Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 200.00 |
P126749
Closed
Josef Leitmann
Municipality of Belo Horizonte
November 8, 2011
(as of board presentation)
June 14, 2013
December 16, 2013
US$ 200.00 million
Municipality of Belo Horizonte
2013
US$ 200.00 million
N/A
Not Applicable
December 31, 2014
BANK APPROVED
August 8, 2014
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 200.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 200.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 200.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 200.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 15, 2018 | IBRD-81690 | Int Charges | 2,395,504.20 |
Jun 15, 2019 | IBRD-81690 | Loan Repay | 2,000,000.00 |
Dec 15, 2018 | IBRD-81690 | Int Charges | 1,139,039.60 |
Dec 15, 2018 | IBRD-81690 | Loan Repay | 2,000,000.00 |
Dec 15, 2018 | IBRD-81690 | Int Charges | 2,000,000.00 |
Jun 15, 2017 | IBRD-81690 | Int Charges | 1,907,468.20 |
Jun 15, 2017 | IBRD-81690 | Loan Repay | 740,000.00 |
Dec 15, 2017 | IBRD-81690 | Loan Repay | 1,000,000.00 |
Dec 15, 2017 | IBRD-81690 | Int Charges | 2,070,828.00 |
Jun 15, 2016 | IBRD-81690 | Int Charges | 1,313,604.50 |
Jun 15, 2016 | IBRD-81690 | Loan Repay | 500,000.00 |
Dec 15, 2016 | IBRD-81690 | Int Charges | 1,521,964.20 |
Dec 15, 2016 | IBRD-81690 | Loan Repay | 740,000.00 |
Dec 15, 2015 | IBRD-81690 | Int Charges | 982,616.50 |
Dec 15, 2015 | IBRD-81690 | Loan Repay | 500,000.00 |
Dec 13, 2013 | IBRD-81690 | Fee Charges | 500,000.00 |
Dec 20, 2013 | IBRD-81690 | Loan Disb | 200,000,000.00 |
Dec 15, 2014 | IBRD-81690 | Int Charges | 802,202.90 |
Jun 15, 2014 | IBRD-81690 | Int Charges | 796,500.00 |
Jun 15, 2014 | IBRD-81690 | Loan Repay | 240,000.00 |
Dec 15, 2014 | IBRD-81690 | Loan Repay | 240,000.00 |
Jun 15, 2015 | IBRD-81690 | Int Charges | 847,294.94 |
Jun 15, 2015 | IBRD-81690 | Loan Repay | 240,000.00 |
Jun 15, 2024 | IBRD-81690 | Int Charges | 4,968,027.50 |
Jun 15, 2024 | IBRD-81690 | Loan Repay | 4,999,999.00 |
Jun 15, 2024 | IBRD-81690 | Int Charges | 175,155.44 |
Jun 15, 2024 | IBRD-81690 | Int Charges | 31,972.45 |
Jun 14, 2013 | IBRD-81690 | Loan Commitment | 200,000,000.00 |
Dec 15, 2022 | IBRD-81690 | Int Charges | 3,131,065.00 |
Dec 15, 2022 | IBRD-81690 | Loan Repay | 868,934.94 |
Dec 15, 2022 | IBRD-81690 | Loan Repay | 3,131,065.00 |
Jun 15, 2023 | IBRD-81690 | Int Charges | 215,964.81 |
Jun 15, 2023 | IBRD-81690 | Int Charges | 4,474,895.00 |
Jun 15, 2023 | IBRD-81690 | Loan Repay | 4,000,000.00 |
Dec 15, 2023 | IBRD-81690 | Int Charges | 87,640.79 |
Dec 15, 2023 | IBRD-81690 | Int Charges | 5,005,794.50 |
Dec 15, 2023 | IBRD-81690 | Loan Repay | 5,000,000.00 |
Jun 15, 2022 | IBRD-81690 | Loan Repay | 899,808.00 |
Jun 15, 2022 | IBRD-81690 | Int Charges | 899,808.00 |
Jun 15, 2022 | IBRD-81690 | Loan Repay | 3,100,192.00 |
Dec 15, 2021 | IBRD-81690 | Int Charges | 790,885.30 |
Dec 15, 2021 | IBRD-81690 | Loan Repay | 3,209,114.80 |
Dec 15, 2021 | IBRD-81690 | Loan Repay | 790,885.30 |
Dec 15, 2020 | IBRD-81690 | Int Charges | 1,042,734.00 |
Dec 15, 2020 | IBRD-81690 | Loan Repay | 4,000,000.00 |
Jun 15, 2021 | IBRD-81690 | Loan Repay | 868,342.25 |
Jun 15, 2021 | IBRD-81690 | Int Charges | 868,342.25 |
Jun 15, 2021 | IBRD-81690 | Loan Repay | 3,131,657.80 |
Dec 15, 2019 | IBRD-81690 | Int Charges | 2,929,098.00 |
Dec 15, 2019 | IBRD-81690 | Loan Repay | 3,000,000.00 |
Jun 15, 2020 | IBRD-81690 | Int Charges | 2,462,997.00 |
Jun 15, 2020 | IBRD-81690 | Loan Repay | 3,000,000.00 |
Jun 15, 2019 | IBRD-81690 | Int Charges | 3,499,213.00 |
Jun 15, 2018 | IBRD-81690 | Loan Repay | 1,000,000.00 |
Name | Review | Date |
---|---|---|
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2015-04-27 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2015-04-27 |
Program Management | Moderately Satisfactory | 2015-04-27 |
Monitoring and Evaluation | Moderately Unsatisfactory | 2015-04-27 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 05-29-2015 |
---|---|
Outcomes | Moderately Unsatisfactory |
Risk to Development Outcome | Modest |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Moderately Satisfactory |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 06-23-2016 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Unsatisfactory | N/a |
Risk To Development Outcome | Moderate | N/a |
Bank Performance | Moderately Unsatisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Exemplary | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Effective demand of projects decided by the community that are includeed in the city's multi-year plan. | Value | 0.00 | 72.00 | 25.00 |
Date | January 1, 2011 | December 5, 2014 | December 31, 2013 | |
Comment |
Increase in the number of civil society participants in participatory processes (OP Digital, OP Regional, PPR) | Value | 10.00 | 2.44 | 15.00 |
Date | January 1, 2011 | December 5, 2014 | December 31, 2013 | |
Comment |
Civil servants retirement plan actuarial deficit | Value | 3466500000.00 | 5293000000.00 | 3428500000.00 |
Date | January 1, 2010 | December 5, 2014 | December 31, 2013 | |
Comment |
Number of households benefiting from land regularization between 2009 and 2013. | Value | 8768.00 | 16342.00 | 12155.00 |
Date | January 1, 2011 | December 5, 2014 | December 31, 2013 | |
Comment |
Number of new housing starts of formally developed low-income housing units. | Value | 1470.00 | 13575.00 | 5302.00 |
Date | January 1, 2011 | December 5, 2014 | December 31, 2013 | |
Comment |
Number of plots transferred by CAIXA | Value | 0.00 | 2325.00 | 1470.00 |
Date | January 1, 2011 | December 5, 2014 | December 31, 2013 | |
Comment |
Number of people remaining in social housing developments after 2 years | Value | 75.00 | 86.00 | 85.00 |
Date | January 1, 2011 | December 5, 2014 | December 31, 2013 | |
Comment |
Number of families with a dedicated action plan implemented | Value | 750.00 | 750.00 | 1500.00 |
Date | January 1, 2011 | December 5, 2014 | December 31, 2013 | |
Comment |
Percentage of female-headed households with a dedicated action plan | Value | 0.00 | 68.00 | 60.00 |
Date | January 1, 2011 | December 5, 2014 | December 31, 2013 | |
Comment |
Number of rehabilitated homes as a result of the program | Value | 0.00 | 24.00 | 250.00 |
Date | December 1, 2011 | December 5, 2014 | December 31, 2013 | |
Comment |
Number of services rendered at BH Resolve units | Value | 94678.00 | 92064.00 | 148500.00 |
Date | January 1, 2011 | December 5, 2014 | December 31, 2013 | |
Comment |
Percentage of users rating the services rendered as good or excellent at BH Resolve units | Value | 0.00 | 97.65 | 90.00 |
Date | January 1, 2011 | October 31, 2014 | December 31, 2013 | |
Comment |
Municipal Change Climate Action Plan that integrates and benchmarks existing sector-specific initiatives in solid waste, water, energy and urban forestry sectors | Value | 0.00 | 1.00 | 1.00 |
Date | January 1, 2011 | December 5, 2014 | December 31, 2013 | |
Comment |
Consolidated database of: (i) hydrological and climate-related parameters; and (ii) disaster events and damages. | Value | 0.00 | 0.50 | 1.00 |
Date | January 1, 2011 | December 5, 2014 | December 31, 2013 | |
Comment |
Number of monthly performance reports of the early warning system issued | Value | 0.00 | 12.00 | 12.00 |
Date | January 1, 2011 | December 5, 2014 | December 31, 2013 | |
Comment |
Percentage of results completed yearly according to schedule | Value | 33.00 | 68.50 | 70.00 |
Date | January 1, 2011 | December 5, 2014 | December 31, 2013 | |
Comment |