Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 105.26 |
Borrower/Recipient | 66.00 |
P126487
Closed
Javier Zuleta , Renan Alberto Poveda
Secretaria de Hacienda y Credito Publico
August 3, 2011
(as of board presentation)
May 17, 2012
December 20, 2012
US$ 171.26 million
National Meteorological Service (Servicio Meteorológico Nacional) under the National Water Commissio
2012
US$ 105.26 million
B
Not Applicable
June 24, 2016
Yes
BANK APPROVED
November 14, 2022
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 105.26 |
Borrower/Recipient | 66.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 105.26 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 105.26 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 171.26 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 17, 2012 | IBRD-81650 | Loan Commitment | 105,263,160.00 |
Apr 15, 2014 | IBRD-81650 | Int Charges | 2,914.01 |
Apr 15, 2024 | IBRD-81650 | Int Charges | 152,844.66 |
Oct 15, 2023 | IBRD-81650 | Int Charges | 2,481.61 |
Oct 15, 2023 | IBRD-81650 | Int Charges | 140,484.25 |
Oct 15, 2022 | IBRD-81650 | Int Charges | 62,299.48 |
Apr 15, 2023 | IBRD-81650 | Int Charges | 4,808.79 |
Apr 15, 2023 | IBRD-81650 | Int Charges | 113,773.94 |
Apr 15, 2021 | IBRD-81650 | Int Charges | 20,204.70 |
Oct 15, 2021 | IBRD-81650 | Int Charges | 20,315.71 |
Apr 15, 2022 | IBRD-81650 | Int Charges | 18,778.47 |
Oct 15, 2020 | IBRD-81650 | Int Charges | 43,499.52 |
Oct 15, 2019 | IBRD-81650 | Int Charges | 77,199.72 |
Apr 15, 2020 | IBRD-81650 | Int Charges | 61,425.14 |
Oct 15, 2018 | IBRD-81650 | Int Charges | 72,897.56 |
Apr 15, 2019 | IBRD-81650 | Int Charges | 76,777.87 |
Apr 15, 2018 | IBRD-81650 | Int Charges | 239.00 |
Apr 15, 2018 | IBRD-81650 | Int Charges | 49,679.78 |
Apr 15, 2017 | IBRD-81650 | Int Charges | 42,073.30 |
Oct 15, 2017 | IBRD-81650 | Int Charges | 46,606.64 |
Sep 23, 2015 | IBRD-81650 | Loan Disb | 137,935.60 |
Sep 23, 2015 | IBRD-81650 | Loan Disb | 810,904.80 |
Dec 3, 2015 | IBRD-81650 | Loan Disb | 6,391.40 |
Dec 3, 2015 | IBRD-81650 | Loan Disb | 330,880.00 |
Feb 22, 2016 | IBRD-81650 | Loan Cancel | 100,561,352.00 |
Apr 15, 2016 | IBRD-81650 | Int Charges | 487.08 |
Apr 15, 2016 | IBRD-81650 | Int Charges | 22,736.00 |
Oct 15, 2016 | IBRD-81650 | Int Charges | 32,744.15 |
Apr 15, 2015 | IBRD-81650 | Int Charges | 274.78 |
Apr 15, 2015 | IBRD-81650 | Int Charges | 8,413.20 |
Apr 17, 2015 | IBRD-81650 | Loan Disb | 363,266.60 |
Oct 15, 2015 | IBRD-81650 | Int Charges | 14,070.58 |
Oct 19, 2015 | IBRD-81650 | Loan Disb | 2,300.18 |
Oct 20, 2015 | IBRD-81650 | Loan Disb | 16,928.43 |
May 12, 2014 | IBRD-81650 | Loan Disb | 289,905.00 |
Aug 27, 2014 | IBRD-81650 | Loan Disb | 292,600.00 |
Apr 20, 2015 | IBRD-81650 | Loan Disb | 188,825.95 |
Jun 9, 2015 | IBRD-81650 | Loan Disb | 270,015.53 |
Jun 9, 2015 | IBRD-81650 | Loan Disb | 36,470.26 |
Dec 16, 2014 | IBRD-81650 | Loan Disb | 241,839.61 |
Dec 23, 2014 | IBRD-81650 | Loan Disb | 302,995.00 |
Oct 15, 2014 | IBRD-81650 | Int Charges | 4,374.89 |
Oct 28, 2014 | IBRD-81650 | Loan Disb | 410,388.20 |
Oct 15, 2013 | IBRD-81650 | Int Charges | 682.27 |
Oct 15, 2013 | IBRD-81650 | Int Charges | 387.92 |
Dec 6, 2013 | IBRD-81650 | Loan Disb | 737,000.00 |
Apr 15, 2024 | IBRD-81650 | Int Charges | 1,630.84 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Unsatisfactory | 2016-06-16 |
Overall Implementation Progress (IP) | Unsatisfactory | 2016-06-16 |
Counterpart Funding | Moderately Satisfactory | 2016-06-16 |
Procurement | Unsatisfactory | 2016-06-16 |
Project Management | Unsatisfactory | 2016-06-16 |
Financial Management | Moderately Satisfactory | 2016-06-16 |
Monitoring and Evaluation | Moderately Unsatisfactory | 2016-06-16 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
SMN is operating an evaluation system using indicators to measure quality of service | Value | 0.00 | 4.00 | 10.00 |
Date | May 31, 2012 | May 25, 2016 | December 31, 2017 | |
Comment |
Accuracy of severe weather warnings increases to 80%. | Value | 0.00 | 60.00 | 0.00 |
Date | May 31, 2012 | May 25, 2016 | December 31, 2017 | |
Comment |
The percentage of climatology data generated by SMN that enters into the WMO international system used in GCM/GFM. | Value | 45.00 | 76.00 | 95.00 |
Date | May 31, 2012 | May 25, 2016 | December 31, 2017 | |
Comment |
Level of strategic clients’ satisfaction with SMN’s services increases. | Value | 20.00 | 60.00 | 80.00 |
Date | May 31, 2012 | May 25, 2016 | December 31, 2017 | |
Comment |
Availability of the telemetric weather observations system | Value | 50.00 | 75.00 | 85.00 |
Date | May 31, 2012 | May 25, 2016 | December 31, 2017 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
SMN has prepared and adopted results of an Institutional Restructuring Plan including the roadmap for piloting the creation of Regional Hydrometeorological Forecast Centers in five priority regions. | Value | No | No | Yes |
Date | May 31, 2012 | May 25, 2016 | December 31, 2017 | |
Comment |
SMN awards contract for procurement and oversees installation of new automatic weather stations (AWSs). | Value | 0.00 | 61.00 | 198.00 |
Date | May 31, 2012 | May 25, 2016 | December 31, 2017 | |
Comment |
SMN develops and begins providing climate products to specialized users (e.g., water users, farmers, municipalities). | Value | 0.00 | 10.00 | 85.00 |
Date | May 31, 2012 | May 25, 2016 | December 31, 2017 | |
Comment |
SMN prepares and implements Integrated Information and Early Warning System in 4 Pilot basins (Yaqui, Veracruzanos Rivers, Valley of Mexico Coast of Chiapas | Value | 0.00 | 0.00 | 4.00 |
Date | May 31, 2012 | May 25, 2016 | December 31, 2017 | |
Comment |