Financier | Commitments |
---|---|
Borrower/Recipient | 327.19 |
International Bank for Reconstruction and Development | 150.00 |
P126856
Closed
Xiaokai Li , Qi Tian
The People's Republic of China
January 17, 2012
(as of board presentation)
March 20, 2013
July 19, 2013
US$ 301.30 million
Jiangxi Provincial Development and Reform Committee
2013
US$ 150.00 million
B
April 22, 2024
December 31, 2019
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Borrower/Recipient | 327.19 |
International Bank for Reconstruction and Development | 150.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 150.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 150.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 301.30 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 15, 2014 | IBRD-82340 | Int Charges | 537.71 |
Sep 15, 2014 | IBRD-82340 | Int Charges | 0.01 |
Sep 15, 2014 | IBRD-82340 | Int Charges | 50,599.99 |
Mar 10, 2015 | IBRD-82340 | Loan Disb | 10,165,144.00 |
Mar 15, 2015 | IBRD-82340 | Int Charges | 76,600.28 |
Oct 16, 2015 | IBRD-82340 | Loan Disb | 10,858,657.00 |
Sep 15, 2015 | IBRD-82340 | Int Charges | 1,171.82 |
Mar 15, 2024 | IBRD-82340 | Int Charges | 4,375,539.00 |
Mar 15, 2024 | IBRD-82340 | Loan Repay | 3,225,000.00 |
Sep 15, 2015 | IBRD-82340 | Int Charges | 147,341.64 |
Mar 15, 2024 | IBRD-82340 | Int Charges | 70,881.33 |
Mar 20, 2013 | IBRD-82340 | Loan Commitment | 150,000,000.00 |
Sep 15, 2021 | IBRD-82340 | Int Charges | 697,666.70 |
Sep 15, 2021 | IBRD-82340 | Loan Repay | 2,850,000.00 |
Mar 15, 2022 | IBRD-82340 | Int Charges | 651,057.00 |
Mar 15, 2022 | IBRD-82340 | Loan Repay | 2,925,000.00 |
Sep 15, 2022 | IBRD-82340 | Loan Repay | 3,000,000.00 |
Sep 15, 2022 | IBRD-82340 | Int Charges | 1,353,563.10 |
Mar 15, 2023 | IBRD-82340 | Int Charges | 164,502.44 |
Mar 15, 2023 | IBRD-82340 | Int Charges | 3,563,087.80 |
Mar 15, 2023 | IBRD-82340 | Loan Repay | 3,075,000.00 |
Sep 15, 2023 | IBRD-82340 | Int Charges | 53,939.13 |
Sep 15, 2023 | IBRD-82340 | Int Charges | 4,032,068.00 |
Sep 15, 2023 | IBRD-82340 | Loan Repay | 3,150,000.00 |
Sep 15, 2020 | IBRD-82340 | Int Charges | 1,088,666.60 |
Mar 15, 2021 | IBRD-82340 | Int Charges | 739,083.30 |
Jan 24, 2019 | IBRD-82340 | Loan Disb | 11,366,615.00 |
Mar 15, 2019 | IBRD-82340 | Int Charges | 54,012.01 |
Mar 15, 2019 | IBRD-82340 | Int Charges | 1,907,403.90 |
Sep 15, 2019 | IBRD-82340 | Int Charges | 51,307.62 |
Sep 15, 2019 | IBRD-82340 | Int Charges | 2,212,943.50 |
Sep 12, 2019 | IBRD-82340 | Loan Disb | 11,688,998.00 |
Dec 11, 2019 | IBRD-82340 | Loan Disb | 7,872,765.50 |
Mar 15, 2020 | IBRD-82340 | Int Charges | 3,292.40 |
Mar 15, 2020 | IBRD-82340 | Int Charges | 2,006,812.40 |
Dec 30, 2019 | IBRD-82340 | Loan Disb | 2,341,424.80 |
Nov 13, 2017 | IBRD-82340 | Loan Disb | 10,083,403.00 |
Sep 15, 2017 | IBRD-82340 | Int Charges | 723,667.56 |
Feb 2, 2018 | IBRD-82340 | Loan Disb | 11,147,650.00 |
Mar 15, 2018 | IBRD-82340 | Int Charges | 859,510.06 |
Sep 14, 2018 | IBRD-82340 | Loan Disb | 9,282,693.00 |
Jul 23, 2018 | IBRD-82340 | Loan Disb | 11,992,966.00 |
Sep 15, 2018 | IBRD-82340 | Int Charges | 26,788.42 |
Sep 15, 2018 | IBRD-82340 | Int Charges | 1,444,121.10 |
Mar 15, 2016 | IBRD-82340 | Int Charges | 220,458.84 |
Sep 15, 2016 | IBRD-82340 | Int Charges | 356,426.60 |
Jun 20, 2016 | IBRD-82340 | Loan Disb | 11,129,841.00 |
Dec 7, 2016 | IBRD-82340 | Loan Disb | 10,521,461.00 |
Mar 15, 2017 | IBRD-82340 | Int Charges | 548,781.44 |
Jun 23, 2017 | IBRD-82340 | Loan Disb | 10,715,988.00 |
Jul 19, 2013 | IBRD-82340 | Loan Disb | 375,000.00 |
Jul 19, 2013 | IBRD-82340 | Fee Charges | 375,000.00 |
Nov 7, 2014 | IBRD-82340 | Loan Disb | 8,457,395.00 |
Jan 14, 2014 | IBRD-82340 | Loan Disb | 12,000,000.00 |
Mar 15, 2014 | IBRD-82340 | Int Charges | 18,602.60 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2019-12-18 |
Project Management | Satisfactory | 2019-12-18 |
Financial Management | Satisfactory | 2019-12-18 |
Monitoring and Evaluation | Satisfactory | 2019-12-18 |
Procurement | Satisfactory | 2019-12-18 |
Counterpart Funding | Satisfactory | 2019-12-18 |
Overall Implementation Progress (IP) | Satisfactory | 2019-12-18 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-23-2020 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 02-16-2021 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | High | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
PO-1. Increased population with access to newly built or rehabilitated roads. | Value | 0.00 | 565850.00 | 478000.00 |
Date | June 21, 2013 | December 31, 2019 | December 21, 2016 | |
Comment |
PO-2. The number of population protected from flooding. | Value | 0.00 | 99880.00 | 100000.00 |
Date | June 21, 2013 | December 31, 2019 | June 23, 2018 | |
Comment |
PO-3. Annual Reduction of COD entering Poyang Lake | Value | 0.00 | 110.25 | 40.00 |
Date | June 21, 2013 | December 31, 2019 | June 21, 2013 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
IO 1.1 Length of newly built/upgraded roads | Value | 0.00 | 66.11 | 65.00 |
Date | June 21, 2013 | December 31, 2019 | December 21, 2016 | |
Comment |
IO-2.1 Length of dike strengthened | Value | 0.00 | 29.35 | 29.35 |
Date | June 21, 2013 | December 31, 2019 | June 23, 2018 | |
Comment |
IO-3.1 Number of officials, experts and PMO staff participating in domestic and overseas study tours, TA and targeted training programs | Value | 0.00 | 2617.00 | 2000.00 |
Date | June 21, 2013 | December 31, 2019 | June 8, 2018 | |
Comment |
IO-2.2 Increase in Area Protected from Flood | Value | 0.00 | 17680.00 | 17052.00 |
Date | June 21, 2013 | December 31, 2019 | June 23, 2018 | |
Comment |
IO-3.2 Number of counties with traffic/transportation master plans completed and applied | Value | 0.00 | 3.00 | 0.00 |
Date | June 21, 2013 | December 31, 2019 | ||
Comment |
Road constructed, non-rural | Value | 0.00 | 66.11 | 65.00 |
Date | June 21, 2013 | December 31, 2019 | December 21, 2016 | |
Comment |
Road constructed, non-rural | Value | 0.00 | 66.11 | 65.00 |
Date | June 21, 2013 | December 31, 2019 | December 21, 2016 | |
Comment |
IO-1.2 Travel time saved (minutes per trip) | Value | 0.00 | 160.90 | 152.00 |
Date | June 21, 2013 | December 31, 2019 | December 21, 2016 | |
Comment |
IO-2.4 Increased area of improved wetland | Value | 0.00 | 128.63 | 160.00 |
Date | June 21, 2013 | December 31, 2019 | June 21, 2013 | |
Comment |
IO-3.3 Number of counties with flood control and management plans completed and applied | Value | 0.00 | 2.00 | 0.00 |
Date | June 21, 2013 | December 31, 2019 | ||
Comment |
IO-2.5 Reduced Annual Wastewater Flow into Poyang Lake from the Mianjiang River tributary | Value | 0.00 | 18666000.00 | 18800000.00 |
Date | June 21, 2013 | December 31, 2019 | June 21, 2013 | |
Comment |