Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 203.20 |
P127822
Closed
Xavier Chauvot De Beauchene
N/A
May 1, 2012
(as of board presentation)
March 27, 2013
May 10, 2013
US$ 203.20 million
MINISTRY OF AGRICULTURE AND MARINE FISHERIES,Ministry of Economy and Finance
2013
US$ 203.20 million
N/A
May 21, 2015
March 15, 2014
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 203.20 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 203.20 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 203.20 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 203.20 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 15, 2023 | IBRD-82400 | Int Charges | 2,104,970.00 |
Nov 15, 2016 | IBRD-82400 | Int Charges | 354,902.66 |
Nov 15, 2023 | IBRD-82400 | Int Charges | 2,991,932.50 |
Nov 15, 2023 | IBRD-82400 | Loan Repay | 3,699,873.00 |
May 15, 2024 | IBRD-82400 | Int Charges | 3,170,995.80 |
May 15, 2024 | IBRD-82400 | Loan Repay | 3,685,912.50 |
Mar 27, 2013 | IBRD-82400 | Loan Commitment | 203,200,000.00 |
Nov 15, 2020 | IBRD-82400 | Loan Repay | 4,024,029.00 |
May 15, 2021 | IBRD-82400 | Int Charges | 174,431.23 |
May 15, 2021 | IBRD-82400 | Loan Repay | 4,124,987.20 |
Nov 15, 2021 | IBRD-82400 | Int Charges | 171,806.10 |
Nov 15, 2021 | IBRD-82400 | Loan Repay | 3,899,065.50 |
May 15, 2022 | IBRD-82400 | Int Charges | 142,458.61 |
May 15, 2022 | IBRD-82400 | Loan Repay | 3,537,114.00 |
Nov 15, 2022 | IBRD-82400 | Int Charges | 318,443.22 |
Nov 15, 2022 | IBRD-82400 | Loan Repay | 3,545,286.00 |
Nov 15, 2019 | IBRD-82400 | Int Charges | 397,537.75 |
May 15, 2020 | IBRD-82400 | Int Charges | 286,902.16 |
May 15, 2020 | IBRD-82400 | Loan Repay | 3,680,634.80 |
Nov 15, 2020 | IBRD-82400 | Int Charges | 487,013.66 |
May 15, 2018 | IBRD-82400 | Int Charges | 341,550.00 |
Nov 15, 2018 | IBRD-82400 | Int Charges | 346,947.34 |
May 15, 2019 | IBRD-82400 | Int Charges | 363,076.94 |
May 15, 2017 | IBRD-82400 | Int Charges | 330,913.25 |
Nov 15, 2017 | IBRD-82400 | Int Charges | 363,308.00 |
Nov 15, 2014 | IBRD-82400 | Int Charges | 858,739.50 |
Nov 15, 2013 | IBRD-82400 | Int Charges | 55.34 |
Nov 15, 2013 | IBRD-82400 | Int Charges | 762,359.06 |
May 15, 2014 | IBRD-82400 | Int Charges | 813,702.44 |
May 15, 2015 | IBRD-82400 | Int Charges | 582,553.00 |
Nov 15, 2015 | IBRD-82400 | Int Charges | 488,045.06 |
May 15, 2016 | IBRD-82400 | Int Charges | 464,598.22 |
May 15, 2023 | IBRD-82400 | Loan Repay | 3,704,469.80 |
Name | Review | Date |
---|---|---|
Program Management | Satisfactory | 2014-01-01 |
Progress towards achievement of PDO | Satisfactory | 2014-01-01 |
Monitoring and Evaluation | Satisfactory | 2014-01-01 |
Overall Implementation Progress (IP) | Highly Satisfactory | 2014-01-01 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | Modest |
Bank Performance | Substantial |
Borrower Performance | Moderately Satisfactory |
Government Performance | Substantial |
Implementing Agency | Moderately Satisfactory |
INDICATOR | ICR REVIEW: 09-28-2015 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | High | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of fruit and vegetable wholesale markets under new management model launched | Value | 0.00 | 0.00 | 3.00 |
Date | December 30, 2010 | October 30, 2013 | ||
Comment | TBD during supervision |
Number of private slaughterhouses launched | Value | 0.00 | 0.00 | 7.00 |
Date | December 30, 2010 | October 30, 2013 | ||
Comment | TBD during supervision |
Number of slaughterhouse concessions under new management model launched | Value | 0.00 | 0.00 | 1.00 |
Date | December 30, 2010 | October 30, 2013 | ||
Comment | TBD during supervision |
Share of new Pillar II projects submitted by the OPA | Value | 10.00 | 0.00 | 40.00 |
Date | December 30, 2010 | October 30, 2013 | ||
Comment | TBD during supervision |
Share of small farmers benefitting from Pillar II support | Value | 5.00 | 0.00 | 15.00 |
Date | December 30, 2010 | October 30, 2013 | ||
Comment | TBD during supervision |
Share of research and extension projects funded through the competitive financing mechanism | Value | 0.00 | 0.00 | 50.00 |
Date | December 30, 2010 | October 30, 2013 | ||
Comment | No baseline available. | TBD during supervision |
Number of public-private partnerships for agricultural extension created | Value | 0.00 | 0.00 | 5.00 |
Date | December 30, 2010 | October 30, 2013 | ||
Comment | TBD during supervision |
Number of training days per category of actor | Value | 180.00 | 0.00 | 880.00 |
Date | December 30, 2010 | October 30, 2013 | ||
Comment | TBD during supervision |
Number of HACCP-certified agri-food processing establishments | Value | 300.00 | 0.00 | 700.00 |
Date | December 30, 2010 | October 30, 2013 | ||
Comment | TBD during supervision |
Number of sanitary alerts notified by commercial partners (third countries) / number of shipment of products (number of certified produced) | Value | 28/22,397 | 20/25,000 | |
Date | December 30, 2010 | October 30, 2013 | ||
Comment | TBD during supervision |
Percentage increase of the number of declarations and authorizations of water abstraction received / delivered | Value | 0.00 | 0.00 | 10.00 |
Date | December 30, 2010 | October 30, 2013 | ||
Comment | The baseline (number) of declarations and authorizations of water abstraction received / delivered was 2,500. | TBD during supervision |
Cumulated number of farmers participating in projects of collection reconversion to drip irrigation | Value | 3000.00 | 0.00 | 10800.00 |
Date | December 30, 2010 | October 30, 2013 | ||
Comment | TBD during supervision |
Share of Operation and Maintenance costs covered by irrigation water tariffs in seven ORMVAs | Value | 76.00 | 0.00 | 88.00 |
Date | December 30, 2010 | October 30, 2013 | ||
Comment | TBD during supervision |
No. of irrigation schemes located downstream of dams under construction or programmed with allocated resources / no. of dams with agricultural scope under construction or progr. with allocated resourc | Value | 18.00 | 0.00 | 100.00 |
Date | December 30, 2010 | October 30, 2013 | ||
Comment | TBD during supervision |