MX Moderniz of National Meteorological Serv (MOMET)

Development Objective

The Project Development Objective (PDO) is to strengthen the human resource, institutional, and infrastructural capacity of the Servicio Meteorológico Nacional to meet the increasing demand for timely and accurate weather and climate information for the purposesof water resources management and disaster risk management in the face of climate change and climate variability.

Key Details

Project Details

  • P126487

  • Closed

  • Javier Zuleta , Renan Alberto Poveda

  • Secretaria de Hacienda y Credito Publico

  • Mexico

  • August 3, 2011

  • (as of board presentation)

    May 17, 2012

  • December 20, 2012

  • US$ 171.26 million

  • National Meteorological Service (Servicio Meteorológico Nacional) under the National Water Commissio

  • Latin America and Caribbean

  • 2012

  • US$ 105.26 million

  • B

  • Not Applicable

  • June 24, 2016

  • Yes

  • BANK APPROVED

  • November 14, 2022

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 105.26
Borrower/Recipient 66.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 105.26
IDA Commitment N/A
IBRD + IDA Commitment 105.26
Lending Instrument
Grant Amount N/A
Total Project Cost** 171.26

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 17, 2012 IBRD-81650 Loan Commitment 105,263,160.00
Apr 15, 2014 IBRD-81650 Int Charges 2,914.01
Apr 15, 2024 IBRD-81650 Int Charges 152,844.66
Oct 15, 2023 IBRD-81650 Int Charges 2,481.61
Oct 15, 2023 IBRD-81650 Int Charges 140,484.25
Oct 15, 2022 IBRD-81650 Int Charges 62,299.48
Apr 15, 2023 IBRD-81650 Int Charges 4,808.79
Apr 15, 2023 IBRD-81650 Int Charges 113,773.94
Apr 15, 2021 IBRD-81650 Int Charges 20,204.70
Oct 15, 2021 IBRD-81650 Int Charges 20,315.71
Apr 15, 2022 IBRD-81650 Int Charges 18,778.47
Oct 15, 2020 IBRD-81650 Int Charges 43,499.52
Oct 15, 2019 IBRD-81650 Int Charges 77,199.72
Apr 15, 2020 IBRD-81650 Int Charges 61,425.14
Oct 15, 2018 IBRD-81650 Int Charges 72,897.56
Apr 15, 2019 IBRD-81650 Int Charges 76,777.87
Apr 15, 2018 IBRD-81650 Int Charges 239.00
Apr 15, 2018 IBRD-81650 Int Charges 49,679.78
Apr 15, 2017 IBRD-81650 Int Charges 42,073.30
Oct 15, 2017 IBRD-81650 Int Charges 46,606.64
Sep 23, 2015 IBRD-81650 Loan Disb 137,935.60
Sep 23, 2015 IBRD-81650 Loan Disb 810,904.80
Dec 3, 2015 IBRD-81650 Loan Disb 6,391.40
Dec 3, 2015 IBRD-81650 Loan Disb 330,880.00
Feb 22, 2016 IBRD-81650 Loan Cancel 100,561,352.00
Apr 15, 2016 IBRD-81650 Int Charges 487.08
Apr 15, 2016 IBRD-81650 Int Charges 22,736.00
Oct 15, 2016 IBRD-81650 Int Charges 32,744.15
Apr 15, 2015 IBRD-81650 Int Charges 274.78
Apr 15, 2015 IBRD-81650 Int Charges 8,413.20
Apr 17, 2015 IBRD-81650 Loan Disb 363,266.60
Oct 15, 2015 IBRD-81650 Int Charges 14,070.58
Oct 19, 2015 IBRD-81650 Loan Disb 2,300.18
Oct 20, 2015 IBRD-81650 Loan Disb 16,928.43
May 12, 2014 IBRD-81650 Loan Disb 289,905.00
Aug 27, 2014 IBRD-81650 Loan Disb 292,600.00
Apr 20, 2015 IBRD-81650 Loan Disb 188,825.95
Jun 9, 2015 IBRD-81650 Loan Disb 270,015.53
Jun 9, 2015 IBRD-81650 Loan Disb 36,470.26
Dec 16, 2014 IBRD-81650 Loan Disb 241,839.61
Dec 23, 2014 IBRD-81650 Loan Disb 302,995.00
Oct 15, 2014 IBRD-81650 Int Charges 4,374.89
Oct 28, 2014 IBRD-81650 Loan Disb 410,388.20
Oct 15, 2013 IBRD-81650 Int Charges 682.27
Oct 15, 2013 IBRD-81650 Int Charges 387.92
Dec 6, 2013 IBRD-81650 Loan Disb 737,000.00
Apr 15, 2024 IBRD-81650 Int Charges 1,630.84

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Unsatisfactory 2016-06-16
Overall Implementation Progress (IP) Unsatisfactory 2016-06-16
Counterpart Funding Moderately Satisfactory 2016-06-16
Procurement Unsatisfactory 2016-06-16
Project Management Unsatisfactory 2016-06-16
Financial Management Moderately Satisfactory 2016-06-16
Monitoring and Evaluation Moderately Unsatisfactory 2016-06-16

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • SMN is operating an evaluation system using indicators to measure quality of serviceValue0.004.0010.00
    DateMay 31, 2012May 25, 2016December 31, 2017
    Comment
  • Accuracy of severe weather warnings increases to 80%.Value0.0060.000.00
    DateMay 31, 2012May 25, 2016December 31, 2017
    Comment
  • The percentage of climatology data generated by SMN that enters into the WMO international system used in GCM/GFM.Value45.0076.0095.00
    DateMay 31, 2012May 25, 2016December 31, 2017
    Comment
  • Level of strategic clients’ satisfaction with SMN’s services increases.Value20.0060.0080.00
    DateMay 31, 2012May 25, 2016December 31, 2017
    Comment
  • Availability of the telemetric weather observations systemValue50.0075.0085.00
    DateMay 31, 2012May 25, 2016December 31, 2017
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • SMN has prepared and adopted results of an Institutional Restructuring Plan including the roadmap for piloting the creation of Regional Hydrometeorological Forecast Centers in five priority regions.ValueNoNoYes
    DateMay 31, 2012May 25, 2016December 31, 2017
    Comment
  • SMN awards contract for procurement and oversees installation of new automatic weather stations (AWSs).Value0.0061.00198.00
    DateMay 31, 2012May 25, 2016December 31, 2017
    Comment
  • SMN develops and begins providing climate products to specialized users (e.g., water users, farmers, municipalities).Value0.0010.0085.00
    DateMay 31, 2012May 25, 2016December 31, 2017
    Comment
  • SMN prepares and implements Integrated Information and Early Warning System in 4 Pilot basins (Yaqui, Veracruzanos Rivers, Valley of Mexico Coast of ChiapasValue0.000.004.00
    DateMay 31, 2012May 25, 2016December 31, 2017
    Comment