Liberia EITI - Post Compliance I

Development Objective

<p style='margin-left: -27pt;'>&nbsp; The Project Development Objective for this grant is to fund Liberia&rsquo;s EITI (LEITI) post validation activities aiming at broadening LEITI&rsquo;s agenda to improve the Extractive Industries&rsquo; transparency through revenue management, national public financial management and accountability.

Key Details

Project Details

  • P128282

  • Closed

  • Daniele La Porta Arrobas

  • Federal Ministry of Finance

  • Liberia

  • July 23, 2013

  • (as of board presentation)

    July 23, 2013

  • August 19, 2013

  • US$ 0.20 million

  • Liberia Extractive Industries Transparency Initiative

  • Western and Central Africa

  • 2014

  • US$ 0.20 million

  • C

  • Not Applicable

  • December 31, 2015

  • BANK APPROVED

  • October 16, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Extractive Industries Transparency Initiative 0.20

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 0.20
Total Project Cost** 0.20

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Satisfactory 2016-04-13
Progress towards achievement of PDO Satisfactory 2016-04-13
Overall Implementation Progress (IP) Satisfactory 2016-04-13

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Implementation of LEITI’s post-validation workplan activitiesValue0.0080.00100.00
    DateAugust 19, 2013December 31, 2015December 31, 2015
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Develop and Implement Multi-stakeholder Steering Group Policy ManualValueYesYes
    DateAugust 19, 2013March 16, 2016December 31, 2015
    Comment
  • Design of capacity building events for EITI participants completed - and ToR done/vendor procuredValue0.003.006.00
    DateAugust 19, 2013December 31, 2015December 31, 2015
    Comment
  • Implement LEITI Secretariat Operations ManualValueNoYesYes
    DateOctober 19, 2013April 28, 2015December 31, 2015
    Comment
  • Capacity building - Delivery of Training to key stakeholders (CSOs, MSG members, Government)Value0.003.006.00
    DateAugust 19, 2013December 31, 2015December 31, 2015
    Comment
  • Design and delivery of Communications StrategyValueNoYesYes
    DateAugust 19, 2013December 31, 2015December 31, 2015
    Comment
  • Decentralizing LEITI Activities throughout Liberia (identification of focal points in each of the 15 subdivisions)ValueNoYesYes
    DateAugust 19, 2013December 31, 2015December 31, 2015
    Comment
  • Disseminate EITI report findings widely using various media/meetings/workshopsValueNoYesYes
    DateAugust 19, 2013April 28, 2015December 31, 2015
    Comment
  • EITI Report completed and publicly disseminated including recommendations for improvementValueNoYesYes
    DateAugust 19, 2013April 28, 2015December 31, 2015
    Comment