Skip to Main Navigation

Disaster Risk Management Project

Abstract*

The objectives of the Disaster Risk Management Project (DRM) for Honduras are to support: (a) continue strengthening its capacity for integrated disaster risk management at the municipal and national level; and (b) improve its capacity to respond promptly and effectively to an eligible emergency. There are four components to the project, the first component being strengthening of national-level DRM capacities. The second component is the strengthening...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objectives are to support Honduras to: (a) continue strengthening its capacity for integrated disaster riskmanagement at the municipal and national level; and (b) improve its capacity to respond promptly and effectively to an eligible emergency.

Key Details

Project Details

  • P131094

  • Closed

  • Eduardo Ereno Blanchet , Horacio Cristian Terraza

  • Republic of Honduras

  • Honduras

  • August 14, 2012

  • (as of board presentation)

    December 13, 2012

  • March 18, 2013

  • US$ 30.00 million

  • COPECO -Comision Permanente de Contingencias (COPECO)

  • Latin America and Caribbean

  • 2013

  • US$ 30.00 million

  • B

  • December 22, 2021

  • June 30, 2021

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 30.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 30.00
IBRD + IDA Commitment 30.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 30.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 23, 2013 IDA-51900 Loan Disb 394,111.03
Jan 10, 2014 IDA-51900 Loan Disb 307,511.03
Jan 27, 2014 IDA-51900 Loan Disb 11,810.74
Jan 27, 2014 IDA-51900 Loan Disb 23,328.49
Jan 27, 2014 IDA-51900 Loan Disb 10,598.73
Jan 27, 2014 IDA-51900 Loan Disb 51,413.87
Jan 27, 2014 IDA-51900 Loan Disb 60,073.29
Jan 27, 2014 IDA-51900 Loan Disb 24,546.91
Feb 25, 2014 IDA-51900 Loan Disb 3,233.93
Nov 1, 2013 IDA-51900 Loan Disb 165,573.88
Jan 21, 2014 IDA-51900 Loan Disb 307,331.40
Feb 3, 2014 IDA-51900 Loan Disb 11,976.49
Sep 25, 2013 IDA-51900 Loan Disb 9,444.67
Oct 15, 2013 IDA-51900 Int Charges 1,950.81
Oct 15, 2013 IDA-51900 Int Charges 1,950.81
Oct 15, 2013 IDA-51900 Int Charges 3,200.66
Feb 25, 2014 IDA-51900 Loan Disb 4,340.25
Feb 25, 2014 IDA-51900 Loan Disb 5,266.29
Feb 25, 2014 IDA-51900 Loan Disb 10,047.30
Mar 25, 2014 IDA-51900 Loan Disb 5,405.30
Apr 22, 2014 IDA-51900 Loan Cancel 3,999,999.20
Jun 20, 2014 IDA-51900 Loan Disb 286,706.53
Apr 15, 2014 IDA-51900 Int Charges 51.33
Apr 15, 2014 IDA-51900 Int Charges 6,200.69
Apr 15, 2014 IDA-51900 Int Charges 6,200.69
Mar 12, 2015 IDA-51900 Loan Disb 373,489.75
Sep 17, 2014 IDA-51900 Loan Disb 277,507.78
Dec 12, 2014 IDA-51900 Loan Disb 644,985.44
Apr 15, 2015 IDA-51900 Int Charges 176.98
Apr 15, 2019 IDA-51900 Int Charges 79,588.75
Apr 15, 2019 IDA-51900 Int Charges 5,708.42
May 24, 2019 IDA-51900 Loan Disb 351,217.90
Nov 22, 2019 IDA-51900 Loan Disb 290,985.22
Sep 3, 2019 IDA-51900 Loan Disb 220,566.44
Oct 15, 2019 IDA-51900 Int Charges 85,106.60
Oct 15, 2019 IDA-51900 Int Charges 2,537.73
Oct 15, 2019 IDA-51900 Loan Repay 382,631.90
Oct 15, 2019 IDA-51900 Int Charges 51,063.97
Oct 15, 2019 IDA-51900 Int Charges 51,063.97
Oct 15, 2019 IDA-51900 Loan Disb 332,806.25
Apr 15, 2017 IDA-51900 Int Charges 33,236.19
Apr 15, 2017 IDA-51900 Int Charges 886.09
Apr 15, 2017 IDA-51900 Int Charges 886.09
Oct 15, 2017 IDA-51900 Int Charges 605.39
Oct 15, 2017 IDA-51900 Int Charges 39,258.37
Oct 15, 2017 IDA-51900 Int Charges 39,258.37
Oct 15, 2017 IDA-51900 Int Charges 64,196.16
Nov 14, 2017 IDA-51900 Loan Disb 569,503.20
Sep 20, 2017 IDA-51900 Loan Disb 497,797.84
Apr 15, 2015 IDA-51900 Int Charges 176.98
Apr 15, 2015 IDA-51900 Int Charges 25,079.45
Apr 15, 2015 IDA-51900 Int Charges 14,870.68
Apr 15, 2015 IDA-51900 Int Charges 14,870.68
Apr 15, 2024 IDA-51900 Int Charges 66,395.94
Apr 15, 2024 IDA-51900 Int Charges 66,395.94
Apr 15, 2024 IDA-51900 Int Charges 110,659.88
Apr 15, 2024 IDA-51900 Loan Repay 354,862.30
Dec 13, 2012 IDA-51900 Loan Commitment 30,000,000.00
Apr 15, 2023 IDA-51900 Loan Repay 18,412.97
Apr 15, 2023 IDA-51900 Loan Repay 356,430.20
Apr 15, 2023 IDA-51900 Int Charges 71,135.02
Apr 15, 2023 IDA-51900 Int Charges 71,135.02
Apr 15, 2023 IDA-51900 Int Charges 111,385.97
Oct 15, 2023 IDA-51900 Int Charges 6,935.88
Oct 15, 2023 IDA-51900 Loan Repay 362,482.03
Oct 15, 2023 IDA-51900 Int Charges 67,429.91
Oct 15, 2023 IDA-51900 Int Charges 67,429.91
Oct 15, 2023 IDA-51900 Int Charges 112,383.20
Apr 15, 2024 IDA-51900 Loan Repay 9,404.59
Apr 15, 2022 IDA-51900 Int Charges 124,595.72
Apr 15, 2022 IDA-51900 Loan Repay 3,631.51
Dec 2, 2021 IDA-51900 Loan Disb -107,147.59
Apr 15, 2022 IDA-51900 Loan Repay 374,479.72
Apr 15, 2022 IDA-51900 Int Charges 74,757.42
Apr 15, 2022 IDA-51900 Int Charges 74,757.42
Dec 2, 2021 IDA-51900 Loan Disb -67,028.65
Dec 2, 2021 IDA-51900 Loan Cancel 178,579.39
Oct 15, 2022 IDA-51900 Loan Repay 14,554.95
Oct 15, 2022 IDA-51900 Loan Repay 338,679.10
Oct 15, 2022 IDA-51900 Int Charges 68,358.82
Oct 15, 2022 IDA-51900 Int Charges 68,358.82
Oct 15, 2022 IDA-51900 Int Charges 113,931.35
Apr 15, 2020 IDA-51900 Loan Repay 653.14
Apr 15, 2020 IDA-51900 Int Charges 58,343.41
Apr 15, 2020 IDA-51900 Int Charges 97,239.03
Aug 31, 2020 IDA-51900 Loan Disb 309,568.34
Jun 11, 2020 IDA-51900 Loan Disb 329,320.66
Aug 20, 2020 IDA-51900 Loan Disb 330,661.28
Oct 15, 2020 IDA-51900 Loan Repay 393,901.28
Oct 30, 2020 IDA-51900 Loan Disb 335,728.88
Oct 15, 2020 IDA-51900 Loan Repay 116.94
Oct 15, 2020 IDA-51900 Int Charges 67,069.19
Oct 15, 2020 IDA-51900 Int Charges 67,069.19
Oct 15, 2020 IDA-51900 Int Charges 106,520.81
Sep 11, 2020 IDA-51900 Loan Disb 664,401.94
Oct 1, 2020 IDA-51900 Loan Disb 418,306.38
Oct 16, 2020 IDA-51900 Loan Disb 621,560.30
Aug 17, 2020 IDA-51900 Loan Disb 360,368.12
Nov 16, 2020 IDA-51900 Loan Disb 451,543.40
Aug 5, 2020 IDA-51900 Loan Disb 533,124.00
Feb 19, 2021 IDA-51900 Loan Disb 214,762.73
Dec 22, 2020 IDA-51900 Loan Disb 345,280.34
Apr 15, 2021 IDA-51900 Int Charges -0.01
Apr 15, 2021 IDA-51900 Int Charges -0.01
Apr 15, 2021 IDA-51900 Int Charges 5,324.86
Apr 15, 2021 IDA-51900 Loan Repay 398,786.00
Apr 15, 2021 IDA-51900 Int Charges 80,204.50
Apr 15, 2021 IDA-51900 Int Charges 80,204.50
Apr 15, 2021 IDA-51900 Int Charges 133,674.23
Apr 15, 2021 IDA-51900 Loan Repay 0.01
Oct 15, 2021 IDA-51900 Loan Repay 389,529.94
Oct 15, 2021 IDA-51900 Int Charges 79,210.20
Oct 15, 2021 IDA-51900 Int Charges 79,210.20
Oct 15, 2021 IDA-51900 Int Charges 132,016.94
Oct 15, 2021 IDA-51900 Loan Repay 4,588.78
Apr 15, 2019 IDA-51900 Int Charges 49,297.86
Apr 15, 2019 IDA-51900 Int Charges 49,297.86
May 18, 2015 IDA-51900 Loan Disb 214,357.50
Oct 15, 2015 IDA-51900 Int Charges 549.67
Oct 15, 2015 IDA-51900 Int Charges 549.67
Oct 15, 2015 IDA-51900 Int Charges 19,798.46
Oct 15, 2015 IDA-51900 Int Charges 19,798.46
Oct 15, 2015 IDA-51900 Int Charges 32,809.90
Oct 15, 2015 IDA-51900 Loan Disb 243,063.84
Sep 3, 2015 IDA-51900 Loan Disb 239,049.55
Dec 18, 2015 IDA-51900 Loan Disb 339,503.88
Oct 27, 2015 IDA-51900 Loan Disb 556,443.75
Dec 9, 2015 IDA-51900 Loan Disb 295,740.40
Jan 29, 2016 IDA-51900 Loan Disb 496,883.84
Nov 25, 2015 IDA-51900 Loan Disb 407,774.20
Apr 15, 2016 IDA-51900 Int Charges 27,510.38
Apr 15, 2016 IDA-51900 Int Charges 27,510.38
Apr 15, 2016 IDA-51900 Int Charges 45,850.58
Apr 15, 2016 IDA-51900 Int Charges 1,094.11
May 12, 2016 IDA-51900 Loan Disb 226,984.52
Oct 15, 2016 IDA-51900 Int Charges 50,647.53
Oct 15, 2016 IDA-51900 Int Charges 30,376.33
Oct 15, 2016 IDA-51900 Int Charges 30,376.33
Oct 15, 2016 IDA-51900 Int Charges 12.19
Oct 15, 2016 IDA-51900 Int Charges 12.19
Feb 25, 2014 IDA-51900 Loan Disb 4,742.56
Jan 14, 2015 IDA-51900 Loan Disb 696,386.44
Jul 16, 2013 IDA-51900 Loan Disb 117,584.15
Nov 21, 2014 IDA-51900 Loan Disb 257,789.44
Nov 19, 2014 IDA-51900 Loan Disb 335,836.12
Dec 3, 2014 IDA-51900 Loan Disb 326,292.97
Oct 16, 2014 IDA-51900 Int Charges 15,022.53
Oct 16, 2014 IDA-51900 Int Charges 9,013.53
Oct 16, 2014 IDA-51900 Int Charges 9,013.53
Oct 16, 2014 IDA-51900 Int Charges 120.20
Apr 15, 2014 IDA-51900 Int Charges 10,209.70
Oct 25, 2013 IDA-51900 Loan Disb 12,778.06
Dec 11, 2019 IDA-51900 Loan Disb 616,026.56
Mar 31, 2020 IDA-51900 Loan Disb 283,539.62
Feb 3, 2020 IDA-51900 Loan Disb 508,512.56
Dec 17, 2019 IDA-51900 Loan Disb 679,113.94
Apr 22, 2020 IDA-51900 Loan Disb 179,029.73
Apr 15, 2020 IDA-51900 Loan Repay 380,828.70
Apr 15, 2020 IDA-51900 Int Charges 58,343.41
Nov 26, 2018 IDA-51900 Loan Disb 360,098.62
Dec 10, 2018 IDA-51900 Loan Disb 331,167.03
Oct 15, 2018 IDA-51900 Int Charges 69,596.37
Oct 15, 2018 IDA-51900 Loan Repay 1,517.63
Oct 15, 2018 IDA-51900 Loan Repay 388,684.70
Oct 15, 2018 IDA-51900 Int Charges 45,200.93
Oct 15, 2018 IDA-51900 Int Charges 45,200.93
Oct 18, 2018 IDA-51900 Loan Disb 364,783.30
Mar 7, 2019 IDA-51900 Loan Disb 515,924.06
Nov 15, 2019 IDA-51900 Loan Disb 368,030.66
Sep 24, 2019 IDA-51900 Loan Disb 187,531.88
Apr 15, 2019 IDA-51900 Loan Repay 388,153.38
Dec 4, 2017 IDA-51900 Loan Disb 144,052.78
Apr 15, 2018 IDA-51900 Int Charges 1,269.04
Apr 15, 2018 IDA-51900 Loan Repay 405,993.53
Apr 15, 2018 IDA-51900 Int Charges 45,771.79
Apr 15, 2018 IDA-51900 Int Charges 45,771.79
Apr 15, 2018 IDA-51900 Int Charges 76,286.29
Jun 12, 2018 IDA-51900 Loan Disb 390,189.88
Jan 23, 2018 IDA-51900 Loan Disb 520,618.47
Sep 18, 2018 IDA-51900 Loan Disb 304,950.06
Dec 20, 2018 IDA-51900 Loan Disb 295,135.53
Jan 27, 2017 IDA-51900 Loan Disb 109,609.57
Aug 4, 2016 IDA-51900 Loan Disb 227,231.30
Dec 16, 2016 IDA-51900 Loan Disb 162,808.88
Dec 8, 2016 IDA-51900 Loan Disb 371,361.78
Feb 10, 2017 IDA-51900 Loan Disb 410,857.80
Nov 10, 2016 IDA-51900 Loan Disb 254,138.03
Oct 4, 2016 IDA-51900 Loan Disb 178,095.83
Jun 27, 2017 IDA-51900 Loan Disb 88,803.58
Jun 5, 2017 IDA-51900 Loan Disb 437,767.20
Apr 15, 2017 IDA-51900 Int Charges 33,236.19
Apr 15, 2017 IDA-51900 Int Charges 56,289.13

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Satisfactory 2021-03-01
Progress towards achievement of PDO Satisfactory 2021-03-01
Financial Management Satisfactory 2021-03-01
Monitoring and Evaluation Satisfactory 2021-03-01
Procurement Moderately Satisfactory 2021-03-01
Project Management Satisfactory 2021-03-01

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-21-2021
OutcomesHighly Satisfactory
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Time taken to disburse funds requested by Government for an eligible emergencyValue0.003.004.00
    DateNovember 30, 2012June 30, 2021
    Comment
  • Direct project beneficiariesValue0.001343780.001285000.00
    DateNovember 30, 2012June 30, 2021April 8, 2019
    Comment
  • Female beneficiariesValue0.0048.0051.00
    DateNovember 30, 2012December 31, 2017
    Comment
  • At least 85% of a representative sample of direct Project beneficiaries are satisfied with COPECO's DRM Project activities (third level on a four-level scale)Value0.0096.0085.00
    DateNovember 30, 2012June 30, 2021April 8, 2019
    Comment
  • At least 85% of sampled female beneficiaries are satisfied with COPECO's DRM Project activitiesValue0.0093.0085.00
    DateNovember 30, 2012June 30, 2021April 8, 2019
    Comment
  • At least 18 participating municipalities have adopted DRM Plans (PMGRs), and Emergency Plans (PEMs) based onthe Project's participatory methodologyValue0.0018.0018.00
    DateNovember 30, 2012June 30, 2021April 8, 2019
    Comment
  • Cities with improved livability, sustainability, and/or managementValue0.0038.008.00
    DateMarch 1, 2019June 30, 2021
    Comment
  • At least 90% of a representative sample of mitigation works is assessed independently as technically, economically and environmentally satisfactory or above.Value0.00100.0090.00
    DateNovember 30, 2012June 30, 2021April 8, 2019
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • 1.1 Standard methodology for municipal development and territorial planning developed and disseminatedValue0.001.000.00
    DateNovember 30, 2012June 30, 2021
    Comment
  • 2.1 CODEMs and CODELs established and functioning effectivelyValue0.00225.00100.00
    DateNovember 30, 2012June 30, 2021April 8, 2019
    Comment
  • 3.1 Prioritized structural mitigation measures implementedValue0.0040.0040.00
    DateNovember 30, 2012June 30, 2021April 8, 2019
    Comment
  • 4.1. Baseline for Project impact, Mid-Term Report, and Final Evaluation Report completed in a timely fashionValue0.003.001.00
    DateNovember 30, 2012June 30, 2021
    Comment
  • 5.1 CERC established and ready to provide access to financial resources to Honduras in case of an eligible emergencyValue0.001.001.00
    DateNovember 30, 2012June 30, 2021
    Comment
  • 1.2 Number of annual climate and meteorological reports / bulletins issued by the COPECO - National Center for Atmospheric, Oceanographic and Seismic Studies (CENAOS)Value0.00130.000.00
    DateMarch 1, 2019June 30, 2021
    Comment
  • 3.2 Prioritized nonstructural mitigation measures implementedValue0.0055.000.00
    DateMarch 1, 2019June 30, 2021
    Comment
  • 5.2 OSI and/or UAM prioritized for COVID-19 response supported by COPECO.Value0.0012.000.00
    DateJune 1, 2020June 30, 2021
    Comment
  • 2.1(a) Women participating actively in management positions of CODEMs and CODELsValue0.0043.0035.00
    DateNovember 30, 2012June 30, 2018
    Comment
  • 1.3 Number of hazard-monitoring stations collecting and transmitting dataValue0.0042.0042.00
    DateNovember 30, 2012June 30, 2021April 8, 2019
    Comment
  • 2.2 At least 85% of sampled technical staff from municipalities rate training received under the Project as SatisfactoryValue0.0096.0085.00
    DateNovember 30, 2012June 30, 2021April 8, 2019
    Comment
  • 3.3 Percentage of a sampled direct beneficiaries that rate structural mitigation measures implemented as satisfactory (reflect their priorities)Value0.0097.0085.00
    DateNovember 30, 2012June 30, 2021April 8, 2019
    Comment
  • 2.3 Database of risk and vulnerability analyses and municipal plans is publicly availableValue0.00100.000.00
    DateNovember 30, 2012June 30, 2021
    Comment
  • 3.3(a) Percentage of a sampled direct female beneficiaries that that rate structural mitigation measures implemented as satisfactory (reflect their priorities)Value0.0096.500.00
    DateNovember 30, 2012June 30, 2018
    Comment
  • 2.4 Number of municipalities with new and/or updated municipal planning or management tools with a risk management approachValue0.0018.000.00
    DateMarch 1, 2019June 30, 2021
    Comment
  • 2.5 Participants in consultation activities during project implementation (number)Value0.0034448.0014094.00
    DateNovember 30, 2012June 30, 2021April 8, 2019
    Comment
  • 2.5 (a) Participants in consultation activities during project implementation - femaleValue0.0014692.006423.00
    DateNovember 30, 2012June 30, 2021April 8, 2019
    Comment
  • 2.5(b) Participants in consultation activities during project implementation – indigenous / afro HonduranValue0.001929.000.00
    DateMarch 1, 2019June 30, 2021
    Comment
  • 2.6 Number of Community Early Warning Systems Strengthened / Rehabilitated through the provision of equipment by the project.Value0.0012.000.00
    DateMarch 1, 2019June 30, 2021
    Comment