Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 470.00 |
Borrower/Recipient | 482.20 |
P127974
Closed
Rohit Mittal
India
August 13, 2012
(as of board presentation)
June 24, 2016
February 20, 2017
US$ 952.20 million
POWERGRID Corporation Limited
2016
US$ 470.00 million
A
Not Applicable
March 31, 2024
Yes
BANK APPROVED
April 25, 2024
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 470.00 |
Borrower/Recipient | 482.20 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 470.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 470.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 952.20 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Sep 26, 2017 | IBRD-86310 | Loan Disb | 18,758,716.00 |
Mar 14, 2018 | IBRD-86310 | Loan Disb | 6,201,541.50 |
Dec 15, 2017 | IBRD-86310 | Int Charges | 558,464.00 |
Dec 15, 2017 | IBRD-86310 | Int Charges | 269,698.38 |
Mar 13, 2024 | IBRD-86310 | Loan Disb | 5,271,613.50 |
Jun 15, 2024 | IBRD-86310 | Int Charges | 21,058.83 |
Jun 15, 2024 | IBRD-86310 | Int Charges | 13,495,772.00 |
Jun 15, 2024 | IBRD-86310 | Loan Repay | 11,897,174.00 |
Jun 15, 2024 | IBRD-86310 | Int Charges | 83,367.78 |
Jun 15, 2024 | IBRD-86310 | Int Charges | 161.20 |
Jun 24, 2016 | IBRD-86310 | Loan Commitment | 470,000,000.00 |
Dec 15, 2022 | IBRD-86310 | Int Charges | 7,198,629.50 |
Dec 15, 2022 | IBRD-86310 | Loan Repay | 10,396,091.00 |
Dec 13, 2022 | IBRD-86310 | Loan Disb | 14,410,908.00 |
Dec 15, 2022 | IBRD-86310 | Int Charges | 874.06 |
Dec 15, 2022 | IBRD-86310 | Int Charges | 3,131.60 |
Dec 15, 2022 | IBRD-86310 | Int Charges | 94,439.90 |
Mar 21, 2023 | IBRD-86310 | Loan Disb | 10,010,642.00 |
Sep 5, 2023 | IBRD-86310 | Loan Disb | 7,450,161.00 |
Jun 15, 2023 | IBRD-86310 | Int Charges | 197.42 |
Jun 15, 2023 | IBRD-86310 | Int Charges | 496,299.47 |
Jun 15, 2023 | IBRD-86310 | Int Charges | 59,932.82 |
Jun 15, 2023 | IBRD-86310 | Int Charges | 10,900,971.00 |
Jun 15, 2023 | IBRD-86310 | Loan Repay | 11,072,568.00 |
Jun 15, 2023 | IBRD-86310 | Loan Disb | 7,952,357.00 |
Dec 15, 2023 | IBRD-86310 | Int Charges | 211,317.02 |
Dec 15, 2023 | IBRD-86310 | Int Charges | 38,360.86 |
Dec 15, 2023 | IBRD-86310 | Int Charges | 12,664,300.00 |
Dec 15, 2023 | IBRD-86310 | Loan Repay | 11,511,540.00 |
Dec 12, 2023 | IBRD-86310 | Loan Disb | 7,845,204.50 |
Jun 15, 2021 | IBRD-86310 | Int Charges | 4,238.71 |
Jun 15, 2021 | IBRD-86310 | Int Charges | 254,472.62 |
Jun 15, 2021 | IBRD-86310 | Int Charges | 1,407,824.90 |
Sep 8, 2021 | IBRD-86310 | Loan Disb | 21,964,720.00 |
Jun 15, 2022 | IBRD-86310 | Int Charges | 144,226.38 |
Jun 15, 2022 | IBRD-86310 | Int Charges | 1,973,070.50 |
Jun 15, 2022 | IBRD-86310 | Loan Repay | 9,324,450.00 |
Jun 15, 2022 | IBRD-86310 | Int Charges | 2,174.54 |
Jun 10, 2022 | IBRD-86310 | Loan Disb | 25,522,770.00 |
Jun 15, 2022 | IBRD-86310 | Int Charges | 731.07 |
Dec 10, 2021 | IBRD-86310 | Loan Disb | 21,347,308.00 |
Mar 9, 2022 | IBRD-86310 | Loan Disb | 20,560,938.00 |
Dec 15, 2021 | IBRD-86310 | Loan Repay | 1,585,958.10 |
Dec 15, 2021 | IBRD-86310 | Int Charges | 2,427.94 |
Dec 15, 2021 | IBRD-86310 | Int Charges | 198,588.55 |
Dec 15, 2021 | IBRD-86310 | Int Charges | 1,549,198.50 |
Dec 15, 2021 | IBRD-86310 | Loan Repay | 6,636,305.00 |
Dec 15, 2021 | IBRD-86310 | Int Charges | 745.16 |
Sep 30, 2022 | IBRD-86310 | Loan Disb | 14,167,633.00 |
Nov 21, 2019 | IBRD-86310 | Loan Disb | 26,112,714.00 |
Dec 15, 2019 | IBRD-86310 | Int Charges | 389,912.12 |
Dec 15, 2019 | IBRD-86310 | Int Charges | 2,466,197.50 |
Dec 15, 2019 | IBRD-86310 | Int Charges | 1,316.18 |
Dec 15, 2019 | IBRD-86310 | Int Charges | 18,380.36 |
Jun 15, 2020 | IBRD-86310 | Int Charges | 4,292.49 |
Jun 1, 2020 | IBRD-86310 | Loan Disb | 21,642,794.00 |
Sep 1, 2020 | IBRD-86310 | Loan Disb | 11,865,409.00 |
Jun 15, 2020 | IBRD-86310 | Int Charges | 50,021.96 |
Jun 15, 2020 | IBRD-86310 | Int Charges | 336,085.20 |
Jun 15, 2020 | IBRD-86310 | Int Charges | 2,718,497.00 |
Dec 15, 2020 | IBRD-86310 | Int Charges | 2,069.66 |
Mar 4, 2021 | IBRD-86310 | Loan Disb | 15,686,824.00 |
Dec 15, 2020 | IBRD-86310 | Int Charges | 20,486.94 |
Dec 15, 2020 | IBRD-86310 | Int Charges | 290,310.78 |
Dec 15, 2020 | IBRD-86310 | Int Charges | 1,457,049.40 |
Dec 4, 2020 | IBRD-86310 | Loan Disb | 14,388,745.00 |
Jun 15, 2021 | IBRD-86310 | Int Charges | 1,081.13 |
Jun 11, 2021 | IBRD-86310 | Loan Disb | 27,197,992.00 |
Jun 15, 2018 | IBRD-86310 | Int Charges | 533,383.44 |
Jun 15, 2018 | IBRD-86310 | Int Charges | 525,602.06 |
Jun 8, 2018 | IBRD-86310 | Loan Disb | 22,488,214.00 |
Sep 4, 2018 | IBRD-86310 | Loan Disb | 10,994,808.00 |
Dec 4, 2018 | IBRD-86310 | Loan Disb | 13,149,301.00 |
Dec 15, 2018 | IBRD-86310 | Int Charges | 1,078.19 |
Dec 15, 2018 | IBRD-86310 | Int Charges | 802,670.10 |
Dec 15, 2018 | IBRD-86310 | Int Charges | 9,941.03 |
Dec 15, 2018 | IBRD-86310 | Int Charges | 496,737.80 |
Dec 15, 2018 | IBRD-86310 | Int Charges | 409,195.50 |
Jun 15, 2019 | IBRD-86310 | Int Charges | 990.69 |
Jun 15, 2019 | IBRD-86310 | Int Charges | 12,147.65 |
Jun 15, 2019 | IBRD-86310 | Int Charges | 1,832,072.00 |
Jun 15, 2019 | IBRD-86310 | Int Charges | 462,150.44 |
Mar 5, 2019 | IBRD-86310 | Loan Disb | 13,002,476.00 |
Jun 10, 2019 | IBRD-86310 | Loan Disb | 38,432,280.00 |
Aug 30, 2019 | IBRD-86310 | Loan Disb | 22,476,840.00 |
Mar 17, 2020 | IBRD-86310 | Loan Disb | 17,490,372.00 |
Feb 20, 2017 | IBRD-86310 | Loan Disb | 1,175,000.00 |
Feb 20, 2017 | IBRD-86310 | Fee Charges | 1,175,000.00 |
Jun 15, 2017 | IBRD-86310 | Int Charges | 446,540.22 |
Jun 15, 2017 | IBRD-86310 | Int Charges | 7,544.48 |
Jul 14, 2017 | IBRD-86310 | Loan Disb | 5,790,347.00 |
Jul 17, 2017 | IBRD-86310 | Loan Disb | 12,363,065.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2023-12-22 |
Financial Management | Satisfactory | 2023-12-22 |
Monitoring and Evaluation | Satisfactory | 2023-12-22 |
Counterpart Funding | Satisfactory | 2023-12-22 |
Overall Implementation Progress (IP) | Satisfactory | 2023-12-22 |
Project Management | Satisfactory | 2023-12-22 |
Procurement | Satisfactory | 2023-12-22 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Amount of electricity delivered at the boundaries of the power distribution network in each state | Value | 12372.00 | 17781.00 | 18370.00 |
Date | March 31, 2015 | March 31, 2023 | March 31, 2024 | |
Comment |
Increase in transformation capacity of the power transmission and distribution network in each state | Value | 0.00 | 5442350.00 | 5672000.00 |
Date | April 1, 2016 | November 30, 2023 | March 31, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Transmission lines constructed or rehabilitated under the project | Value | 0.00 | 1074.00 | 1182.00 |
Date | April 1, 2016 | November 30, 2023 | March 31, 2024 | |
Comment |
Number of practice/ process manuals updated or developed (procurement, O&M, financial management, human resource, and so on) | Value | 0.00 | 10.00 | 6.00 |
Date | April 1, 2016 | November 30, 2023 | March 31, 2024 | |
Comment |
Person-days of utility staff participating in trainings across areas like technical, operational, commercial, financial, HR, environment, social, procurement, change management, and so on | Value | 0.00 | 11435.00 | 1650.00 |
Date | April 1, 2016 | November 30, 2023 | March 31, 2024 | |
Comment |
Transmission lines rehabilitated under the project | Value | 0.00 | 91.00 | 91.00 |
Date | April 1, 2016 | November 30, 2023 | March 31, 2024 | |
Comment |
Transmission lines constructed under the project | Value | 0.00 | 986.00 | 1091.00 |
Date | April 1, 2016 | November 30, 2023 | March 31, 2024 | |
Comment |
Distribution lines constructed or rehabilitated under the project | Value | 0.00 | 1146.26 | 1269.00 |
Date | April 1, 2016 | November 30, 2023 | March 31, 2024 | |
Comment |
Distribution lines constructed under the project | Value | 0.00 | 1146.26 | 1269.00 |
Date | April 1, 2016 | November 30, 2023 | March 31, 2024 | |
Comment |
Distribution lines rehabilitated under the project | Value | 0.00 | 0.00 | 0.00 |
Date | April 1, 2016 | November 30, 2023 | March 31, 2024 | |
Comment |
Number of distribution substations constructed/ upgraded | Value | 0.00 | 182.00 | 187.00 |
Date | April 1, 2016 | November 30, 2023 | March 31, 2024 | |
Comment |
Number of transmission substations constructed/ upgraded | Value | 0.00 | 61.00 | 65.00 |
Date | April 1, 2016 | November 30, 2023 | March 31, 2024 | |
Comment |
Percentage of females among the number of persons participating in the safeguard consultation meetings | Value | 0.00 | 23.90 | 25.00 |
Date | June 1, 2014 | October 31, 2023 | March 31, 2024 | |
Comment |
Grievances received that are addressed within two months of receipt (percentage) | Value | 0.00 | 97.56 | 90.00 |
Date | April 1, 2016 | November 30, 2023 | March 31, 2024 | |
Comment |