China Renewable Energy Scale-Up Program Phase II

Abstract*

The development objective of the Second Phase of Renewable Energy Scaling-Up Program Project for China is to support the ambitious renewable energy scale-up program in China with a focus on efficiency improvement and reduction of incremental costs. There are five components to the project. The first component of the project is policy support. This will support developing and implementing Renewable Energy (RE) legislation and policies to achieve cost...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective of the CRESP program (three phases) is to enable commercial renewable electricity suppliers to provide energy to the electricity market efficiently, cost-effectively and on a large scale. The objective of CRESP Phase II is to support the ambitious renewable energy scale-up program in China with a focus on efficiency improvement and reduction of incremental costs.

Key Details

Project Details

  • P127033

  • Closed

  • Yanqin Song , Xiaodong Wang

  • People's Republic of China

  • China

  • December 28, 2011

  • (as of board presentation)

    October 29, 2013

  • December 26, 2013

  • US$ 27.28 million

  • National Energy Administration

  • East Asia and Pacific

  • 2014

  • US$ 27.28 million

  • C

  • October 31, 2022

  • December 31, 2021

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Global Environment Facility (GEF) 27.28

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 27.28
Total Project Cost** 27.28

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Summary Global Objective Rating Highly Satisfactory 2021-06-24
Procurement Satisfactory 2021-06-24
Project Management Satisfactory 2021-06-24
Financial Management Moderately Satisfactory 2021-06-24
Monitoring and Evaluation Satisfactory 2021-06-24
Overall Implementation Progress (IP) Satisfactory 2021-06-24

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 10-31-2022
OutcomesHighly Satisfactory
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 04-07-2023PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingHighly Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Additional RE-based power generation from improved design of the large wind bases (GWh)Value0.001078.000.00
    DateJanuary 31, 2013June 15, 2021
    Comment
  • Additional RE consumption from increased RE penetration in New Energy Cities (Mtce)Value0.003.900.00
    DateJanuary 31, 2013June 15, 2021
    Comment
  • Annual avoided carbon dioxide emission reduction(million tons)Value0.009.200.00
    DateJanuary 31, 2013June 15, 2021
    Comment
  • Reduced incremental costs of wind power over coal-fired power plants (cent/kWh USD)Value2.170.160.00
    DateNovember 30, 2012August 14, 2020
    Comment
  • Reduced incremental costs of solar PV over coal-fired power plants (cent/kWh USD)Value11.300.610.00
    DateNovember 30, 2012August 14, 2020
    Comment
  • RE 13th FYP developed and adoptedValue2013013120161216
    DateJanuary 31, 2013July 28, 2020
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • RE quota policy issuedValue2013013120190515
    DateJanuary 31, 2013June 28, 2019
    Comment
  • Increased penetration of wind power generation in Inner Mongolia (percentage of wind power generation in total provincial power consumption)Value13.0015.000.00
    DateJanuary 31, 2013June 15, 2021
    Comment
  • Number of Chinese off-shore wind turbine standards accepted by Standardization Administration of ChinaValue0.003.000.00
    DateJanuary 31, 2013June 15, 2021
    Comment
  • New Energy City policy submittedValue2013013120160215
    DateJanuary 31, 2013February 15, 2016
    Comment
  • Number of RE investment projects supportedValue0.0012.002.00
    DateJanuary 31, 2013June 15, 2021
    Comment
  • RE 14th FYP developedValue2013013120210615
    DateJanuary 31, 2013June 15, 2021
    Comment
  • Design for China’s first off-shore wind testing center aligned with international best practicesValueNoNo
    DateJanuary 31, 2013June 15, 2021
    Comment