Skip to Main Navigation

Additional Financing to IREP

Development Objective

The revised development objectives are: (i) to improve water use efficiency in the selected irrigation schemes; and (ii) to foster immediate rural employment.

Key Details

Project Details

  • P126509

  • Closed

  • Giuseppe Fantozzi

  • N/A

  • Armenia

  • August 17, 2011

  • (as of board presentation)

    October 25, 2011

  • N/A

  • US$ 18.00 million

  • B

  • Not Applicable

  • January 30, 2013

  • BANK APPROVED

  • P116681

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 18.00
Local Beneficiaries 0.20
Borrower/Recipient 3.40

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 18.00
IDA Commitment N/A
IBRD + IDA Commitment 18.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 21.60

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of permanent agricultural jobs createdValue2400.000.003250.00
    DateAugust 11, 2011June 30, 2013
    CommentUnder AF overall possible increase in agricultural area due to saved water would be about 6,400 ha. However, only 20% of thepotential increase may occur in each year due to associated investment costs. Therefore, by the end of the Project– which is two agricultural seasons– only about 40% (2,600 ha) may bebrought back to irrigation and consequently the estimated agricultural jobs would about 850 with a possibility to become around2,100 in 3 years after Project closing.
  • Amount of wages generated (only for construction workers)Value5450000.000.008200000.00
    DateAugust 11, 2011June 30, 2013
    CommentUnder IREP the actual result is US$5.4 million; the original target was US$4.5 million.The new target is set based on the original target.
  • Direct project beneficiariesValue30000.000.00118000.00
    DateAugust 11, 2011June 30, 2013
    CommentDirect project beneficiaries are water users. The baseline value is a number of beneficiaries under IREP.
  • Female beneficiariesValue4.000.007.50
    DateAugust 11, 2011June 30, 2013
    Comment
  • Reduction of water losses in the selected schemesValue40400000.000.006100000.00
    DateAugust 11, 2011June 30, 2013
    Comment
  • Number of temporary person-months jobs createdValue11379.000.0016000.00
    DateAugust 11, 2011June 30, 2013
    CommentUnder IREP the actual result is 11,379 person/month but the original target was 9,000.The new target is set based on the original target.

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Potential increase of total irrigation area as a result of rehabilitation works on main/secondary canalsValue31195.000.0049095.00
    DateAugust 11, 2011June 30, 2013
    CommentUnder AF overall potential increase in agricultural area due to saved water in main and secondary canals would be about 4,700 ha.However, only 20% of potential increase may occur each year due to associated investment costs. Therefore, by end-Project– two agricultural seasons – only about 40% (1,880 ha) may be brought back toirrigation though potentially in five yearsit would bepossible to reach 52,000 ha.
  • Restored irrigation area in communities with rehabilitated tertiary network.Value0.000.00704.00
    DateAugust 11, 2011June 30, 2013
    CommentUnder AF overall potential increase in agricultural area due to saved water in tertiary canals would be about 1,760 ha. However,only 20% of potential increase may occur each year due to associated investment costs. Therefore, by end-Project– two agriculturalseasons – only about 40% (704 ha) may be brought back toirrigation.
  • Developed WUA business plansValue0.000.0044.00
    DateAugust 11, 2011December 31, 2011
    CommentThis activity started under IREP and will be completed by end 2011.
  • Subsidy policy studyValueNoYes
    DateAugust 11, 2011December 31, 2011
    CommentThis activity started under IREP and will be completed by end 2011.
  • GIS WUA information system in place nation wideValueYes
    DateAugust 11, 2011
    CommentThis activity has been completed.