Financier | Commitments |
---|---|
EC: European Investment Bank | 135.52 |
Borrower/Recipient | 157.48 |
International Bank for Reconstruction and Development | 100.00 |
P127876
Closed
Murad Gurmeric , Svetlana Vukanovic
Republic of Serbia
September 25, 2012
(as of board presentation)
April 26, 2013
October 24, 2014
US$ 393.01 million
Public Enterprise Roads of Serbia
2013
US$ 235.52 million
B
Not Applicable
December 31, 2020
Yes
BANK APPROVED
May 16, 2023
Financier | Commitments |
---|---|
EC: European Investment Bank | 135.52 |
Borrower/Recipient | 157.48 |
International Bank for Reconstruction and Development | 100.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 100.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 100.00 |
Lending Instrument | |
---|---|
Grant Amount | 135.52 |
Total Project Cost** | 393.01 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 15, 2022 | IBRD-82550 | Int Charges | 118,864.91 |
Jun 15, 2016 | IBRD-82550 | Int Charges | 54,368.57 |
Jun 15, 2023 | IBRD-82550 | Int Charges | 503,442.47 |
Jun 15, 2023 | IBRD-82550 | Loan Repay | 3,289,118.20 |
Dec 15, 2023 | IBRD-82550 | Loan Repay | 3,327,646.00 |
Dec 15, 2023 | IBRD-82550 | Int Charges | 660,144.30 |
Jun 15, 2024 | IBRD-82550 | Int Charges | 593,331.30 |
Jun 15, 2024 | IBRD-82550 | Loan Repay | 3,245,433.20 |
Apr 26, 2013 | IBRD-82550 | Loan Commitment | 100,000,000.00 |
Jun 15, 2021 | IBRD-82550 | Int Charges | 7,804.43 |
Jun 15, 2021 | IBRD-82550 | Loan Repay | 3,677,617.20 |
Sep 21, 2021 | IBRD-82550 | Loan Cancel | 19,536.17 |
Jun 15, 2022 | IBRD-82550 | Loan Repay | 3,180,057.50 |
Sep 21, 2021 | IBRD-82550 | Loan Disb | -19,536.17 |
Dec 15, 2021 | IBRD-82550 | Int Charges | 6,775.54 |
Dec 15, 2021 | IBRD-82550 | Loan Repay | 3,418,960.00 |
Dec 15, 2019 | IBRD-82550 | Int Charges | 78,178.63 |
Dec 15, 2019 | IBRD-82550 | Loan Repay | 3,121,001.50 |
Jun 15, 2020 | IBRD-82550 | Int Charges | 53,621.34 |
Jun 15, 2020 | IBRD-82550 | Loan Repay | 3,140,970.50 |
Aug 17, 2020 | IBRD-82550 | Loan Disb | 4,302,094.50 |
Dec 15, 2020 | IBRD-82550 | Int Charges | 101,201.89 |
Dec 15, 2020 | IBRD-82550 | Loan Repay | 3,690,364.00 |
Dec 15, 2018 | IBRD-82550 | Int Charges | 38,536.51 |
Dec 15, 2018 | IBRD-82550 | Loan Repay | 1,424,991.90 |
Dec 28, 2017 | IBRD-82550 | Loan Cancel | 20,765,008.00 |
Feb 5, 2019 | IBRD-82550 | Loan Disb | 31,433,110.00 |
Jun 15, 2019 | IBRD-82550 | Int Charges | 74,824.81 |
Jun 15, 2019 | IBRD-82550 | Loan Repay | 3,145,858.00 |
Dec 15, 2016 | IBRD-82550 | Int Charges | 50,638.53 |
Jun 15, 2017 | IBRD-82550 | Int Charges | 47,043.76 |
Dec 15, 2017 | IBRD-82550 | Int Charges | 42,410.50 |
Jun 15, 2018 | IBRD-82550 | Int Charges | 41,447.72 |
Jun 15, 2018 | IBRD-82550 | Loan Repay | 1,464,008.50 |
Oct 24, 2014 | IBRD-82550 | Loan Disb | 233,447.84 |
Oct 24, 2014 | IBRD-82550 | Fee Charges | 233,447.84 |
Jun 15, 2015 | IBRD-82550 | Int Charges | 263.08 |
Jun 15, 2015 | IBRD-82550 | Int Charges | 28,959.50 |
Apr 9, 2015 | IBRD-82550 | Loan Disb | 19,910,624.00 |
Dec 15, 2015 | IBRD-82550 | Int Charges | 62,737.79 |
Jul 5, 2016 | IBRD-82550 | Loan Disb | 7,327,719.50 |
Dec 15, 2022 | IBRD-82550 | Loan Repay | 3,223,135.80 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2020-06-24 |
Procurement | Moderately Satisfactory | 2020-06-24 |
Financial Management | Satisfactory | 2020-06-24 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2020-06-24 |
Counterpart Funding | Satisfactory | 2020-06-24 |
Project Management | Moderately Satisfactory | 2020-06-24 |
Monitoring and Evaluation | Satisfactory | 2020-06-24 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 05-26-2021 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 06-29-2021 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Reduction in road traffic accidents with fatalities on the improved roads in the first phase of NRNRP | Value | 100.00 | 78.00 | 95.00 |
Date | April 30, 2014 | December 30, 2020 | December 31, 2019 | |
Comment |
Improvement in road conditions measured by a reduction in the average IRI for the roads in the first phase of NRNRP | Value | 5.34 | 1.90 | 2.50 |
Date | October 30, 2014 | December 30, 2020 | December 31, 2019 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Roads in good and fair condition as a share of total classified roads | Value | 58.79 | 63.70 | 61.30 |
Date | October 30, 2014 | December 31, 2020 | December 31, 2020 | |
Comment |
Road Condition Survey Completed on National Roads | Value | 0.00 | 15076.00 | 9000.00 |
Date | October 30, 2014 | December 31, 2020 | December 31, 2019 | |
Comment |
Safety Inspection of National Roads beyond the first phase of NRNRP | Value | 0.00 | 1016.00 | 1000.00 |
Date | October 30, 2014 | June 15, 2020 | December 31, 2019 | |
Comment |
Size of the total classified network | Value | 9000.00 | 16900.00 | 16900.00 |
Date | October 30, 2014 | August 25, 2017 | December 31, 2019 | |
Comment |
Roads rehabilitated, Non-rural | Value | 0.00 | 416.50 | 389.80 |
Date | December 15, 2014 | December 30, 2020 | December 31, 2020 | |
Comment |
PBMC Contracts in Implementation | Value | 0.00 | 3000.00 | 3000.00 |
Date | October 30, 2014 | June 15, 2020 | December 31, 2019 | |
Comment |
Implementation of a circular for the preparation of rehabilitation program based socioeconomic & regional considerations | Value | None, except for on IFI funded projects | Road Maintenance Circular (RMC) is prepared and re | |
Date | October 30, 2014 | June 15, 2020 | ||