Sierra Leone Energy Access Project - Sierra Leone Infrastructure Development Fund

Abstract*

The objectives of the Energy Access Project for Sierra Leone are to: 1) reduce losses in electricity supply in Freetown Capital Western Area; 2) improve commercial performance of the National Power Authority (NPA); and 3) increase access to electricity in selected rural areas. The project consists of the following components: i) rehabilitation of primary distribution network, loss reduction and improvement of NPA's operational and commercial performance;...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The proposed new PDO is to reduce losses in electricity supply in Freetown Capital Western Area and to improve commercial performance of the Electricity Distribution and Supply Authority (EDSA).

Key Details

Project Details

  • P126180

  • Closed

  • Nash Eyison

  • Government of Sierra Leone

  • Sierra Leone

  • May 17, 2012

  • (as of board presentation)

    January 31, 2013

  • September 18, 2013

  • US$ 16.00 million

  • B

  • Not Applicable

  • July 31, 2017

  • Yes

  • BANK APPROVED

  • May 14, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Sierra Leone Infrastructure Trust Fund 16.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 16.00
Total Project Cost** 16.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Satisfactory 2017-06-07
Project Management Moderately Satisfactory 2017-06-07
Monitoring and Evaluation Moderately Satisfactory 2017-06-07
Progress towards achievement of PDO Satisfactory 2017-06-07
Financial Management Satisfactory 2017-06-07
Overall Implementation Progress (IP) Moderately Satisfactory 2017-06-07

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-04-2018PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Collection rate by EDSAValue76.0086.0086.00
    DateFebruary 2, 2009October 28, 2015July 31, 2017
    Comment
  • Direct project beneficiariesValue0.00624000.00720000.00
    DateJune 30, 2012October 28, 2015July 31, 2017
    Comment
  • Electricity losses per year in the project areaValue38.0033.0034.50
    DateFebruary 2, 2009October 28, 2015September 16, 2106
    Comment
  • Female beneficiariesValue0.0051.0051.00
    DateJune 30, 2012October 28, 2015July 31, 2017
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Substations rehabilitated under the projectValue0.004.005.00
    DateFebruary 2, 2009October 28, 2015July 31, 2017
    Comment
  • Pre-paid meters installed under the projectValue0.0020000.0020000.00
    DateFebruary 2, 2009October 28, 2015July 31, 2017
    Comment
  • Staff recruited at the Project Management Unit (PMU) under the ProjectValue0.004.006.00
    DateJune 30, 2008October 28, 2015July 31, 2017
    Comment
  • Statistical meters installed under the projectValue0.00200.00100.00
    DateJune 30, 2008October 28, 2015September 16, 2106
    Comment
  • Distribution lines constructed or rehabilitated under the projectValue0.007.507.80
    DateDecember 31, 2008October 28, 2015July 31, 2017
    Comment
  • Distribution lines rehabilitated under the projectValue0.007.507.80
    DateDecember 31, 2008October 28, 2015July 31, 2017
    Comment