Financier | Commitments |
---|---|
Special Financing | 3.00 |
P126586
Closed
Jana Hughes Malinska , Abdalwahab Khatib
Palestinian Liberation Organization (for the Benefit of the Palestinian Authority)
November 3, 2011
(as of board presentation)
May 8, 2012
January 11, 2013
US$ 3.00 million
Ministry of National Economy
2012
US$ 3.00 million
C
February 27, 2020
February 2, 2016
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Special Financing | 3.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 3.00 |
Total Project Cost** | 3.00 |
Name | Review | Date |
---|---|---|
Financial Management | Moderately Unsatisfactory | 2015-11-06 |
Overall Implementation Progress (IP) | Unsatisfactory | 2015-11-06 |
Procurement | Moderately Satisfactory | 2015-11-06 |
Monitoring and Evaluation | Moderately Unsatisfactory | 2015-11-06 |
Overall | High | 2015-11-06 |
Progress towards achievement of PDO | Unsatisfactory | 2015-11-06 |
Project Management | Moderately Unsatisfactory | 2015-11-06 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-18-2016 |
---|---|
Outcomes | Unsatisfactory |
Risk to Development Outcome | High |
Bank Performance | Moderately Unsatisfactory |
Borrower Performance | Unsatisfactory |
Government Performance | Not Applicable |
Implementing Agency | Not Applicable |
INDICATOR | ICR REVIEW: 03-27-2017 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Unsatisfactory | N/a |
Risk To Development Outcome | High | N/a |
Bank Performance | Moderately Unsatisfactory | N/a |
Borrower Performance | Unsatisfactory | N/a |
Government Performance | Unsatisfactory | N/a |
Implementing Agency | Unsatisfactory | N/a |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Creation of a competently staffed Business Development Unit to promote private sector development. | Value | No | No | No |
Date | November 28, 2012 | October 23, 2015 | June 30, 2016 | |
Comment |
BDU regularly planned 1 annual and 1 quarterly papers relevant to Palestinian private sector development are published within one month of a set deadline | Value | No | No | No |
Date | November 28, 2012 | October 23, 2015 | June 30, 2016 | |
Comment |
Increase in the number of firms (MSMEs, women, marginalized) receiving MoNE services to plan for business development | Value | 0.00 | 0.00 | 300.00 |
Date | October 23, 2015 | June 30, 2016 | ||
Comment |
% satisfaction of MoNE clients with the quality of services provided (web-based survey upon service delivery) | Value | 0.00 | 0.00 | 60.00 |
Date | November 28, 2012 | October 23, 2015 | June 30, 2016 | |
Comment |
Direct project beneficiaries | Value | 0.00 | 0.00 | 330.00 |
Date | November 28, 2012 | October 23, 2015 | June 30, 2016 | |
Comment |
Female beneficiaries | Value | 0.00 | 0.00 | 110.00 |
Date | November 28, 2012 | October 23, 2015 | June 30, 2016 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
% of firms that receive information that are women-owned | Value | 0.00 | 0.00 | 20.00 |
Date | November 28, 2012 | October 23, 2015 | June 30, 2016 | |
Comment |
% of businesses that receive information that are outside Ramallah | Value | 0.00 | 0.00 | 20.00 |
Date | November 28, 2012 | October 23, 2015 | June 30, 2016 | |
Comment |
Business Development Working Group created (end Y1), Business Development Strategy Prepared (end Y2), implemented (from Y3 onwards)and monitored and evaluated (by end of Y3) | Value | 20151023 | 20160623 | |
Date | October 23, 2015 | June 30, 2016 | ||
Comment |
MoNE internal applications are modernized (by end Y1), website updated (by end Y2) and portal built and operating (by end Y3) | Value | 20151023 | 20160630 | |
Date | October 23, 2015 | June 30, 2016 | ||
Comment |
Gradual increase in the number of visitors to the new MoNE website and portal | Value | 0.00 | 0.00 | 400.00 |
Date | November 28, 2012 | October 23, 2015 | June 30, 2016 | |
Comment |
% of MoNE business forms available online | Value | 0.00 | 0.00 | 50.00 |
Date | November 28, 2012 | October 23, 2015 | June 30, 2016 | |
Comment |
Semi-annual project progress reports, including an M&E section, are produced on a timely and satisfactory basis | Value | No | Yes | |
Date | October 23, 2015 | June 30, 2016 | ||
Comment |