Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 150.00 |
P129652
Closed
Tania Dmytraczenko
N/A
May 25, 2012
(as of board presentation)
May 21, 2013
October 3, 2013
US$ 150.00 million
Secretaria de Estado da Fazenda - SERGIPE
2013
US$ 150.00 million
N/A
Not Applicable
December 31, 2014
BANK APPROVED
December 3, 2014
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 150.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 150.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 150.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 150.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jan 15, 2016 | IBRD-82570 | Int Charges | 3,112,500.00 |
Jul 15, 2017 | IBRD-82570 | Int Charges | 3,180,000.00 |
Jan 15, 2018 | IBRD-82570 | Int Charges | 3,187,500.00 |
Jul 17, 2018 | IBRD-82570 | Int Charges | 3,195,000.00 |
Jul 17, 2018 | IBRD-82570 | Loan Repay | 2,490,000.00 |
Jan 15, 2019 | IBRD-82570 | Int Charges | 3,156,714.00 |
Jan 15, 2019 | IBRD-82570 | Loan Repay | 2,490,000.00 |
Jan 15, 2019 | IBRD-82570 | Int Charges | 592.07 |
Jul 15, 2019 | IBRD-82570 | Int Charges | 3,117,930.00 |
Jul 15, 2019 | IBRD-82570 | Loan Repay | 2,490,000.00 |
Jan 15, 2020 | IBRD-82570 | Loan Repay | 2,490,000.00 |
Jan 15, 2020 | IBRD-82570 | Int Charges | 3,057,268.50 |
Jul 15, 2020 | IBRD-82570 | Int Charges | 2,996,856.00 |
Jul 15, 2020 | IBRD-82570 | Loan Repay | 2,490,000.00 |
Jan 15, 2021 | IBRD-82570 | Int Charges | 2,957,325.00 |
Jan 15, 2021 | IBRD-82570 | Loan Repay | 2,490,000.00 |
Jul 15, 2021 | IBRD-82570 | Int Charges | 2,917,296.00 |
Jul 15, 2021 | IBRD-82570 | Loan Repay | 2,490,000.00 |
Jul 15, 2022 | IBRD-82570 | Int Charges | 2,822,736.00 |
Jul 15, 2022 | IBRD-82570 | Loan Repay | 2,490,000.00 |
Jan 15, 2022 | IBRD-82570 | Int Charges | 2,870,140.50 |
Jan 15, 2022 | IBRD-82570 | Loan Repay | 2,490,000.00 |
Jan 15, 2023 | IBRD-82570 | Int Charges | 2,762,323.50 |
Jan 15, 2023 | IBRD-82570 | Loan Repay | 2,490,000.00 |
Jul 15, 2023 | IBRD-82570 | Int Charges | 2,670,885.00 |
Jul 15, 2023 | IBRD-82570 | Loan Repay | 2,490,000.00 |
Jan 15, 2024 | IBRD-82570 | Int Charges | 2,654,506.50 |
Jan 15, 2024 | IBRD-82570 | Loan Repay | 2,490,000.00 |
Jul 15, 2024 | IBRD-82570 | Int Charges | 2,624,622.00 |
Jul 15, 2024 | IBRD-82570 | Loan Repay | 2,490,000.00 |
May 21, 2013 | IBRD-82570 | Loan Commitment | 150,000,000.00 |
Oct 3, 2013 | IBRD-82570 | Loan Disb | 375,000.00 |
Oct 3, 2013 | IBRD-82570 | Fee Charges | 375,000.00 |
Jan 15, 2014 | IBRD-82570 | Int Charges | 343,603.66 |
Oct 10, 2013 | IBRD-82570 | Loan Disb | 149,624,992.00 |
Jan 15, 2014 | IBRD-82570 | Loan Disb | -150,000,000.00 |
Jan 15, 2014 | IBRD-82570 | Loan Disb | 150,000,000.00 |
Jul 15, 2014 | IBRD-82570 | Int Charges | 3,345,000.00 |
Jan 15, 2015 | IBRD-82570 | Int Charges | 2,782,500.00 |
Jul 15, 2015 | IBRD-82570 | Int Charges | 3,097,500.00 |
Jul 15, 2016 | IBRD-82570 | Int Charges | 3,127,500.00 |
Jan 15, 2017 | IBRD-82570 | Int Charges | 3,157,500.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2014-12-18 |
Program Management | Satisfactory | 2014-12-18 |
Monitoring and Evaluation | Satisfactory | 2014-12-18 |
Overall Implementation Progress (IP) | Satisfactory | 2014-12-18 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-24-2015 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | Modest |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Moderately Satisfactory |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 07-08-2016 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Unsatisfactory | N/a |
Risk To Development Outcome | Modest | N/a |
Bank Performance | Moderately Unsatisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Increase responsiveness to citizen complaints in the Citizen Service Centers (CEAC) | Value | 15.00 | 100.00 | 90.00 |
Date | October 31, 2011 | November 30, 2013 | December 31, 2013 | |
Comment |
Increase the number of seasonal workers benefitting from the program Mão Amiga included in the program Sergipe Alfabetizado | Value | 0 | 241 of which 74 are women | 565 of which 1/8 are women |
Date | February 29, 2012 | December 31, 2013 | December 31, 2013 | |
Comment |
Increase in revenues collected from tax arrears as a share of the stock of tax arrears | Value | 0.43 | 0.39 | 0.52 |
Date | December 31, 2011 | December 31, 2013 | December 31, 2013 | |
Comment |
Reduce the cesarean section rate at the referral Maternity Hospital Nossa Senhora de Lourdes according to the guidelines in Portaria No. 3477/1998 | Value | 55.20 | 57.46 | 50.20 |
Date | December 31, 2011 | December 31, 2013 | December 31, 2013 | |
Comment |
Increase # of small producers in the Program for Agroecological Production and linked to the Social Control Orgs. selling directly in agroecological fairs and to private and public/inst. markets | Value | 83 producers, 5 women | 114 producers, 44 women | 100 producers, 15 women |
Date | December 31, 2011 | December 31, 2013 | December 31, 2013 | |
Comment |
Increase the number of maternity hospitals implementing the protocol for classification of admissions by risk (Acolhimento com Classificação de Risco – ACCR) | Value | 1.00 | 3.00 | 3.00 |
Date | December 31, 2011 | December 31, 2013 | December 31, 2013 | |
Comment |
Increase the number of women in situations of violence and vulnerability attended in the Rede de Atendimento à Mulher Vítima de Violência | Value | 3985.00 | 7630.00 | 6973.00 |
Date | March 31, 2012 | December 31, 2013 | December 31, 2013 | |
Comment |
Reduce the time to produce agreed upon managerial reports through i-Gesp | Value | 0.00 | 4.00 | 4.00 |
Date | December 31, 2011 | December 31, 2013 | December 31, 2013 | |
Comment |
Increase the number of school directors selected by merit and with signed management agreements | Value | 0.00 | 159.00 | 151.00 |
Date | December 31, 2011 | December 31, 2013 | December 31, 2013 | |
Comment |
Increase the number of municipalities receiving technical assistance from the State in the implementation of PNAIC | Value | 0.00 | 73.00 | 38.00 |
Date | December 31, 2011 | November 30, 2013 | December 31, 2013 | |
Comment |
Increase the number of families with monthly per capita income of less than R$70.00/month living in the poorest 15 municipalities included in the CadÚnico | Value | 39582.00 | 48396.00 | 41561.00 |
Date | December 31, 2011 | September 30, 2013 | December 31, 2013 | |
Comment |
Increase the number of trained small producer units included in the Núcleos de Produção de Leite and selling at least 90 percent oftheir production to private and public/institutional markets | Value | 3.00 | 30.00 | 30.00 |
Date | December 31, 2011 | November 30, 2013 | December 31, 2013 | |
Comment |