Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 479.00 |
Borrower/Recipient | 184.90 |
P127741
Closed
Ditte Fallesen
Republic of the Philippines
April 23, 2012
(as of board presentation)
February 20, 2014
June 13, 2014
US$ 663.90 million
Department of Social Welfare and Development
2014
US$ 479.00 million
B
May 15, 2024
December 31, 2024
Yes
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 479.00 |
Borrower/Recipient | 184.90 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 479.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 479.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 663.90 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Aug 15, 2014 | IBRD-83350 | Int Charges | 1,676.50 |
Jan 23, 2017 | IBRD-83350 | Loan Disb | 8,000,000.00 |
Jun 10, 2016 | IBRD-83350 | Loan Disb | 15,575,971.00 |
Sep 9, 2016 | IBRD-83350 | Loan Disb | 30,286,624.00 |
Apr 1, 2016 | IBRD-83350 | Loan Disb | 20,220,000.00 |
Aug 15, 2016 | IBRD-83350 | Int Charges | 1,262,650.80 |
Jun 29, 2015 | IBRD-83350 | Loan Disb | 14,682,139.00 |
Aug 4, 2015 | IBRD-83350 | Loan Disb | 28,277,162.00 |
Dec 11, 2015 | IBRD-83350 | Loan Disb | 12,949,243.00 |
Feb 15, 2016 | IBRD-83350 | Int Charges | 25,305.81 |
Feb 15, 2016 | IBRD-83350 | Int Charges | 796,224.40 |
Jul 31, 2014 | IBRD-83350 | Loan Disb | 22,000,000.00 |
Aug 15, 2015 | IBRD-83350 | Int Charges | 94,837.85 |
Aug 15, 2015 | IBRD-83350 | Int Charges | 448,319.94 |
Aug 15, 2024 | IBRD-83350 | Loan Repay | 14,337,043.00 |
Nov 17, 2023 | IBRD-83350 | Loan Disb | 430,541,824.00 |
Nov 20, 2023 | IBRD-91910 | Loan Disb | 267,070,976.00 |
Jun 1, 2024 | IBRD-91910 | Int Charges | 446,379.47 |
Jun 1, 2024 | IBRD-91910 | Int Charges | 7,833,414.50 |
Feb 15, 2024 | IBRD-83350 | Int Charges | 5,726,206.50 |
Aug 15, 2024 | IBRD-83350 | Int Charges | 11,775,558.00 |
Dec 1, 2023 | IBRD-91910 | Int Charges | 169,297.67 |
Dec 1, 2023 | IBRD-91910 | Int Charges | 41,274.06 |
Aug 15, 2018 | IBRD-83350 | Int Charges | 82,055.41 |
Aug 15, 2018 | IBRD-83350 | Int Charges | 5,428,196.00 |
Jan 5, 2018 | IBRD-83350 | Loan Disb | 34,146,280.00 |
Feb 15, 2018 | IBRD-83350 | Int Charges | 120,115.71 |
Feb 15, 2018 | IBRD-83350 | Int Charges | 3,798,038.80 |
Oct 4, 2017 | IBRD-83350 | Loan Disb | 23,604,930.00 |
Aug 15, 2017 | IBRD-83350 | Int Charges | 9,251.10 |
Aug 15, 2017 | IBRD-83350 | Int Charges | 2,741,489.20 |
Apr 20, 2018 | IBRD-83350 | Loan Disb | 6,480,000.00 |
Feb 15, 2017 | IBRD-83350 | Int Charges | 1,996,978.00 |
Jun 29, 2017 | IBRD-83350 | Loan Disb | 46,466,428.00 |
Mar 2, 2017 | IBRD-83350 | Loan Disb | 29,290,238.00 |
Apr 18, 2017 | IBRD-83350 | Loan Disb | 31,251,670.00 |
Aug 15, 2019 | IBRD-83350 | Int Charges | 7,155,461.00 |
Mar 13, 2019 | IBRD-83350 | Loan Disb | 16,930,616.00 |
Dec 2, 2019 | IBRD-83350 | Loan Disb | 6,545,474.50 |
Jul 16, 2019 | IBRD-83350 | Loan Disb | 16,305,746.00 |
Feb 15, 2019 | IBRD-83350 | Int Charges | 6,509,030.50 |
Jun 11, 2021 | IBRD-83350 | Loan Disb | -60,167.61 |
Jun 11, 2021 | IBRD-83350 | Loan Disb | -8,397,995.00 |
Apr 16, 2021 | IBRD-91910 | Loan Disb | 69,782,736.00 |
Mar 12, 2021 | IBRD-91910 | Fee Charges | 750,000.00 |
Feb 15, 2021 | IBRD-83350 | Int Charges | 2,333,529.00 |
Aug 15, 2020 | IBRD-83350 | Int Charges | 5,304,339.50 |
Dec 11, 2019 | IBRD-83350 | Loan Cancel | 40,000,000.00 |
Feb 15, 2020 | IBRD-83350 | Int Charges | 46,743.14 |
Feb 15, 2020 | IBRD-83350 | Int Charges | 6,049,170.00 |
Dec 16, 2022 | IBRD-91910 | Loan Disb | 129,222,144.00 |
Dec 1, 2022 | IBRD-91910 | Int Charges | 203,244.27 |
Dec 1, 2021 | IBRD-91910 | Int Charges | 21,986.34 |
Dec 1, 2021 | IBRD-91910 | Int Charges | 107,305.56 |
Dec 1, 2021 | IBRD-91910 | Int Charges | 275,745.25 |
Dec 1, 2021 | IBRD-91910 | Int Charges | 569,379.90 |
Dec 22, 2021 | IBRD-91910 | Loan Disb | 47,506,140.00 |
Feb 15, 2022 | IBRD-83350 | Int Charges | 1,958,487.00 |
Jun 1, 2022 | IBRD-91910 | Int Charges | 990,402.00 |
Jun 1, 2022 | IBRD-91910 | Int Charges | 208,966.72 |
Aug 15, 2022 | IBRD-83350 | Int Charges | 2,972,193.20 |
Sep 1, 2021 | IBRD-91910 | Loan Disb | 20,559,958.00 |
Jun 1, 2021 | IBRD-91910 | Int Charges | 187,602.70 |
Jun 11, 2021 | IBRD-83350 | Loan Cancel | 8,458,163.00 |
Aug 15, 2021 | IBRD-83350 | Int Charges | 2,038,488.10 |
Aug 15, 2024 | IBRD-83350 | Int Charges | 0.01 |
Aug 15, 2023 | IBRD-83350 | Int Charges | 12,183,076.00 |
Jun 1, 2023 | IBRD-91910 | Int Charges | 54,324.76 |
Jun 1, 2023 | IBRD-91910 | Int Charges | 215,607.20 |
Jun 1, 2023 | IBRD-91910 | Int Charges | 7,487,410.00 |
Nov 20, 2023 | IBRD-91910 | Loan Disb | -267,070,976.00 |
Dec 1, 2023 | IBRD-91910 | Int Charges | 8,468,636.00 |
Feb 15, 2023 | IBRD-83350 | Int Charges | 695,271.00 |
Feb 15, 2023 | IBRD-83350 | Int Charges | 9,928,208.00 |
Aug 15, 2023 | IBRD-83350 | Int Charges | 451,454.44 |
Dec 1, 2022 | IBRD-91910 | Int Charges | 2,702,893.00 |
Dec 16, 2020 | IBRD-91910 | Loan Commitment | 300,000,000.00 |
Jun 1, 2024 | IBRD-91910 | Int Charges | 8,084.37 |
Jun 1, 2024 | IBRD-91910 | Int Charges | 40,718.33 |
Feb 20, 2014 | IBRD-83350 | Loan Commitment | 479,000,000.00 |
Jun 1, 2024 | IBRD-91910 | Int Charges | 892,483.30 |
Feb 15, 2024 | IBRD-83350 | Int Charges | 125,197.55 |
Feb 15, 2024 | IBRD-83350 | Int Charges | 7,189,356.00 |
Nov 17, 2023 | IBRD-83350 | Loan Disb | -430,541,824.00 |
Dec 18, 2023 | IBRD-91910 | Loan Disb | 29,181,544.00 |
Jun 13, 2014 | IBRD-83350 | Loan Disb | 1,197,500.00 |
Jun 13, 2014 | IBRD-83350 | Fee Charges | 1,197,500.00 |
Dec 22, 2014 | IBRD-83350 | Loan Disb | 74,789,976.00 |
Feb 15, 2015 | IBRD-83350 | Int Charges | 7,333.33 |
Feb 15, 2015 | IBRD-83350 | Int Charges | 98,408.96 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2024-10-15 |
Financial Management | Moderately Satisfactory | 2024-10-15 |
Overall Safeguards Rating | Satisfactory | 2024-10-15 |
Monitoring and Evaluation | Satisfactory | 2024-10-15 |
Overall Implementation Progress (IP) | Satisfactory | 2024-10-15 |
Procurement | Moderately Satisfactory | 2024-10-15 |
Project Management | Satisfactory | 2024-10-15 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
% increase in access to roads, education, health centers and water (major KC investments) in KC-NCDDP municipalities | Value | 53.00 | 63.00 | 63.00 |
Date | June 30, 2014 | September 30, 2022 | December 31, 2024 | |
Comment |
% of households in NCDDP municipalities with at least one member attending regular Barangay Assemblies | Value | 56.00 | 69.99 | 70.00 |
Date | June 30, 2014 | April 15, 2024 | December 31, 2024 | |
Comment |
% of members from marginalized groups (women and IP) in KC-NCDDP municipalities who attend regular Barangay Assemblies | Value | 50.00 | 82.00 | 65.00 |
Date | June 30, 2014 | April 15, 2024 | December 31, 2024 | |
Comment |
% of members from female headed households KC-NCDDP municipalities who attend regular barangay assemblies | Value | 55.00 | 60.00 | 65.00 |
Date | June 30, 2014 | March 1, 2016 | June 30, 2019 | |
Comment |
% of members from IP households in KC-NCDDP municipalities who attend regular barangay assemblies | Value | 42.00 | 53.00 | 65.00 |
Date | June 30, 2014 | March 1, 2016 | June 30, 2019 | |
Comment |
Direct project beneficiaries | Value | 0.00 | 15800000.00 | 10200000.00 |
Date | June 30, 2014 | April 15, 2024 | December 31, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
% of NCDDP community sub-projects completed in accordance with technical plans, schedule and budget | Value | 0.00 | 83.00 | 85.00 |
Date | July 1, 2013 | April 15, 2024 | December 31, 2024 | |
Comment |
% of NCDDP municipalities with municipal poverty reduction plans prepared in accordance with NCDDP participatory process | Value | 0.00 | 96.60 | 85.00 |
Date | July 1, 2013 | April 15, 2024 | December 31, 2024 | |
Comment |
Grievances registered related to delivery of project benefits addressed (%) | Value | 0.00 | 99.90 | 99.60 |
Date | July 1, 2013 | April 15, 2024 | January 31, 2024 | |
Comment |
% of completed NCDDP sub-projects that have satisfactory or better sustainability evaluation rating | Value | 0.00 | 99.90 | 80.00 |
Date | July 1, 2013 | April 15, 2024 | December 31, 2024 | |
Comment |
% of NCDDP municipalities with increased membership of POs & CSOs in local development councils | Value | 0.00 | 91.20 | 85.00 |
Date | July 1, 2013 | April 15, 2024 | December 31, 2024 | |
Comment |
MIS providing necessary information in a timely fashion to measure project effectiveness and results | Value | No | yes | Yes |
Date | July 1, 2013 | April 15, 2024 | December 31, 2024 | |
Comment |
% of female participation in NCDDP paid labor component during sub-project implementation | Value | 8.00 | 34.70 | 35.00 |
Date | July 1, 2013 | April 15, 2024 | December 31, 2024 | |
Comment |
Number of NCDDP municipalities w/ staff trained by DILG using the Local Governance modules. | Value | 0.00 | 99.70 | 80.00 |
Date | July 1, 2013 | April 15, 2024 | December 31, 2024 | |
Comment |
Number of NCDDP studies regarding effectiveness and outcomes completed | Value | 0.00 | 8.00 | 15.00 |
Date | July 1, 2013 | April 15, 2024 | December 31, 2024 | |
Comment |
Percent of barangays with isolation units in accordance with health protocols | Value | 16.00 | 89.90 | 60.00 |
Date | March 31, 2022 | April 15, 2024 | December 31, 2024 | |
Comment |
Issuance of joint DILG-DSWD Memorandum Circular on participatory local development guidelines | Value | No | Yes | Yes |
Date | November 30, 2020 | December 31, 2023 | December 31, 2024 | |
Comment |
Percent of barangays with organized and trained Barangay Health Emergency Response Team | Value | 44.00 | 93.00 | 80.00 |
Date | March 31, 2022 | April 15, 2024 | December 31, 2024 | |
Comment |
Number of barangay local government units trained on community-based emergency response and recovery | Value | 0.00 | 85.00 | 90.00 |
Date | January 1, 2021 | September 29, 2023 | December 31, 2024 | |
Comment |