Bolivia Climate Resilience - Integrated Basin Management

Abstract*

The development objective of the Climate Resilience - Integrated Basin Management Project for Bolivia is to support the implementation of Borrower's strategic program for climate resilience by: (a) strengthening the Borrower's institutional capacity to define the new integrated river basin management approach to climate change adaptation; and (b) supporting its implementation in three pilot sub-basins in the Rio Grande basin. The project comprises...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective of the Project is to support the implementation of Borrower's Strategic Program for Climate Resilience by:(a)strengthening the Borrower's institutional capacity to define the new integrated river basin management approach to climatechange adaptation; and (b) supporting its implementation in three pilot subbasins in the Rio Grande basin.

Key Details

Project Details

  • P129640

  • Closed

  • Martin Albrecht

  • PLURINATIONAL STATE OF BOLIVIA

  • Bolivia

  • April 30, 2012

  • (as of board presentation)

    July 25, 2014

  • May 7, 2015

  • US$ 71.40 million

  • SDC Departmental River Basin Service,FPS National Fund for Productive and Social Investment,Ministry of Environment and Water

  • Latin America and Caribbean

  • 2015

  • US$ 91.00 million

  • N/A

  • March 15, 2022

  • December 31, 2020

  • TBD

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Strategic Climate Fund Grant 19.00
Borrower/Recipient 25.90
Strategic Climate Fund Credit 72.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 91.00
Total Project Cost** 71.40

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jul 25, 2014 TF-16083 Loan Commitment 36,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Satisfactory 2020-06-29
Financial Management Moderately Satisfactory 2020-06-29
Progress towards achievement of PDO Moderately Satisfactory 2020-06-29
Overall Implementation Progress (IP) Moderately Satisfactory 2020-06-29
Project Management Moderately Satisfactory 2020-06-29
Monitoring and Evaluation Satisfactory 2020-06-29
Counterpart Funding Satisfactory 2020-06-29

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 09-30-2021
OutcomesModerately Satisfactory
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualityModestN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Adoption by the Government of an Integrated River Basin Planning Methodology that considers CC scenariosValueNoYes
    DateNovember 14, 2013August 31, 2021
    Comment
  • Number of government institutions using the tools developed and knowledge created by the PPCR for CC adaptationValue0.004.004.00
    DateNovember 14, 2013August 31, 2021May 28, 2020
    Comment
  • Availability and adequacy of timely and reliable hydro-meteorological data, forecasts and climate change related studies measured through the increasein target users satisfactionValue0.0020.830.00
    DateNovember 14, 2013August 31, 2021
    Comment
  • Number of pilot sub-basins where an Integrated River basin management system focused on improving climate resilience is operationalValue0.002.000.00
    DateNovember 14, 2013August 31, 2021
    Comment
  • Direct project beneficiariesValue0.0015041.003500.00
    DateNovember 14, 2013August 31, 2021May 28, 2020
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • MPD, MMyA and SDC demonstrate a better capacity to understand and take into account climate change impacts, through a capacity assessmentValueNoYes
    DateJune 23, 2014August 31, 2021
    Comment
  • Number of IRBM participation mechanisms establishedValue0.002.000.00
    DateNovember 14, 2012August 31, 2021
    Comment
  • Area provided with irrigation and drainage services (ha)Value0.003581.000.00
    DateJune 23, 2012August 31, 2021
    Comment
  • Installed capacities for the operation of the National Climate Change and Water Information System and of the national drought monitoring systemValueNoYes
    DateJune 23, 2014August 31, 2021
    Comment
  • Number of new or rehabilitated hydro-meteorological monitoring stationsValue0.0060.0060.00
    DateNovember 14, 2013August 31, 2021May 28, 2020
    Comment
  • Number of protocols that establish and define the coordination and continuous interchange of hydro-meteorological information between the identified relevant institutions.Value0.005.000.00
    DateNovember 14, 2013August 31, 2021
    Comment
  • Number of hydro-meteorological stations installedValue0.0055.0045.00
    DateNovember 14, 2013August 31, 2021May 28, 2020
    Comment
  • Website for dissemination of centralized hydro-meteorological data is operationalValueNoNo
    DateNovember 14, 2013August 31, 2021
    Comment
  • Additional area protected from erosion (Ha)Value0.002238.452300.00
    DateNovember 14, 2013August 31, 2021May 28, 2020
    Comment
  • Number of hydro-meteorological stations rehabilitatedValue0.005.005.00
    DateNovember 14, 2013August 31, 2021May 28, 2020
    Comment
  • Number of operating drought and flood early warning systems.Value0YesYes
    DateNovember 14, 2013August 31, 2021May 28, 2020
    Comment
  • Length of waterways equipped with new or rehabilitated defensive flood protection infrastructure or natural bank stabilizationValue0.0028696.661700.00
    DateNovember 14, 2013August 31, 2021May 28, 2020
    Comment
  • Number of integrated river basin management plans elaborated with the Integrated River Basin Planning methodology of MMAyA adoptedValue0.002.000.00
    DateNovember 14, 2013August 31, 2021
    Comment
  • Number of water basin management sub-projects within the pilot river basins financed by PPCRValue0.0017.0017.00
    DateNovember 14, 2013August 31, 2021May 28, 2020
    Comment