Skip to Main Navigation

Anhui Yellow Mountain New Countryside Demonstration Project

Abstract*

The development objective of the Anhui Yellow Mountain New Countryside Demonstration Project for China is to improve the quality of services and income generating opportunities available to rural households in selected villages of Huangshan municipality. The project has four components. The first component is infrastructure improvement which aims to improve infrastructure services in project villages by financing sustainable priority investments in...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective of the Project is to improve the quality of services and income generating opportunities available to rural households in selected villages of Huangshan Municipality.

Key Details

Project Details

  • P129563

  • Closed

  • Ahmed Eiweida , Minghe Tao

  • People's Republic of China

  • China

  • October 5, 2012

  • (as of board presentation)

    December 27, 2013

  • May 30, 2014

  • US$ 145.19 million

  • Huangshan Municipality development and Reform Commission

  • East Asia and Pacific

  • 2014

  • US$ 100.00 million

  • B

  • July 12, 2023

  • June 30, 2020

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Local Govts. (Prov., District, City) of Borrowing Country 45.19
International Bank for Reconstruction and Development 100.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 100.00
IDA Commitment N/A
IBRD + IDA Commitment 100.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 145.19

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 5, 2019 IBRD-83090 Loan Disb 3,440,682.80
Oct 25, 2019 IBRD-83090 Loan Disb 2,797,242.50
Sep 15, 2019 IBRD-83090 Int Charges 1,305,042.40
Sep 15, 2019 IBRD-83090 Int Charges 9,970.32
Sep 15, 2019 IBRD-83090 Loan Repay 1,657,580.80
Mar 15, 2020 IBRD-83090 Int Charges 1,132,459.80
Mar 15, 2020 IBRD-83090 Loan Repay 1,715,763.40
Jan 16, 2020 IBRD-83090 Loan Disb 5,245,553.00
Jun 23, 2020 IBRD-83090 Loan Disb 8,506,053.00
Sep 15, 2018 IBRD-83090 Int Charges 6,218.54
Sep 15, 2018 IBRD-83090 Int Charges 692,771.60
Aug 29, 2018 IBRD-83090 Loan Disb 2,942,732.80
Jan 9, 2019 IBRD-83090 Loan Disb 5,860,934.50
Jan 25, 2019 IBRD-83090 Loan Disb 2,253,887.50
Oct 25, 2018 IBRD-83090 Loan Disb 3,794,392.80
Nov 20, 2018 IBRD-83090 Loan Disb 5,017,988.50
Mar 15, 2019 IBRD-83090 Int Charges 974,634.70
Mar 15, 2019 IBRD-83090 Loan Repay 1,321,412.80
Mar 15, 2019 IBRD-83090 Int Charges 4,113.30
Apr 12, 2019 IBRD-83090 Loan Disb 4,784,174.50
Jun 28, 2019 IBRD-83090 Loan Disb 6,000,079.00
Jan 24, 2018 IBRD-83090 Loan Disb 2,121,970.80
Apr 3, 2018 IBRD-83090 Loan Disb 3,234,839.50
Mar 15, 2018 IBRD-83090 Int Charges 370,179.44
Dec 7, 2017 IBRD-83090 Loan Disb 4,877,598.50
Jan 29, 2016 IBRD-83090 Loan Disb 1,936,085.20
May 30, 2014 IBRD-83090 Loan Disb 250,000.00
May 30, 2014 IBRD-83090 Fee Charges 250,000.00
Sep 15, 2014 IBRD-83090 Int Charges 600.00
Jan 6, 2015 IBRD-83090 Loan Disb 2,386,551.80
Mar 15, 2015 IBRD-83090 Int Charges 13,416.85
Oct 10, 2014 IBRD-83090 Loan Disb 2,400,000.00
Mar 15, 2024 IBRD-83090 Int Charges 41,100.52
Mar 15, 2024 IBRD-83090 Int Charges 2,533,026.20
Mar 15, 2024 IBRD-83090 Loan Repay 1,953,906.80
Dec 27, 2013 IBRD-83090 Loan Commitment 100,000,000.00
Mar 15, 2023 IBRD-83090 Int Charges 95,826.07
Mar 15, 2023 IBRD-83090 Int Charges 2,070,366.20
Mar 15, 2023 IBRD-83090 Loan Repay 1,953,906.80
Sep 15, 2023 IBRD-83090 Int Charges 31,341.85
Sep 15, 2023 IBRD-83090 Int Charges 2,337,993.20
Sep 15, 2023 IBRD-83090 Loan Repay 1,953,906.80
Mar 15, 2022 IBRD-83090 Int Charges 380,360.40
Mar 15, 2022 IBRD-83090 Loan Repay 1,953,906.80
Sep 15, 2022 IBRD-83090 Int Charges 788,478.50
Sep 15, 2022 IBRD-83090 Loan Repay 1,953,906.80
Sep 15, 2020 IBRD-83090 Int Charges 23,555.45
Sep 15, 2020 IBRD-83090 Int Charges 651,608.40
Sep 15, 2020 IBRD-83090 Loan Repay 2,008,672.60
Nov 12, 2020 IBRD-83090 Loan Cancel 3,420,807.80
Nov 12, 2020 IBRD-83090 Loan Disb -2,519,116.00
Mar 15, 2021 IBRD-83090 Int Charges 446,815.25
Mar 15, 2021 IBRD-83090 Loan Repay 1,953,906.80
Sep 15, 2021 IBRD-83090 Int Charges 408,934.30
Sep 15, 2021 IBRD-83090 Loan Repay 1,953,906.80
Jun 11, 2018 IBRD-83090 Loan Disb 4,870,243.50
Mar 30, 2017 IBRD-83090 Loan Disb 7,009,242.50
Mar 15, 2017 IBRD-83090 Int Charges 197,844.95
Nov 17, 2017 IBRD-83090 Loan Disb 3,150,566.50
Sep 15, 2017 IBRD-83090 Int Charges 313,463.84
Jun 28, 2016 IBRD-83090 Loan Disb 5,209,492.00
Dec 16, 2016 IBRD-83090 Loan Disb 4,001,689.50
Nov 30, 2015 IBRD-83090 Loan Disb 1,919,908.00
Sep 15, 2015 IBRD-83090 Int Charges 28,872.17
Dec 21, 2015 IBRD-83090 Loan Disb 1,070,861.40
Mar 15, 2016 IBRD-83090 Int Charges 56,965.78
Sep 15, 2016 IBRD-83090 Int Charges 122,662.23
Sep 15, 2016 IBRD-83090 Int Charges 2,696.53
May 13, 2015 IBRD-83090 Loan Disb 500,000.00
Jun 17, 2015 IBRD-83090 Loan Disb 1,426,738.60
Oct 14, 2015 IBRD-83090 Loan Disb 2,088,799.90

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Satisfactory 2020-06-30
Overall Implementation Progress (IP) Highly Satisfactory 2020-06-30
Progress towards achievement of PDO Highly Satisfactory 2020-06-30
Procurement Satisfactory 2020-06-30
Project Management Highly Satisfactory 2020-06-30
Monitoring and Evaluation Highly Satisfactory 2020-06-30

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-18-2020
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-08-2021PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Indicator One: Number of beneficiaries with access to improved infrastructure services in project villagesValue0.00145788.00145357.00
    DateDecember 30, 2013June 25, 2020December 31, 2019
    Comment
  • Indicator Two: Number of Tourists visiting project villages which have implemented the cultural heritage conservation component of the project. ('000)Value2580.003754.003630.00
    DateDecember 30, 2013June 25, 2020December 31, 2019
    Comment
  • Indicator three: Number of enhanced economic opportunities related jobs createdValue0.004565.004200.00
    DateDecember 30, 2013June 25, 2020December 31, 2019
    Comment
  • Indicator one (i): Number of beneficiaries with access to an all season road within 500m rangeValue0.00126299.0012000.00
    DateDecember 30, 2013March 31, 2015
    Comment
  • Indicator one (ii): Number of beneficiaries with access to improved water sources.Value0.0031770.0018000.00
    DateDecember 30, 2013March 31, 2015
    Comment
  • Indicator one (iii): Number of beneficiaries with access to improved sanitation.Value0.0011407.0012000.00
    DateDecember 30, 2013March 31, 2015
    Comment
  • Indicator One: (0) Number of beneficiaries with access to improved infrastructure services in project villages of which womenValue0.0066972.0030000.00
    DateDecember 30, 2013
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • IOI 1-1: Increased length of roads constructed/rehabilitated under the projectValue0.00426.00370.00
    DateDecember 30, 2013June 25, 2020December 31, 2019
    Comment
  • IOI 2-1: Area of historic buildings restoredValue0.0058062.0057953.00
    DateDecember 30, 2013June 25, 2020December 31, 2019
    Comment
  • IOI 3-1: Area of production bases developed in project villagesValue0.00684.00600.00
    DateDecember 30, 2013June 25, 2020December 31, 2019
    Comment
  • IOI 4-1: Staff from various line departments trained - men and womenValue0.002908.002600.00
    DateDecember 30, 2013June 25, 2020December 31, 2019
    Comment
  • IOI 1-2: Length of water supply pipeline installed under the project.Value0.00256.00241.00
    DateDecember 30, 2013June 25, 2020December 31, 2019
    Comment
  • IOI 2-2: Increase in number of audience attending exhibitions and performanesValue0.0054284.0035000.00
    DateDecember 30, 2013June 25, 2020December 31, 2019
    Comment
  • IOI 3-2: Farmers trained in new agriculture technologiesValue0.004831.004600.00
    DateDecember 30, 2013June 25, 2020December 31, 2019
    Comment
  • IOI 4-1 (i): Staff from various line departments trained - of which womenValue0.001119.001080.00
    DateDecember 30, 2013June 25, 2020December 31, 2019
    Comment
  • IOI 1-3 :Increased daily production of quality water supply under the projectValue0.0011715.0010226.00
    DateDecember 30, 2013June 25, 2020December 31, 2019
    Comment
  • IOI 2-3: number of successors trained for traditional arts and techniquesValue0.001409.00900.00
    DateDecember 30, 2013June 25, 2020December 31, 2019
    Comment
  • IOI 4-2: PMO and PIU Staff trainedValue0.002110.001500.00
    DateDecember 30, 2013June 25, 2020December 31, 2019
    Comment
  • IOI 3-2: (i) Farmers trained in new agriculture technologies of which womenValue0.002191.002180.00
    DateDecember 30, 2013June 25, 2020December 31, 2019
    Comment
  • IOI 1-4: Increased daily capacity of wastewater treatment and disposal facilities under the projectValue0.001921.001663.00
    DateDecember 30, 2013June 25, 2020December 31, 2019
    Comment
  • IOI 3-3: Rural residents trained in provision of tourism servicesValue0.002401.002400.00
    DateDecember 30, 2013June 25, 2020December 31, 2019
    Comment
  • IOI 4-3: Number of units trained in O&MValue0.0095.0068.00
    DateDecember 30, 2013June 25, 2020December 31, 2019
    Comment
  • IOI 1-5: Land area with improved access to irrigation and flood control with improved irrigation and drainage servicesValue0.004198.004151.00
    DateDecember 30, 2013June 25, 2020December 31, 2019
    Comment
  • IOI 3-3: (i) Rural residents trained in provision of tourism services of which womenValue0.001361.001350.00
    DateDecember 30, 2013June 25, 2020December 31, 2019
    Comment
  • IOI 3-4: Increase in number of tourism facilitiesValue0.00301.00215.00
    DateDecember 30, 2013June 25, 2020December 31, 2019
    Comment