Skip to Main Navigation

VILLAGE INNOVATION PROGRAM (VIP)

Abstract*

The development objective of the National Program for Community Empowerment in Rural Areas Project for Indonesia is to rural locations to benefit from improved local governance and socio-economic conditions. There are three components to the project. The first component of the project is kecamatan grants. This component will provide grants to participating kecamatan to finance subprojects identified by communities. The second component of the project...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To improve participating village capacity to develop quality village development and implementation plans

Key Details

Project Details

  • P128832

  • Closed

  • Samuel Clark , Bambang Soetono

  • Republic of Indonesia

  • Indonesia

  • June 22, 2012

  • (as of board presentation)

    December 11, 2012

  • March 25, 2013

  • US$ 4500.00 million

  • Ministry of Villages, Development of Disadvantaged Areas and Transmigration

  • East Asia and Pacific

  • 2013

  • US$ 650.00 million

  • B

  • Not Applicable

  • December 31, 2019

  • Yes

  • BANK APPROVED

  • March 7, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 3850.00
International Bank for Reconstruction and Development 650.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 650.00
IDA Commitment N/A
IBRD + IDA Commitment 650.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 4500.00

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 1, 2022 IBRD-82170 Loan Repay 13,737,776.00
Jun 1, 2022 IBRD-82170 Int Charges 95.89
Sep 21, 2022 IBRD-82170 Loan Disb -45,766.74
Dec 1, 2022 IBRD-82170 Loan Repay 14,046,865.00
Nov 15, 2022 IBRD-82170 Loan Disb -28,037.17
Dec 1, 2022 IBRD-82170 Int Charges 10,565,018.00
Dec 12, 2022 IBRD-82170 Loan Disb -166,874.31
Dec 8, 2017 IBRD-82170 Loan Disb 25,381,000.00
Jun 1, 2018 IBRD-82170 Int Charges 6,409,085.00
Jan 28, 2019 IBRD-82170 Loan Disb 16,451.00
Oct 31, 2018 IBRD-82170 Loan Disb -283.30
Feb 8, 2019 IBRD-82170 Loan Disb 5,000,000.00
Dec 1, 2018 IBRD-82170 Int Charges 14,836.27
Dec 1, 2018 IBRD-82170 Int Charges 9,351,095.00
Jun 1, 2019 IBRD-82170 Int Charges 0.76
Jun 1, 2019 IBRD-82170 Int Charges 10,758,466.00
Jun 3, 2019 IBRD-82170 Loan Disb 30,000,000.00
Dec 2, 2019 IBRD-82170 Loan Disb 14,000,000.00
Dec 1, 2019 IBRD-82170 Int Charges 10,310,218.00
Jun 23, 2020 IBRD-82170 Loan Disb -6,269,488.50
Jun 1, 2020 IBRD-82170 Int Charges 8,429,441.00
Dec 1, 2015 IBRD-82170 Int Charges 1,915,117.20
Dec 7, 2015 IBRD-82170 Loan Disb 36,885,000.00
Nov 24, 2015 IBRD-82170 Loan Disb 4,977,000.00
Apr 5, 2016 IBRD-82170 Loan Disb 22,844,000.00
Dec 1, 2016 IBRD-82170 Int Charges 50,526.33
Dec 1, 2016 IBRD-82170 Int Charges 3,875,013.80
May 25, 2016 IBRD-82170 Loan Disb 30,526,000.00
Dec 13, 2016 IBRD-82170 Loan Disb 25,211,000.00
Jun 1, 2016 IBRD-82170 Int Charges 919.36
Jun 1, 2016 IBRD-82170 Int Charges 2,667,076.80
Jun 5, 2017 IBRD-82170 Loan Disb 5,029,000.00
Jun 1, 2017 IBRD-82170 Int Charges 4,950,259.00
Apr 3, 2018 IBRD-82170 Loan Disb 3,902,000.00
Dec 1, 2017 IBRD-82170 Int Charges 5,465,530.50
Dec 28, 2017 IBRD-82170 Loan Disb -16,451.00
Jun 26, 2018 IBRD-82170 Loan Disb 40,000,000.00
Apr 22, 2013 IBRD-82170 Fee Charges 1,625,000.00
Nov 14, 2013 IBRD-82170 Loan Disb 98,317,000.00
Jun 1, 2014 IBRD-82170 Int Charges 40,856.17
Jun 1, 2014 IBRD-82170 Int Charges 621,060.94
Apr 23, 2014 IBRD-82170 Loan Disb 199,976,352.00
Dec 1, 2013 IBRD-82170 Int Charges 196,373.97
Aug 20, 2014 IBRD-82170 Loan Disb 14,255,000.00
Jun 1, 2015 IBRD-82170 Int Charges 1,658,814.90
Jun 1, 2023 IBRD-82170 Int Charges 968,126.25
Jun 1, 2023 IBRD-82170 Int Charges 16,054,566.00
Jun 1, 2023 IBRD-82170 Loan Repay 14,421,862.00
Dec 1, 2023 IBRD-82170 Int Charges 387,342.80
Dec 1, 2023 IBRD-82170 Int Charges 18,313,620.00
Dec 1, 2023 IBRD-82170 Loan Repay 14,801,384.00
Jun 1, 2024 IBRD-82170 Int Charges 19,000,054.00
Jun 1, 2024 IBRD-82170 Int Charges 115,616.69
Jun 1, 2024 IBRD-82170 Loan Repay 15,180,907.00
Dec 11, 2012 IBRD-82170 Loan Commitment 650,000,000.00
Jul 16, 2020 IBRD-82170 Loan Cancel 15,941,744.00
Nov 10, 2020 IBRD-82170 Loan Disb -139,835.50
Nov 2, 2020 IBRD-82170 Loan Disb -215,197.80
Dec 1, 2020 IBRD-82170 Int Charges 3,904,314.20
Jun 1, 2021 IBRD-82170 Int Charges 308.45
Jun 1, 2021 IBRD-82170 Int Charges 3,075,264.50
Nov 23, 2021 IBRD-82170 Loan Disb -13,769.58
Nov 23, 2021 IBRD-82170 Loan Disb -465,641.00
Jun 30, 2022 IBRD-82170 Loan Disb -282,544.50
Nov 30, 2021 IBRD-82170 Loan Disb -117,753.45
Dec 1, 2021 IBRD-82170 Int Charges 2,899,096.20
Dec 15, 2021 IBRD-82170 Loan Disb -28,809.58
Jun 1, 2022 IBRD-82170 Int Charges 3,136,458.20
Dec 8, 2014 IBRD-82170 Loan Disb 32,528,000.00
Dec 1, 2014 IBRD-82170 Int Charges 177,645.67
Dec 1, 2014 IBRD-82170 Int Charges 1,436,918.80

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Satisfactory 2019-12-18
Financial Management Moderately Satisfactory 2019-12-18
Progress towards achievement of PDO Moderately Satisfactory 2019-12-18
Project Management Moderately Satisfactory 2019-12-18
Monitoring and Evaluation Moderately Satisfactory 2019-12-18
Overall Implementation Progress (IP) Moderately Satisfactory 2019-12-18

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-26-2020
OutcomesModerately Satisfactory
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 04-30-2021PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Villages benefiting from technical services supported by the project (number)Value0.0015644.0014000.00
    DateApril 1, 2017December 31, 2019December 31, 2019
    Comment
  • Beneficiaries in project locations satisfied that village investments meet their needs, disaggregated by gender (percentage)Value40.0069.7070.00
    DateJuly 1, 2017December 31, 2019December 31, 2019
    Comment
  • Villages with development plans that reflect local development priorities (percentage)Value40.0068.3070.00
    DateJuly 1, 2017December 31, 2019December 31, 2019
    Comment
  • Villages with quality technical implementation plans (percentage)Value40.0082.1070.00
    DateJuly 1, 2017December 31, 2019December 31, 2019
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Female participants in consultative forums to develop village innovation activities (percentage)Value50.0038.6050.00
    DateJanuary 1, 2017December 31, 2019December 31, 2019
    Comment
  • District with functional village innovation and knowledge sharing platform (percentage)Value0.0099.7080.00
    DateJanuary 1, 2017December 31, 2019December 31, 2019
    Comment
  • MOV M&E system uitilized to track project performance and improve project implementationValueNoYesYes
    DateJanuary 1, 2017December 31, 2019December 31, 2019
    Comment
  • Villages implement innovation activities that are shared through innovation forums (percentage)Value0.0043.6070.00
    DateJanuary 1, 2017December 31, 2019December 31, 2019
    Comment
  • Participants of village innovation forums aware of priority usage of village funds (percentage, by gender)Value30.0088.0080.00
    DateJuly 1, 2017December 31, 2019December 31, 2019
    Comment
  • MOV capacity to implement annual workplan improved as the result of the Executive Transformation Program supported by the projectValueNoYesYes
    DateApril 3, 2017December 31, 2019December 31, 2019
    Comment
  • Participants in village innovation forums who feel that their capacity to solve village priority development needs improved (percentage)Value0.0085.0070.00
    DateJanuary 1, 2017December 31, 2019December 31, 2019
    Comment
  • Villages with functional dataset that can be used to inform village development priorities (percentage)Value0.0042.0060.00
    DateJanuary 1, 2017December 31, 2019December 31, 2019
    Comment
  • Village facilitators reporting on their dissemination of village innovations in village-level planning meetings (percentage)Value0.0069.7070.00
    DateJanuary 1, 2017December 31, 2019December 31, 2019
    Comment
  • Result from pilots disseminated in village innovation forums (number)Value0.00678.004000.00
    DateJanuary 1, 2017December 31, 2019December 31, 2019
    Comment
  • Technical service providers with improved competencies to conduct their works as the result of project intervention (percentage)Value0.0091.1080.00
    DateJuly 1, 2017December 31, 2019December 31, 2019
    Comment
  • Participants of village innovation forums feel that technical service providers provide useful assistance in developing village plans (percentage, by gender)Value0.0098.4070.00
    DateJuly 1, 2017December 31, 2019December 31, 2019
    Comment