Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 4.20 |
P127258
Closed
Philippe Dardel , Paola Agostini, Amadou Alassane
The Ministry of Finance
February 11, 2013
(as of board presentation)
April 30, 2013
June 8, 2012
US$ 4.20 million
Ministry of Agriculture and Livestock
2013
US$ 4.20 million
B
N/A
October 30, 2018
No
BANK APPROVED
August 30, 2024
Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 4.20 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 4.20 |
Total Project Cost** | 4.20 |
Name | Review | Date |
---|---|---|
Overall Implementation Progress (IP) | Satisfactory | 2018-04-19 |
Procurement | Satisfactory | 2018-04-19 |
Summary Global Objective Rating | Satisfactory | 2018-04-19 |
Financial Management | Satisfactory | 2018-04-19 |
Monitoring and Evaluation | Satisfactory | 2018-04-19 |
Project Management | Satisfactory | 2018-04-19 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 04-29-2019 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 06-28-2019 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Land area where sustainable land mgt. practices were adopted as a result of proj | Value | 0.00 | 4656.08 | 2200.00 |
Date | August 21, 2013 | October 30, 2018 | ||
Comment |
Environmentally friendly effluent control systems implemented in selected CWS as a result of the project | Value | 0.00 | 6.00 | 2.00 |
Date | August 21, 2013 | October 30, 2018 | ||
Comment |
Direct project beneficiaries | Value | 0.00 | 17971.00 | 7000.00 |
Date | August 21, 2013 | October 30, 2018 | ||
Comment |
Female beneficiaries | Value | 0.00 | 39.70 | 0.00 |
Date | August 21, 2013 | October 30, 2018 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Target population trained in SLWM, shade- grown coffee, and biodiversity conservation practices as a result of the project | Value | 0.00 | 23506.00 | 14000.00 |
Date | August 21, 2013 | October 30, 2018 | ||
Comment |
Research demonstration sites for shade-grown coffee | Value | 0.00 | 61.00 | 6.00 |
Date | August 21, 2013 | October 30, 2018 | ||
Comment |
Improved biodiversity conservation in the protected area as measured by the PAMETT | Value | 0.00 | 80.00 | 0.00 |
Date | August 21, 2013 | October 30, 2018 | ||
Comment |
GEF tracking tools updated (SFM, Land Degrad., Biodiversity 1 and2) | Value | 0.00 | 4.00 | 0.00 |
Date | August 21, 2013 | October 30, 2018 | ||
Comment |
Submission for adoption of new environmental regulations for CWS | Value | No | Yes | |
Date | August 21, 2013 | October 30, 2018 | ||
Comment |
Capacity building program to enhance enforcement and monitoring of environmental and social standards | Value | No | Yes | Yes |
Date | August 21, 2013 | October 30, 2018 | ||
Comment |
CWS meet national effluent discharge standards as a result of the project | Value | No | No | |
Date | August 21, 2013 | October 30, 2018 | ||
Comment |
Contracts signed by the CWS with a certification agency | Value | No | No | Yes |
Date | August 21, 2013 | October 30, 2018 | ||
Comment |
20% increase in the number of certification indicators met by farmers each year (specific indicators will depend on the certification scheme selected). | Value | No | Yes | |
Date | August 21, 2013 | October 30, 2018 | ||
Comment |
M&E system functioning and providing accurate and on-time data (including impact evaluation) | Value | No | Yes | Yes |
Date | August 21, 2013 | October 30, 2018 | ||
Comment |
Communication plan designed and implemented | Value | No | Yes | Yes |
Date | August 21, 2013 | October 30, 2018 | ||
Comment |