Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 216.00 |
Borrower/Recipient | 229.00 |
P130339
Closed
Justin Runji , N. Srinivas
India
September 12, 2012
(as of board presentation)
May 14, 2013
September 6, 2013
US$ 445.00 million
Public Works Department, Govt of Kerala
2013
US$ 216.00 million
A
August 1, 2023
April 30, 2021
Yes
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 216.00 |
Borrower/Recipient | 229.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 216.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 216.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 445.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Oct 14, 2021 | IBRD-82540 | Loan Disb | 16,774,135.00 |
Sep 15, 2021 | IBRD-82540 | Int Charges | 519,184.80 |
Sep 15, 2021 | IBRD-82540 | Loan Repay | 7,607,134.50 |
Sep 15, 2021 | IBRD-82540 | Int Charges | 14,889.01 |
Mar 15, 2022 | IBRD-82540 | Int Charges | 541,565.10 |
Mar 15, 2022 | IBRD-82540 | Loan Repay | 8,491,132.00 |
Jun 8, 2018 | IBRD-82540 | Loan Disb | 1,618,328.10 |
Sep 15, 2018 | IBRD-82540 | Loan Repay | 3,738,241.20 |
Jan 29, 2019 | IBRD-82540 | Loan Disb | 4,581,162.00 |
Sep 27, 2018 | IBRD-82540 | Loan Disb | 5,488,764.00 |
Jun 28, 2019 | IBRD-82540 | Loan Disb | 1,885,518.00 |
Jun 28, 2019 | IBRD-82540 | Loan Disb | 1,233,492.50 |
Apr 18, 2019 | IBRD-82540 | Loan Disb | 1,623,175.90 |
Mar 20, 2019 | IBRD-82540 | Loan Disb | 2,494,907.80 |
Mar 15, 2019 | IBRD-82540 | Int Charges | 256.71 |
Mar 15, 2019 | IBRD-82540 | Int Charges | 1,511,337.90 |
Mar 15, 2019 | IBRD-82540 | Loan Repay | 3,960,703.20 |
May 17, 2019 | IBRD-82540 | Loan Disb | 1,934,232.50 |
Nov 14, 2019 | IBRD-82540 | Loan Disb | 2,343,880.00 |
Sep 15, 2019 | IBRD-82540 | Int Charges | 17,465.68 |
Sep 15, 2019 | IBRD-82540 | Int Charges | 1,721,267.10 |
Sep 15, 2019 | IBRD-82540 | Loan Repay | 4,534,182.00 |
Mar 15, 2020 | IBRD-82540 | Int Charges | 1,365,947.20 |
Mar 15, 2020 | IBRD-82540 | Loan Repay | 4,689,237.00 |
Dec 13, 2019 | IBRD-82540 | Loan Disb | 1,220,602.80 |
May 12, 2020 | IBRD-82540 | Loan Disb | 4,072,047.80 |
Jan 23, 2020 | IBRD-82540 | Loan Disb | 1,229,419.90 |
Jun 30, 2020 | IBRD-82540 | Loan Disb | 3,579,776.00 |
Jun 22, 2016 | IBRD-82540 | Loan Disb | 1,689,780.80 |
Jun 29, 2017 | IBRD-82540 | Loan Disb | 3,722,550.50 |
Mar 15, 2017 | IBRD-82540 | Int Charges | 441,030.75 |
May 15, 2017 | IBRD-82540 | Loan Disb | 8,040,036.00 |
Oct 17, 2017 | IBRD-82540 | Loan Disb | 5,100,556.00 |
Sep 15, 2017 | IBRD-82540 | Int Charges | 5,330.22 |
Sep 15, 2017 | IBRD-82540 | Int Charges | 606,051.20 |
Sep 15, 2017 | IBRD-82540 | Int Charges | 16,815.26 |
Jan 12, 2018 | IBRD-82540 | Loan Disb | 4,691,737.50 |
Aug 11, 2017 | IBRD-82540 | Loan Disb | 3,438,464.00 |
Jul 31, 2018 | IBRD-82540 | Loan Disb | 72,788.17 |
May 9, 2018 | IBRD-82540 | Loan Disb | 1,036,416.50 |
Sep 15, 2018 | IBRD-82540 | Int Charges | 1,852.23 |
Jun 26, 2018 | IBRD-82540 | Loan Disb | 2,024,754.20 |
Sep 15, 2018 | IBRD-82540 | Int Charges | 1,333,094.80 |
Nov 18, 2014 | IBRD-82540 | Loan Disb | 1,274,823.90 |
Jan 16, 2014 | IBRD-82540 | Loan Disb | 1,694,832.60 |
Jan 30, 2014 | IBRD-82540 | Loan Disb | 1,711,564.00 |
Sep 6, 2013 | IBRD-82540 | Loan Disb | 540,000.00 |
Sep 6, 2013 | IBRD-82540 | Fee Charges | 540,000.00 |
May 9, 2014 | IBRD-82540 | Loan Disb | 50,000.00 |
Mar 15, 2014 | IBRD-82540 | Int Charges | 90.45 |
Mar 15, 2014 | IBRD-82540 | Int Charges | 3,591.42 |
Dec 23, 2013 | IBRD-82540 | Loan Disb | 1,233,766.50 |
Mar 26, 2014 | IBRD-82540 | Loan Disb | 2,510,843.20 |
Jun 24, 2014 | IBRD-82540 | Loan Disb | 1,701,813.60 |
Feb 3, 2015 | IBRD-82540 | Loan Disb | 3,442,014.50 |
Sep 15, 2014 | IBRD-82540 | Int Charges | 3,134.60 |
Sep 15, 2014 | IBRD-82540 | Int Charges | 25,587.11 |
Mar 31, 2015 | IBRD-82540 | Loan Disb | 3,317,363.20 |
Mar 30, 2015 | IBRD-82540 | Loan Disb | 3,315,591.00 |
Mar 15, 2015 | IBRD-82540 | Int Charges | 12.10 |
Mar 15, 2015 | IBRD-82540 | Int Charges | 32,563.71 |
Jul 24, 2014 | IBRD-82540 | Loan Disb | 13,694.98 |
Aug 4, 2015 | IBRD-82540 | Loan Disb | 135,559.73 |
Jun 23, 2015 | IBRD-82540 | Loan Disb | 3,131,954.80 |
Oct 22, 2015 | IBRD-82540 | Loan Disb | 3,036,810.50 |
Sep 15, 2015 | IBRD-82540 | Int Charges | 2,409.41 |
Sep 15, 2015 | IBRD-82540 | Int Charges | 80,880.63 |
Mar 15, 2016 | IBRD-82540 | Int Charges | 115.44 |
Mar 15, 2016 | IBRD-82540 | Int Charges | 119,204.95 |
Jan 21, 2016 | IBRD-82540 | Loan Disb | 8,513,268.00 |
Sep 15, 2016 | IBRD-82540 | Int Charges | 290,545.34 |
Sep 15, 2016 | IBRD-82540 | Int Charges | 11,365.21 |
Apr 28, 2016 | IBRD-82540 | Loan Disb | 2,411,390.00 |
Mar 23, 2016 | IBRD-82540 | Loan Disb | 5,381,554.00 |
Jun 30, 2016 | IBRD-82540 | Loan Disb | 2,446,886.80 |
Oct 14, 2016 | IBRD-82540 | Loan Disb | 4,005,409.80 |
Nov 28, 2016 | IBRD-82540 | Loan Disb | 3,257,141.00 |
Feb 9, 2017 | IBRD-82540 | Loan Disb | 3,399,851.20 |
Mar 15, 2024 | IBRD-82540 | Int Charges | 3,991,820.80 |
Mar 15, 2024 | IBRD-82540 | Loan Repay | 8,491,132.00 |
Mar 15, 2024 | IBRD-82540 | Int Charges | 69,582.21 |
May 14, 2013 | IBRD-82540 | Loan Commitment | 216,000,000.00 |
Sep 15, 2022 | IBRD-82540 | Int Charges | 1,276,174.20 |
Sep 15, 2022 | IBRD-82540 | Loan Repay | 8,491,132.00 |
Mar 15, 2023 | IBRD-82540 | Int Charges | 174,055.25 |
Mar 15, 2023 | IBRD-82540 | Int Charges | 3,490,944.50 |
Mar 15, 2023 | IBRD-82540 | Loan Repay | 8,491,132.00 |
Sep 15, 2023 | IBRD-82540 | Loan Repay | 8,491,132.00 |
Sep 15, 2023 | IBRD-82540 | Int Charges | 55,040.69 |
Sep 15, 2023 | IBRD-82540 | Int Charges | 3,819,537.20 |
Oct 23, 2020 | IBRD-82540 | Loan Cancel | 20,000,000.00 |
Nov 12, 2020 | IBRD-82540 | Loan Disb | 4,034,188.20 |
Sep 15, 2020 | IBRD-82540 | Int Charges | 4,510.60 |
Sep 15, 2020 | IBRD-82540 | Int Charges | 676,989.75 |
Sep 15, 2020 | IBRD-82540 | Loan Repay | 5,093,333.50 |
Mar 15, 2021 | IBRD-82540 | Int Charges | 429,746.84 |
Mar 15, 2021 | IBRD-82540 | Loan Repay | 5,285,764.50 |
Jan 21, 2021 | IBRD-82540 | Loan Disb | 12,965,760.00 |
Apr 28, 2021 | IBRD-82540 | Loan Disb | 29,624,956.00 |
Jun 10, 2021 | IBRD-82540 | Loan Disb | 3,744,020.50 |
Mar 9, 2018 | IBRD-82540 | Loan Disb | 5,818,523.50 |
Mar 15, 2018 | IBRD-82540 | Int Charges | 6,251.32 |
Mar 15, 2018 | IBRD-82540 | Int Charges | 760,781.75 |
Apr 6, 2018 | IBRD-82540 | Loan Disb | 3,389,893.80 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Moderately Satisfactory | 2021-05-05 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2021-05-05 |
Progress towards achievement of PDO | Moderately Satisfactory | 2021-05-05 |
Project Management | Moderately Satisfactory | 2021-05-05 |
Financial Management | Moderately Satisfactory | 2021-05-05 |
Monitoring and Evaluation | Moderately Satisfactory | 2021-05-05 |
Procurement | Moderately Satisfactory | 2021-05-05 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-23-2022 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Direct project beneficiaries | Value | 13.40 | 17.33 | 0.00 |
Date | April 17, 2013 | April 30, 2021 | ||
Comment |
Female beneficiaries | Value | 7.00 | 7.35 | 0.00 |
Date | April 30, 2013 | April 13, 2018 | ||
Comment |
A reduction of travel time on the improved project roads (3 priority corridors) | Value | K-K:29; P-P:21; T-V:58 | K-K:23; P-P:17.5; T-V:58 | |
Date | April 17, 2013 | April 30, 2021 | ||
Comment |
Improved riding quality of project roads | Value | 0 km with IRI <4 | 375 | 408 |
Date | April 17, 2013 | April 30, 2021 | August 27, 2020 | |
Comment |
A reduction in annual fatality count of total and vulnerable road users on demonstration corridor (No. of fatalities/year of which women) | Value | 80.00 | 43.00 | 65.00 |
Date | April 17, 2013 | April 30, 2021 | June 19, 2019 | |
Comment |
Reduction in number of vulnerable fatalities/year | Value | 49.00 | 49.00 | 0.00 |
Date | April 23, 2013 | August 31, 2017 | ||
Comment |
Climate change and disaster resilience vulnerability assessment on all new project corridors taken up under RKI | Value | No | Yes | |
Date | June 19, 2019 | April 30, 2021 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
State Highways upgraded | Value | 0.00 | 331.00 | 333.00 |
Date | April 17, 2013 | April 30, 2021 | August 27, 2020 | |
Comment |
Pilot safety corridor developed | Value | 0.00 | 82.00 | 0.00 |
Date | April 17, 2013 | April 30, 2021 | ||
Comment |
Modernization of PWD | Value | Existing PWD | PWD website with integrated e-governance system WI | |
Date | April 17, 2013 | April 30, 2021 | ||
Comment |
Number of km of PWD roads re-built/re-constructed (Kiliometers) | Value | 0.00 | 44.00 | 0.00 |
Date | June 19, 2019 | April 30, 2021 | ||
Comment |
Number of district level road safety improvement schemes implemented through challenge fund | Value | 0.00 | 0.00 | 5.00 |
Date | April 17, 2013 | April 30, 2021 | June 19, 2019 | |
Comment |
Functioning Road Asset Management System | Value | No functional road asset management system | Supply, installation and configuration of RAMS in | |
Date | April 17, 2013 | April 30, 2021 | ||
Comment |
Communications strategy and interfaces for public engagement implemented | Value | No communications strategy | PWD helpline is being used as a stop-gap arrangeme | |
Date | April 17, 2013 | April 30, 2021 | ||
Comment |
Regular road user surveys conducted | Value | No formal road user survey | RUSS was completed for 239.2 km of project roads. | |
Date | April 17, 2013 | April 30, 2021 | ||
Comment |