P129322
Closed
Shyam KC
Department of Finance
Papua New Guinea
October 20, 2011
(as of board presentation)
October 20, 2011
May 16, 2012
US$ 2.93 million
Department of Works
2012
US$ 2.93 million
C
August 15, 2024
June 30, 2015
BANK APPROVED
Financier | Commitments |
---|---|
Trust Funds | 2.93 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 2.93 |
Total Project Cost** | 2.93 |
Name | Review | Date |
---|---|---|
Overall Implementation Progress (IP) | Moderately Satisfactory | 2015-07-13 |
Procurement | Moderately Satisfactory | 2015-07-13 |
Financial Management | Moderately Unsatisfactory | 2015-07-13 |
Progress towards achievement of PDO | Moderately Satisfactory | 2015-07-13 |
Project Management | Moderately Satisfactory | 2015-07-13 |
Monitoring and Evaluation | Moderately Satisfactory | 2015-07-13 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Data related with disaster is actively utilized and continuously updated | Value | Data (Hazard, Exposure, and risk) is partial and n | Data has been collected, analyzed and open access | Data actively utilized and continuously updated |
Date | December 7, 2011 | June 19, 2015 | June 30, 2015 | |
Comment |
A system of disater risk assessment is in place | Value | 25.00 | 100.00 | 100.00 |
Date | December 7, 2011 | June 19, 2015 | June 30, 2015 | |
Comment |
Roads and bridges are analyzed for disaster risks | Value | 0.00 | 530.00 | 10.00 |
Date | December 7, 2013 | June 19, 2015 | June 30, 2015 | |
Comment |
Installation of the equipment provided under Component B | Value | 0.00 | 4.00 | 3.00 |
Date | November 7, 2012 | June 19, 2015 | June 30, 2015 | |
Comment |
Training on the use of the equipment provided under Component B is carried out for effective future use (Number of people) | Value | 0.00 | 25.00 | 25.00 |
Date | November 7, 2012 | June 19, 2015 | June 30, 2015 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
A user-friendly manual for design and construction of disaster risk management works is developed | Value | 0.00 | 1.00 | 1.00 |
Date | November 7, 2012 | June 19, 2015 | June 30, 2015 | |
Comment |