Financier | Commitments |
---|---|
Borrower/Recipient | 4.30 |
International Bank for Reconstruction and Development | 10.00 |
P131029
Closed
Carmen Veronica Del Rosario Silva Villalobos
Republic of Peru
July 18, 2012
(as of board presentation)
December 13, 2012
April 11, 2013
US$ 14.30 million
Ministry of Development and Social Inclusion,Ministry of Economy and Finance
2013
US$ 10.00 million
C
Not Applicable
March 31, 2018
Yes
BANK APPROVED
September 12, 2023
Financier | Commitments |
---|---|
Borrower/Recipient | 4.30 |
International Bank for Reconstruction and Development | 10.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 10.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 10.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 14.30 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 13, 2012 | IBRD-82220 | Loan Commitment | 10,000,000.00 |
Mar 15, 2015 | IBRD-82220 | Int Charges | 2,404.15 |
Dec 21, 2018 | IBRD-82220 | Loan Repay | 6,105,513.50 |
Mar 15, 2018 | IBRD-82220 | Int Charges | 87,150.45 |
Mar 15, 2018 | IBRD-82220 | Loan Repay | 1,561,588.90 |
Dec 8, 2017 | IBRD-82220 | Loan Disb | 630,000.00 |
Jun 8, 2018 | IBRD-82220 | Loan Disb | -173,721.06 |
Jul 31, 2018 | IBRD-82220 | Loan Cancel | 806,061.06 |
Sep 15, 2018 | IBRD-82220 | Int Charges | 108,799.10 |
Sep 15, 2018 | IBRD-82220 | Loan Repay | 1,526,836.40 |
Sep 29, 2016 | IBRD-82220 | Loan Disb | 800,000.00 |
Dec 22, 2016 | IBRD-82220 | Loan Disb | 1,400,000.00 |
Mar 15, 2017 | IBRD-82220 | Int Charges | 66,082.58 |
Sep 15, 2017 | IBRD-82220 | Int Charges | 83,512.62 |
Aug 27, 2015 | IBRD-82220 | Loan Disb | 2,426,920.00 |
Sep 15, 2015 | IBRD-82220 | Int Charges | 3,572.09 |
Mar 15, 2016 | IBRD-82220 | Int Charges | 935.03 |
Mar 15, 2016 | IBRD-82220 | Int Charges | 16,609.73 |
Dec 29, 2015 | IBRD-82220 | Loan Disb | 600,000.00 |
Feb 23, 2016 | IBRD-82220 | Loan Disb | 2,500,000.00 |
Sep 15, 2016 | IBRD-82220 | Int Charges | 1,297.92 |
Sep 15, 2016 | IBRD-82220 | Int Charges | 42,770.80 |
Aug 13, 2013 | IBRD-82220 | Loan Disb | 114,000.00 |
Feb 7, 2014 | IBRD-82220 | Loan Disb | 645,000.00 |
Mar 15, 2014 | IBRD-82220 | Int Charges | 73.15 |
Mar 15, 2014 | IBRD-82220 | Int Charges | 372.56 |
Sep 15, 2014 | IBRD-82220 | Int Charges | 419.25 |
Sep 15, 2014 | IBRD-82220 | Int Charges | 2,327.60 |
Apr 23, 2015 | IBRD-82220 | Loan Disb | 251,740.00 |
Dec 21, 2018 | IBRD-82220 | Int Charges | 50,175.44 |
Name | Review | Date |
---|---|---|
Project Management | Satisfactory | 2017-12-07 |
Overall Implementation Progress (IP) | Satisfactory | 2017-12-07 |
Counterpart Funding | Satisfactory | 2017-12-07 |
Monitoring and Evaluation | Satisfactory | 2017-12-07 |
Progress towards achievement of PDO | Satisfactory | 2017-12-07 |
Procurement | Satisfactory | 2017-12-07 |
Financial Management | Moderately Satisfactory | 2017-12-07 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 11-30-2018 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 04-12-2019 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Key monitoring and evaluation, and coordination mechanisms are established | Value | 0.00 | 3.00 | 3.00 |
Date | April 30, 2013 | June 30, 2017 | October 31, 2017 | |
Comment |
Coverage of MIDIS programs is improved | Value | 0.00 | 2.00 | 4.00 |
Date | April 30, 2013 | June 30, 2017 | October 31, 2017 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
MIDIS designs and implements a policy tool to coordinate interventions to reduce chronic malnutrition (Number of operations rules designed to coordinate interventions to reduce chronic malnutrition). | Value | 0.00 | 2.00 | 3.00 |
Date | April 30, 2013 | June 30, 2017 | October 31, 2017 | |
Comment |
MIDIS operates in a de-concentrated way along the country’s territory (steps to support that MIDIS's one-stop shops or decentralized offices use tool for territorial coordination). | Value | 0.00 | 4.00 | 4.00 |
Date | April 30, 2013 | June 30, 2017 | October 31, 2017 | |
Comment |
Improved performance of SISFOH by interconnecting Local Targeting Units (Percentage of ULEs interconnected and with their staff trained on standardized practices). | Value | 0.00 | 100.00 | 100.00 |
Date | April 30, 2013 | June 30, 2017 | October 31, 2017 | |
Comment |
Improvement in quality of MIDIS's programs as shown by the implementation of users accountability mechanisms (number of MIDIS's programs with user accountability mechanisms). | Value | 0.00 | 4.00 | 4.00 |
Date | April 30, 2013 | June 30, 2017 | October 31, 2017 | |
Comment |
MIDIS is implementing an integrated information system for its programs (number of MIDIS's programs that share a common informationplatform). | Value | 0.00 | 4.00 | 4.00 |
Date | April 30, 2013 | June 30, 2017 | October 31, 2017 | |
Comment |
A national communications strategy for MIDIS is in place and includes different approaches for different population groups (i.e., indigenous peoples) (Number of steps completed). | Value | 0.00 | 1.00 | 1.00 |
Date | April 30, 2013 | June 30, 2017 | October 31, 2017 | |
Comment |
MIDIS monitors infant malnutrition and development plans indicators at the regional level (number of regions). | Value | 0.00 | 10.00 | 26.00 |
Date | April 30, 2013 | June 30, 2017 | October 31, 2017 | |
Comment |
MIDIS's programs and policies are being evaluated (number of programs and policies that are being evaluated). | Value | 0.00 | 6.00 | 7.00 |
Date | April 30, 2013 | June 30, 2017 | November 27, 2017 | |
Comment |
MIDIS introduces results-oriented human resource management practices (number of steps completed). | Value | 0.00 | 1.00 | 3.00 |
Date | April 30, 2013 | June 30, 2017 | October 31, 2017 | |
Comment |