-56660 Int Charges 18,202.95
Apr 15, 2024 IDA-56660 Int Charges 18,202.95
Dec 18, 2019 IDA-D5470 Loan Commitment 10,000,000.00
Jun 22, 2015 IDA-56660 Loan Commitment 5,500,000.00
Jun 22, 2015 IDA-D0700 Loan Commitment 4,500,000.00
Jul 30, 2013 IDA-H8790 Loan Commitment 15,000,000.00
Jan 30, 2021 IDA-D0700 Loan Cancel 16.66
Feb 23, 2021 IDA-D5470 Loan Disb 1,000,000.00
Apr 15, 2021 IDA-56660 Int Charges 27.93
Apr 15, 2021 IDA-56660 Int Charges 27.93
Apr 15, 2021 IDA-56660 Int Charges 21,429.00
Apr 15, 2021 IDA-56660 Int Charges 21,429.00
Apr 15, 2018 IDA-56660 Int Charges 5,474.71
Apr 15, 2018 IDA-56660 Int Charges 5,474.71
May 4, 2018 IDA-56660 Loan Disb 115,289.11
May 4, 2018 IDA-H8790 Loan Disb 631,219.80
May 4, 2018 IDA-D0700 Loan Disb 395,916.50
Jul 17, 2018 IDA-D0700 Loan Disb 411,623.47
Jul 1, 2019 IDA-D0700 Loan Disb 177,239.92
Jun 23, 2019 IDA-H8790 Loan Disb 977,810.75
Jun 14, 2021 IDA-D5470 Loan Disb 216,841.55
Sep 7, 2021 IDA-D5470 Loan Disb 315,065.70
Oct 15, 2021 IDA-56660 Loan Repay 182.49
Oct 15, 2021 IDA-56660 Loan Repay 21,122.76
Oct 15, 2021 IDA-56660 Loan Repay 66,937.26
Oct 15, 2021 IDA-56660 Int Charges 21,178.20
Oct 15, 2021 IDA-56660 Int Charges 21,178.20
Sep 23, 2021 IDA-D5470 Loan Disb 1,000,000.00
Sep 23, 2021 IDA-D5470 Loan Disb 523,948.16
Jun 14, 2022 IDA-D5470 Loan Disb 1,065,994.00
Apr 15, 2022 IDA-56660 Loan Repay 84,743.58
Apr 15, 2022 IDA-56660 Int Charges 20,175.77
Apr 15, 2022 IDA-56660 Int Charges 20,175.77
Apr 15, 2022 IDA-56660 Loan Repay 656.42
Jul 28, 2022 IDA-D5470 Loan Disb 720,853.94
Feb 23, 2022 IDA-D5470 Loan Disb 396,396.16
Aug 2, 2022 IDA-D5470 Loan Disb 563,304.50
Oct 14, 2022 IDA-D5470 Loan Disb 1,385,090.60
Dec 27, 2022 IDA-D5470 Loan Disb 1,260,619.40
Jan 28, 2022 IDA-D5470 Loan Disb 624,655.00
Oct 15, 2022 IDA-56660 Loan Repay 77,120.22
Oct 15, 2022 IDA-56660 Int Charges 18,549.13
Oct 15, 2022 IDA-56660 Int Charges 18,549.13
Oct 15, 2022 IDA-56660 Loan Repay 2,661.03
Feb 15, 2023 IDA-D5470 Loan Disb 169,345.52
Apr 15, 2023 IDA-56660 Loan Repay 81,280.98
Apr 15, 2023 IDA-56660 Int Charges 18,044.71
Apr 15, 2023 IDA-56660 Int Charges 18,044.71
Jan 16, 2019 IDA-56660 Loan Disb 600,000.00
Nov 1, 2018 IDA-56660 Loan Disb 320,364.25
Feb 12, 2019 IDA-56660 Loan Disb 494,881.12
Feb 19, 2019 IDA-D0700 Loan Disb 154,702.19
Feb 19, 2019 IDA-H8790 Loan Disb 473,081.88
Oct 15, 2018 IDA-56660 Int Charges 116.69
Oct 15, 2018 IDA-56660 Int Charges 116.69
Oct 15, 2018 IDA-56660 Int Charges 7,379.26
Oct 15, 2018 IDA-56660 Int Charges 7,379.26
May 3, 2019 IDA-D0700 Loan Disb 200,137.47
Jul 16, 2019 IDA-56660 Loan Disb 301,181.40
Aug 6, 2019 IDA-56660 Loan Disb -598,091.20
Aug 6, 2019 IDA-H8790 Loan Disb 598,091.20
Nov 7, 2019 IDA-H8790 Loan Disb 376,000.62
Sep 27, 2019 IDA-56660 Loan Disb 401,303.60
Oct 15, 2019 IDA-56660 Int Charges 16,408.25
Oct 15, 2019 IDA-56660 Int Charges 16,408.25
Oct 15, 2019 IDA-56660 Int Charges 33.12
Oct 15, 2019 IDA-56660 Int Charges 33.12
Sep 5, 2019 IDA-56660 Loan Disb 224,444.42
Nov 14, 2019 IDA-56660 Loan Disb 54,880.24
Jul 30, 2019 IDA-H8790 Loan Disb 496,380.53
Oct 21, 2019 IDA-56660 Loan Disb 127,989.27
Oct 21, 2019 IDA-D0700 Loan Disb 228,198.06
Jul 18, 2019 IDA-56660 Loan Disb 977,810.80
Dec 23, 2019 IDA-D0700 Loan Disb 70,111.79
Apr 20, 2020 IDA-D0700 Loan Disb 17,334.57
Apr 16, 2020 IDA-56660 Int Charges 293.28
Apr 16, 2020 IDA-56660 Int Charges 293.28
Apr 16, 2020 IDA-56660 Int Charges 20,423.93
Apr 16, 2020 IDA-56660 Int Charges 20,423.93
Oct 15, 2020 IDA-56660 Int Charges 21,104.84
Oct 15, 2020 IDA-56660 Int Charges 21,104.84
Oct 15, 2020 IDA-56660 Int Charges 40.37
Oct 15, 2020 IDA-56660 Int Charges 40.37
May 24, 2017 IDA-56660 Loan Disb 86,927.94
May 31, 2017 IDA-H8790 Loan Disb 633,881.06
Mar 20, 2017 IDA-56660 Loan Disb 250,000.00
May 26, 2017 IDA-56660 Loan Disb 30,742.88
Jun 20, 2017 IDA-H8790 Loan Disb 131,323.62
May 26, 2017 IDA-56660 Loan Disb 33,708.32
Jul 13, 2017 IDA-H8790 Loan Disb 525,080.75
Mar 9, 2017 IDA-D0700 Loan Disb 69,600.00
Mar 9, 2017 IDA-H8790 Loan Disb 877,346.25
Mar 16, 2017 IDA-56660 Loan Disb 28,743.25
Oct 25, 2017 IDA-H8790 Loan Disb 58,479.00
Oct 15, 2017 IDA-56660 Int Charges 153.81
Oct 15, 2017 IDA-56660 Int Charges 153.81
Oct 15, 2017 IDA-56660 Int Charges 1,532.93
Oct 15, 2017 IDA-56660 Int Charges 1,532.93
Sep 5, 2018 IDA-D0700 Loan Disb 292,507.53
Jul 13, 2018 IDA-56660 Loan Disb 256,572.11
Sep 6, 2018 IDA-D0700 Loan Disb 224,425.39
Aug 28, 2018 IDA-D0700 Loan Disb 155,006.33
Aug 28, 2018 IDA-56660 Loan Disb 211,599.52
Jul 30, 2018 IDA-D0700 Loan Disb 620,025.30
Aug 13, 2018 IDA-H8790 Loan Disb 578,958.25
Nov 28, 2018 IDA-D0700 Loan Disb 134,038.22
Nov 28, 2018 IDA-H8790 Loan Disb 512,735.97
Dec 5, 2014 IDA-H8790 Loan Disb 771,986.40
Nov 21, 2014 IDA-H8790 Loan Disb 154,107.27
Apr 10, 2014 IDA-H8790 Loan Disb 1,000,000.00
Feb 17, 2015 IDA-H8790 Loan Disb 98,216.00
Feb 23, 2015 IDA-H8790 Loan Disb 99,440.74
Feb 19, 2015 IDA-H8790 Loan Disb 612,705.00
Mar 2, 2015 IDA-H8790 Loan Disb 99,683.00
Jun 26, 2015 IDA-H8790 Loan Disb 380,629.53
May 6, 2015 IDA-H8790 Loan Disb 127,500.00
Jun 22, 2015 IDA-H8790 Loan Disb 97,420.00
Aug 11, 2015 IDA-H8790 Loan Disb 170,612.00
Aug 25, 2015 IDA-H8790 Loan Disb 555,044.60
Dec 3, 2015 IDA-H8790 Loan Disb 499,620.88
May 3, 2016 IDA-D0700 Loan Disb 500,000.00
Apr 6, 2016 IDA-D0700 Loan Disb 500,000.00
Sep 1, 2016 IDA-H8790 Loan Disb 571,825.60
May 13, 2016 IDA-H8790 Loan Disb 853,495.10
Oct 18, 2016 IDA-D0700 Loan Disb 69,600.00
Jun 27, 2016 IDA-H8790 Loan Disb 312,200.80
Aug 29, 2016 IDA-H8790 Loan Disb 95,132.28
Oct 31, 2016 IDA-H8790 Loan Disb 883,574.94
Jun 23, 2019 IDA-H8790 Loan Disb -977,810.75
Apr 29, 2019 IDA-56660 Loan Disb 314,753.00
Apr 15, 2019 IDA-56660 Int Charges 283.41
Apr 15, 2019 IDA-56660 Int Charges 283.41
Apr 15, 2019 IDA-56660 Int Charges 11,542.51
Apr 15, 2019 IDA-56660 Int Charges 11,542.51
Jul 18, 2019 IDA-H8790 Loan Disb -977,810.80
Aug 19, 2019 IDA-D0700 Loan Disb 282,547.06

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Counterpart Funding Moderately Satisfactory 2023-06-29
Project Management Satisfactory 2023-06-29
Financial Management Satisfactory 2023-06-29
Progress towards achievement of PDO Satisfactory 2023-06-29
Monitoring and Evaluation Satisfactory 2023-06-29
Procurement Satisfactory 2023-06-29
Overall Implementation Progress (IP) Satisfactory 2023-06-29

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 03-18-2024
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 09-03-2024PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Average Health Facility Quality of Care Score in existing project districtsValue180 (Spitamen pre-pilot Rural Health Center - RHC)1144 (average among 10 participating districts, RHRevision 1 (introduction of new manual): RHC: 1040
    DateFebruary 15, 2015June 30, 2023June 30, 2023
    Comment
  • Mothers receiving timely postnatal counselling in existing districtsValue90.0099.7095.00
    DateOctober 11, 2019June 30, 2023June 30, 2023
    Comment
  • Average Health Facility Quality of Care Score in new project districtsValueRHC 55%HH 50%Rural health center 55 percentHealth House 50 per
    Date
    Comment
  • Mothers receiving timely postnatal counselling in new districtsValue60.0060.0063.00
    Date
    Comment
  • Number of mothers counselled on nutritionValue182452.00326730.00290512.00
    DateOctober 11, 2019June 30, 2023June 30, 2023
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of eligible health facilities in which PBF is initiatedValue0.00720.00720.00
    DateOctober 1, 2013June 30, 2023June 30, 2023
    Comment
  • Health personnel receiving trainingValue0.0013867.0013700.00
    DateOctober 1, 2013June 30, 2023June 30, 2023
    Comment
  • Number of new project districts in which PBF MIS is operationalValue0.006.006.00
    DateOctober 11, 2019June 30, 2023March 31, 2021
    Comment
  • Percentage of Primary Health Care facilities eligible for PBF payments who received timely PBF payments in the preceding quarterValue0.00100.000.00
    DateOctober 1, 2013June 30, 2023
    Comment
  • Health facilities rehabilitated and/or equippedValue0.00481.00425.00
    DateOctober 1, 2013June 30, 2023June 30, 2023
    Comment
  • Number of independent verification visits completed per scheduleValue0.0014.0014.00
    DateOctober 1, 2013June 30, 2023June 30, 2023
    Comment
  • Percentage of hypertension patient charts with treatment according to protocol in existing districtsValue80%98%97%
    DateOctober 11, 2019June 30, 2023December 31, 2021
    Comment
  • Percentage of hypertension patient charts with treatment according to protocol in new districtsValue20%20%
    Date
    Comment
  • Number of citizen scorecard exercises/sessions conducted in the project districts.Value0.00816.00816.00
    DateMarch 13, 2015June 30, 2023December 31, 2022
    Comment
  • Average proportion of women attending citizen scorecard exercisesValue0.000.0020.00
    Date
    Comment
  • Percentage of PHC facilities that act on community action plansValue0.0099.2415.00
    DateOctober 11, 2019June 30, 2023December 31, 2021
    Comment
  • People who have received essential health, nutrition, and population (HNP) servicesValue0.002176204.002230685.00
    DateOctober 1, 2013June 30, 2023June 30, 2023
    Comment
  • People who have received essential health, nutrition, and population (HNP) services - Female (RMS requirement)Value0.00793854.000.00
    DateOctober 1, 2013April 13, 2018
    Comment
  • Number of children immunizedValue0.00262577.00262256.00
    DateOctober 11, 2019June 30, 2023June 30, 2023
    Comment
  • Number of women and children who have received basic nutrition servicesValue0.001814084.001878990.00
    DateOctober 1, 2013June 30, 2023June 30, 2023
    Comment
  • Number of deliveries attended by skilled health personnelValue0.0082800.0080000.00
    DateOctober 1, 2013June 30, 2023June 30, 2023
    Comment
  • Percentage of PBF facilities completing household engagement exerciseValue0.0097.1045.00
    DateOctober 11, 2019June 30, 2023June 30, 2023
    Comment