Financier | Commitments |
---|---|
Sierra Leone Infrastructure Trust Fund | 16.00 |
P126180
Closed
Nash Eyison
Government of Sierra Leone
May 17, 2012
(as of board presentation)
January 31, 2013
September 18, 2013
US$ 16.00 million
Ministry of Energy
2013
US$ 16.00 million
B
Not Applicable
July 31, 2017
Yes
BANK APPROVED
May 14, 2024
Financier | Commitments |
---|---|
Sierra Leone Infrastructure Trust Fund | 16.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 16.00 |
Total Project Cost** | 16.00 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2017-06-07 |
Project Management | Moderately Satisfactory | 2017-06-07 |
Monitoring and Evaluation | Moderately Satisfactory | 2017-06-07 |
Progress towards achievement of PDO | Satisfactory | 2017-06-07 |
Financial Management | Satisfactory | 2017-06-07 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2017-06-07 |
INDICATOR | ICR REVIEW: 06-04-2018 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Collection rate by EDSA | Value | 76.00 | 86.00 | 86.00 |
Date | February 2, 2009 | October 28, 2015 | July 31, 2017 | |
Comment |
Direct project beneficiaries | Value | 0.00 | 624000.00 | 720000.00 |
Date | June 30, 2012 | October 28, 2015 | July 31, 2017 | |
Comment |
Electricity losses per year in the project area | Value | 38.00 | 33.00 | 34.50 |
Date | February 2, 2009 | October 28, 2015 | September 16, 2106 | |
Comment |
Female beneficiaries | Value | 0.00 | 51.00 | 51.00 |
Date | June 30, 2012 | October 28, 2015 | July 31, 2017 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Substations rehabilitated under the project | Value | 0.00 | 4.00 | 5.00 |
Date | February 2, 2009 | October 28, 2015 | July 31, 2017 | |
Comment |
Pre-paid meters installed under the project | Value | 0.00 | 20000.00 | 20000.00 |
Date | February 2, 2009 | October 28, 2015 | July 31, 2017 | |
Comment |
Staff recruited at the Project Management Unit (PMU) under the Project | Value | 0.00 | 4.00 | 6.00 |
Date | June 30, 2008 | October 28, 2015 | July 31, 2017 | |
Comment |
Statistical meters installed under the project | Value | 0.00 | 200.00 | 100.00 |
Date | June 30, 2008 | October 28, 2015 | September 16, 2106 | |
Comment |
Distribution lines constructed or rehabilitated under the project | Value | 0.00 | 7.50 | 7.80 |
Date | December 31, 2008 | October 28, 2015 | July 31, 2017 | |
Comment |
Distribution lines rehabilitated under the project | Value | 0.00 | 7.50 | 7.80 |
Date | December 31, 2008 | October 28, 2015 | July 31, 2017 | |
Comment |