Financier | Commitments |
---|---|
Health Results-based Financing | 1.80 |
IDA Credit | 35.00 |
Borrower/Recipient | 8.20 |
P128442
Closed
Christine Pena
Republic of Armenia
April 2, 2012
(as of board presentation)
March 27, 2013
July 22, 2013
US$ 45.00 million
Ministry of Health, HPIU
2013
US$ 36.80 million
B
March 28, 2024
June 30, 2024
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Health Results-based Financing | 1.80 |
IDA Credit | 35.00 |
Borrower/Recipient | 8.20 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 35.00 |
IBRD + IDA Commitment | 35.00 |
Lending Instrument | |
---|---|
Grant Amount | 1.80 |
Total Project Cost** | 45.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 15, 2023 | IBRD-92020 | Int Charges | 94,307.22 |
Jan 31, 2023 | IDA-52220 | Loan Cancel | 7,482.39 |
Feb 23, 2023 | IBRD-92020 | Loan Disb | 600,000.00 |
Aug 11, 2023 | IBRD-92020 | Loan Disb | 1,081,905.20 |
Jun 27, 2023 | IBRD-92020 | Loan Disb | 1,047,576.30 |
Nov 10, 2023 | IBRD-92020 | Loan Disb | 232,281.62 |
Nov 15, 2023 | IDA-52220 | Int Charges | 8,317.83 |
Nov 15, 2023 | IDA-52220 | Int Charges | 92,793.28 |
Nov 15, 2023 | IDA-52220 | Int Charges | 92,793.28 |
Nov 15, 2023 | IDA-52220 | Int Charges | 257,029.61 |
Nov 15, 2023 | IDA-52220 | Int Charges | 102,406.24 |
Nov 15, 2023 | IDA-52220 | Loan Repay | 498,827.44 |
Nov 15, 2023 | IBRD-92020 | Int Charges | 150.96 |
Nov 15, 2023 | IBRD-92020 | Int Charges | 5,757.49 |
Nov 15, 2023 | IBRD-92020 | Int Charges | 1,245.43 |
Nov 15, 2023 | IBRD-92020 | Int Charges | 209,185.98 |
May 15, 2024 | IBRD-92020 | Int Charges | 1,432.49 |
May 8, 2020 | IDA-52220 | Loan Disb | 209,734.88 |
Jun 17, 2020 | IDA-52220 | Loan Disb | 333,606.70 |
May 26, 2020 | IDA-52220 | Loan Disb | 166,752.00 |
May 15, 2020 | IDA-52220 | Int Charges | 92,643.43 |
May 15, 2020 | IDA-52220 | Int Charges | 92,643.43 |
May 15, 2020 | IDA-52220 | Int Charges | 364,397.47 |
Jun 4, 2020 | IDA-52220 | Loan Disb | 87,775.99 |
May 15, 2020 | IDA-52220 | Int Charges | 1,223.26 |
May 15, 2020 | IDA-52220 | Loan Repay | 511,402.53 |
Jun 9, 2020 | IDA-52220 | Loan Disb | 410,329.16 |
Jul 15, 2020 | IDA-52220 | Loan Disb | 708,847.75 |
Dec 9, 2020 | IDA-52220 | Loan Disb | 1,784,029.40 |
May 15, 2021 | IDA-52220 | Loan Repay | 541,238.94 |
May 15, 2021 | IDA-52220 | Int Charges | 174,041.23 |
Jun 14, 2021 | IBRD-92020 | Loan Disb | 18,500.00 |
Jun 14, 2021 | IBRD-92020 | Fee Charges | 18,500.00 |
Nov 15, 2020 | IDA-52220 | Loan Repay | 13,236.34 |
Nov 15, 2020 | IDA-52220 | Int Charges | 101,438.60 |
Nov 15, 2020 | IDA-52220 | Int Charges | 101,438.60 |
Nov 15, 2020 | IDA-52220 | Int Charges | 396,674.75 |
Nov 15, 2020 | IDA-52220 | Loan Repay | 520,899.94 |
May 5, 2021 | IDA-52220 | Loan Disb | 260,000.00 |
May 15, 2017 | IDA-52220 | Int Charges | 60,538.86 |
Nov 15, 2017 | IDA-52220 | Int Charges | 73,553.47 |
Nov 15, 2017 | IDA-52220 | Int Charges | 73,553.47 |
Sep 6, 2013 | IDA-52220 | Loan Disb | 1,368,090.20 |
Sep 6, 2013 | IDA-52220 | Loan Disb | 42,375.59 |
Aug 27, 2013 | IDA-52220 | Loan Disb | 2,500,000.00 |
Dec 9, 2014 | IDA-52220 | Loan Disb | 285,271.28 |
Nov 15, 2014 | IDA-52220 | Int Charges | 319.91 |
Nov 15, 2014 | IDA-52220 | Int Charges | 319.91 |
Nov 15, 2014 | IDA-52220 | Int Charges | 17,336.00 |
Nov 15, 2014 | IDA-52220 | Int Charges | 17,336.00 |
Nov 15, 2014 | IDA-52220 | Int Charges | 29,426.49 |
Dec 27, 2013 | IDA-52220 | Loan Disb | 228,528.16 |
Jun 2, 2014 | IDA-52220 | Loan Disb | 617,160.80 |
May 15, 2014 | IDA-52220 | Int Charges | 6,194.17 |
May 15, 2014 | IDA-52220 | Int Charges | 6,194.17 |
May 15, 2014 | IDA-52220 | Int Charges | 10,323.66 |
May 15, 2014 | IDA-52220 | Int Charges | 15,574.11 |
May 15, 2014 | IDA-52220 | Int Charges | 15,574.11 |
May 15, 2014 | IDA-52220 | Int Charges | 25,956.84 |
Sep 11, 2014 | IDA-52220 | Loan Disb | 530,271.20 |
Mar 16, 2015 | IDA-52220 | Loan Disb | 248,949.48 |
Jul 8, 2015 | IDA-52220 | Loan Disb | 373,141.00 |
May 15, 2015 | IDA-52220 | Int Charges | 18,558.23 |
May 15, 2015 | IDA-52220 | Int Charges | 18,558.23 |
May 15, 2015 | IDA-52220 | Int Charges | 30,351.05 |
May 15, 2015 | IDA-52220 | Int Charges | 1,146.09 |
May 15, 2015 | IDA-52220 | Int Charges | 1,146.09 |
Nov 15, 2015 | IDA-52220 | Int Charges | 2,433.43 |
Nov 15, 2015 | IDA-52220 | Int Charges | 21,686.04 |
Nov 15, 2015 | IDA-52220 | Int Charges | 21,686.04 |
Nov 15, 2015 | IDA-52220 | Int Charges | 35,454.65 |
Dec 8, 2015 | IDA-52220 | Loan Disb | 570,023.06 |
Oct 13, 2015 | IDA-52220 | Loan Disb | 1,035,293.80 |
Feb 2, 2016 | IDA-52220 | Loan Disb | 1,175,279.50 |
May 15, 2024 | IBRD-92020 | Int Charges | 254,066.66 |
May 15, 2024 | IDA-52220 | Int Charges | 5,538.19 |
May 15, 2024 | IBRD-92020 | Int Charges | 7.95 |
May 15, 2024 | IDA-52220 | Int Charges | 356,812.06 |
May 15, 2024 | IDA-52220 | Loan Repay | 495,263.72 |
May 15, 2024 | IDA-52220 | Loan Repay | 2,424.16 |
May 15, 2024 | IDA-52220 | Int Charges | 90,714.94 |
May 15, 2024 | IDA-52220 | Int Charges | 90,714.94 |
Feb 4, 2021 | IBRD-92020 | Loan Commitment | 7,400,000.00 |
Mar 27, 2013 | IDA-52220 | Loan Commitment | 35,000,000.00 |
Mar 21, 2022 | IDA-52220 | Loan Disb | 9,000.00 |
Nov 15, 2022 | IBRD-92020 | Int Charges | 434.02 |
Nov 15, 2022 | IBRD-92020 | Int Charges | 6,649.66 |
Nov 15, 2022 | IBRD-92020 | Int Charges | 37,085.48 |
Nov 15, 2022 | IBRD-92020 | Int Charges | 105.59 |
Nov 15, 2022 | IDA-52220 | Loan Repay | 467,301.60 |
Nov 7, 2022 | IBRD-92020 | Loan Disb | 588,318.30 |
Nov 15, 2022 | IDA-52220 | Int Charges | 95,666.20 |
Nov 15, 2022 | IDA-52220 | Int Charges | 95,666.20 |
Nov 15, 2022 | IDA-52220 | Int Charges | 147,438.23 |
Nov 15, 2022 | IDA-52220 | Loan Repay | 27,766.34 |
Dec 7, 2022 | IBRD-92020 | Loan Disb | 401,809.88 |
May 15, 2023 | IDA-52220 | Int Charges | 368,503.03 |
Apr 27, 2023 | IBRD-92020 | Loan Disb | 1,224,494.10 |
May 15, 2023 | IBRD-92020 | Int Charges | 32.24 |
May 15, 2023 | IBRD-92020 | Int Charges | 3,782.36 |
May 15, 2023 | IBRD-92020 | Int Charges | 4,766.52 |
May 15, 2023 | IDA-52220 | Int Charges | 12,248.90 |
May 15, 2023 | IDA-52220 | Loan Repay | 504,961.47 |
May 15, 2023 | IDA-52220 | Int Charges | 95,827.90 |
May 15, 2023 | IDA-52220 | Int Charges | 95,827.90 |
May 15, 2021 | IDA-52220 | Int Charges | 108,056.20 |
May 15, 2021 | IDA-52220 | Int Charges | 108,056.20 |
May 15, 2021 | IDA-52220 | Int Charges | 2,347.94 |
Oct 27, 2021 | IBRD-92020 | Loan Disb | 661,459.40 |
Oct 27, 2021 | IBRD-92020 | Loan Disb | 2,797.48 |
Oct 18, 2021 | IBRD-92020 | Loan Disb | 900,000.00 |
Nov 15, 2021 | IDA-52220 | Loan Repay | 528,534.70 |
Nov 15, 2021 | IDA-52220 | Int Charges | 105,312.93 |
Nov 15, 2021 | IDA-52220 | Int Charges | 105,312.93 |
Nov 15, 2021 | IDA-52220 | Int Charges | 175,521.56 |
Nov 15, 2021 | IDA-52220 | Int Charges | 5,910.32 |
May 15, 2022 | IBRD-92020 | Int Charges | 1,022.65 |
May 15, 2022 | IBRD-92020 | Int Charges | 7,106.21 |
May 15, 2022 | IBRD-92020 | Int Charges | 10,026.75 |
May 15, 2022 | IBRD-92020 | Int Charges | 259.05 |
Nov 15, 2021 | IBRD-92020 | Int Charges | 10,365.26 |
Nov 15, 2021 | IBRD-92020 | Int Charges | 96.57 |
Jun 10, 2022 | IDA-52220 | Loan Disb | 221,500.00 |
Mar 22, 2022 | IBRD-92020 | Loan Disb | 285,502.16 |
May 15, 2022 | IDA-52220 | Int Charges | 97,886.32 |
May 15, 2022 | IDA-52220 | Int Charges | 97,886.32 |
May 15, 2022 | IDA-52220 | Int Charges | 163,143.88 |
Jul 19, 2022 | IBRD-92020 | Loan Disb | 355,355.44 |
May 15, 2022 | IDA-52220 | Loan Repay | 488,408.78 |
May 15, 2022 | IDA-52220 | Loan Repay | 12,226.89 |
Nov 15, 2017 | IDA-52220 | Int Charges | 122,589.15 |
Nov 15, 2017 | IDA-52220 | Int Charges | 4,902.18 |
Nov 22, 2017 | IDA-52220 | Loan Disb | 1,395,136.20 |
Aug 23, 2017 | IDA-52220 | Loan Disb | 557,934.30 |
Jan 16, 2018 | IDA-52220 | Loan Disb | 1,290,203.90 |
Jan 16, 2018 | IDA-52220 | Loan Disb | 1,078,272.20 |
May 22, 2018 | IDA-52220 | Loan Disb | 938,186.50 |
May 15, 2018 | IDA-52220 | Loan Repay | 1,546.68 |
May 15, 2018 | IDA-52220 | Loan Repay | 535,749.70 |
May 15, 2018 | IDA-52220 | Int Charges | 86,422.58 |
May 15, 2018 | IDA-52220 | Int Charges | 86,422.58 |
May 15, 2018 | IDA-52220 | Int Charges | 144,037.56 |
Nov 15, 2018 | IDA-52220 | Loan Repay | 13,476.67 |
Nov 15, 2018 | IDA-52220 | Loan Repay | 506,307.60 |
Nov 15, 2018 | IDA-52220 | Int Charges | 88,614.64 |
Nov 15, 2018 | IDA-52220 | Int Charges | 88,614.64 |
Nov 15, 2018 | IDA-52220 | Int Charges | 220,797.45 |
Nov 15, 2018 | IDA-52220 | Int Charges | 127,753.48 |
Jan 28, 2019 | IDA-52220 | Loan Disb | 919,925.70 |
Oct 29, 2018 | IDA-52220 | Loan Disb | 1,755,086.50 |
Jun 10, 2019 | IDA-52220 | Loan Disb | 223,232.16 |
May 15, 2019 | IDA-52220 | Int Charges | 94,853.42 |
May 15, 2019 | IDA-52220 | Int Charges | 373,090.03 |
May 15, 2019 | IDA-52220 | Loan Repay | 508,389.06 |
May 15, 2019 | IDA-52220 | Loan Repay | 11,643.48 |
May 15, 2019 | IDA-52220 | Int Charges | 94,853.42 |
Nov 15, 2019 | IDA-52220 | Int Charges | 94,527.32 |
Nov 15, 2019 | IDA-52220 | Int Charges | 94,527.32 |
Nov 15, 2019 | IDA-52220 | Int Charges | 370,570.60 |
Oct 1, 2019 | IDA-52220 | Loan Disb | 61,000.86 |
Nov 15, 2019 | IDA-52220 | Loan Repay | 509,922.03 |
Nov 15, 2019 | IDA-52220 | Loan Repay | 7,168.63 |
Feb 12, 2020 | IDA-52220 | Loan Disb | 393,605.72 |
Jun 15, 2016 | IDA-52220 | Loan Disb | 1,176,210.60 |
Jul 7, 2016 | IDA-52220 | Loan Disb | 1,395,205.10 |
Jul 28, 2016 | IDA-52220 | Loan Disb | 1,102,634.90 |
Jul 21, 2016 | IDA-52220 | Loan Disb | 1,055,021.60 |
May 10, 2016 | IDA-52220 | Loan Disb | 812,511.44 |
May 15, 2016 | IDA-52220 | Int Charges | 702.11 |
May 15, 2016 | IDA-52220 | Int Charges | 30,274.05 |
May 15, 2016 | IDA-52220 | Int Charges | 30,274.05 |
May 15, 2016 | IDA-52220 | Int Charges | 49,239.47 |
Sep 13, 2016 | IDA-52220 | Loan Disb | 1,335,365.20 |
Jun 29, 2016 | IDA-52220 | Loan Disb | 895,718.44 |
Nov 15, 2016 | IDA-52220 | Int Charges | 1,176.36 |
Nov 15, 2016 | IDA-52220 | Int Charges | 50,486.09 |
Nov 15, 2016 | IDA-52220 | Int Charges | 50,486.09 |
Nov 15, 2016 | IDA-52220 | Int Charges | 84,143.50 |
Dec 22, 2016 | IDA-52220 | Loan Disb | 1,093,087.20 |
Apr 21, 2017 | IDA-52220 | Loan Disb | 1,636,881.90 |
May 15, 2017 | IDA-52220 | Int Charges | 3,661.20 |
May 15, 2017 | IDA-52220 | Int Charges | 3,661.20 |
May 15, 2017 | IDA-52220 | Int Charges | 102,245.67 |
May 15, 2017 | IDA-52220 | Int Charges | 60,538.86 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2024-06-27 |
Monitoring and Evaluation | Satisfactory | 2024-06-27 |
Overall Implementation Progress (IP) | Satisfactory | 2024-06-27 |
Project Management | Satisfactory | 2024-06-27 |
Overall Safeguards Rating | Satisfactory | 2024-06-27 |
Procurement | Satisfactory | 2024-06-27 |
Financial Management | Satisfactory | 2024-06-27 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of antenatal care (ANC) attendees screened for glycosuria, hypertension and proteinuria in at least three antenatal visits (Percentage) | Value | 0.00 | 94.80 | 85.00 |
Date | January 23, 2013 | December 31, 2022 | June 30, 2024 | |
Comment |
Bed occupancy rate at the a) Artashat Medical Center; b) Sevan Medical Center (Percentage) | Value | a)64.00b)51.00 | a) 58.7b) 61.9 | a)70.00 b)70.00 |
Date | January 23, 2013 | August 31, 2023 | June 30, 2024 | |
Comment |
Number of designated intensive care units that are fully equipped and functional, without stock-outs in the final two weeks of the calendar year (Number) | Value | 0.00 | 5.00 | 4.00 |
Date | January 23, 2013 | December 31, 2022 | June 30, 2024 | |
Comment |
Percentage of population aged 35-68 screened for hypertension at least once in the last year a) female; b) male (Percentage) | Value | a) 22.50b) 17.80 | a) 40.2 b) 26.7 | a)39.00b)27.00 |
Date | December 31, 2013 | December 31, 2022 | June 30, 2024 | |
Comment |
Percentage of deaths following hospital discharges for acute myocardial infarction or pneumonia, in the last year, at Sevan and Artashat MCs (Percentage) | Value | 10.60 | 3.60 | 8.00 |
Date | December 31, 2013 | October 4, 2023 | June 30, 2024 | |
Comment |
Percentage of population aged 35-68 screened for diabetes mellitus at PHC level at least once during the last 3 years a) female; b)male (Percentage) | Value | a)9.80b)7.50 | a) 23.1 b) 14.8 | a)20.00b)15.00 |
Date | December 31, 2013 | December 31, 2022 | June 30, 2024 | |
Comment |
Percentage of women aged 30-60 screened for cervical cancer at least once during the last 3 years and received the results (Percentage) | Value | 8.50 | 9.70 | 10.00 |
Date | January 23, 2013 | December 31, 2022 | June 30, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of PHC facilities undergoing enhanced verification of results by the HPIU (Percentage) | Value | 0.00 | 98.30 | 98.00 |
Date | January 23, 2013 | December 31, 2022 | June 30, 2024 | |
Comment |
Health facilities constructed, renovated, and/or equipped (Number) | Value | 0.00 | 5.00 | 6.00 |
Date | January 23, 2013 | November 15, 2023 | June 30, 2024 | |
Comment |
Number of ventilators for management of COVID-19 cases, financed through the Project (Number) | Value | 0.00 | 70.00 | 70.00 |
Date | January 23, 2013 | December 31, 2022 | June 30, 2024 | |
Comment |
Percentage of adults aware of key NCD risk factors a) high blood pressure; b) high cholesterol level; c) high salt intake; d) obesity; e) high glucose level (disaggregated by gender) (Percentage) | Value | Malea)45.00b)24.00c)55.00d)65.00e)33.00Fema | Male a) 27.4 b) 12.5c) 75.7d) 63.5 e) 18.3F | Malea)47.00b)26.00c)57.00d)66.00e)35.00Fema |
Date | January 31, 2013 | December 31, 2022 | June 30, 2024 | |
Comment |
Number of hospital health workers receiving training on new clinical practice guidelines (Number) | Value | 0.00 | 316.00 | 300.00 |
Date | January 23, 2013 | December 31, 2022 | June 30, 2024 | |
Comment |
Medical Centers operational a) Sevan MC; b) Artashat MC; c) Martuni MC; d) Vayots Dzor MC (Text) | Value | a)Not operational b)Not operational c)Not operat | a) Operational b) Operational c) Operationald) | a)Operational b)Operational c)Operational d)Ope |
Date | January 23, 2013 | November 15, 2023 | June 30, 2024 | |
Comment |
Percentage of workers under the Project with adequate awareness of GBV, including SEA and SH, in the last year: a) Male; b) Female (Percentage) | Value | a)9.50 b)14.20 | a) 73.2 b) 86.7 | a)70.00b)80.00 |
Date | October 31, 2020 | December 31, 2022 | June 30, 2024 | |
Comment |
Percentage of beneficiaries in annual consultations that express satisfaction with the Project, including the community engagement process: (a) Gegharkunik Marz (b) Vayots Dzor Marz (Percentage) | Value | a)0.00 b)0.00 | a) 100.00 b) 100.00 | a)60.00b)60.00 |
Date | October 31, 2020 | December 31, 2022 | June 30, 2024 | |
Comment |