PK-Sindh Barrages Improvement Project

Abstract*

The objectives of the Sindh Barrages Improvement Project for Pakistan are to improve the reliability and safety of the Guddu barrage and strengthen the Sindh Irrigation Department’s capacity to operate and manage the barrage. There are three components to the project, the first component being rehabilitation of the Guddu barrage. This component will support rehabilitation of the barrage and its associated structures. The component will finance: concrete...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The PDO is to strengthen the Sindh Irrigation Department’s capacity to operate and manage barrages and improve the reliability and safety of Guddu and Sukkur Barrages in the Province of Sindh.

Key Details

Project Details

  • P131324

  • Active

  • Francois Onimus , Thiruni Lekamwasam Liyanage

  • Islamic Republic of Pakistan

  • Pakistan

  • February 6, 2014

  • (as of board presentation)

    June 19, 2015

  • November 5, 2015

  • US$ 208.00 million

  • Irrigation Department

  • South Asia

  • 2015

  • US$ 219.53 million

  • A

  • February 1, 2024

  • June 30, 2028

  • TBD

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 219.53
Borrower/Recipient 23.70

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 219.53
IBRD + IDA Commitment 219.53
Lending Instrument
Grant Amount N/A
Total Project Cost** 208.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Sep 15, 2017 IDA-56840 Int Charges 66,302.85
Mar 15, 2018 IDA-56840 Int Charges 30,938.38
Sep 15, 2017 IDA-56840 Int Charges 171.36
Sep 15, 2017 IDA-56840 Int Charges 171.36
Mar 15, 2018 IDA-56840 Int Charges 94,508.81
Mar 15, 2018 IDA-56840 Int Charges 94,508.81
Mar 15, 2018 IDA-56840 Int Charges 153,554.40
Mar 15, 2017 IDA-56840 Int Charges 103.20
Mar 15, 2017 IDA-56840 Int Charges 52,520.98
Mar 15, 2017 IDA-56840 Int Charges 52,520.98
Mar 15, 2017 IDA-56840 Int Charges 87,534.96
Apr 12, 2016 IDA-56840 Loan Disb 2,786,081.00
Sep 15, 2016 IDA-56840 Int Charges 8,799.14
Sep 15, 2016 IDA-56840 Int Charges 8,799.14
Sep 15, 2016 IDA-56840 Int Charges 14,558.15
Sep 19, 2016 IDA-56840 Loan Disb 12,000,000.00
Mar 22, 2024 IDA-75130 Loan Commitment 71,700,000.00
May 25, 2018 IDA-62420 Loan Commitment 140,000,000.00
Jun 19, 2015 IDA-56840 Loan Commitment 188,000,000.00
Jan 15, 2024 IDA-62420 Int Charges 130,546.82
Jan 15, 2024 IDA-62420 Int Charges 197,641.78
Feb 26, 2024 IDA-62420 Loan Disb 159,461.90
Jul 1, 2024 IDA-62420 Loan Disb 73,300.28
Mar 15, 2024 IDA-56840 Loan Repay 48,558.33
Mar 15, 2024 IDA-56840 Loan Repay 1,119,837.20
Mar 15, 2024 IDA-56840 Int Charges 234,874.03
Mar 15, 2024 IDA-56840 Int Charges 234,874.03
Mar 15, 2024 IDA-56840 Int Charges 391,456.75
Jul 15, 2024 IDA-62420 Int Charges 288,670.88
Jun 20, 2024 IDA-62420 Loan Disb 163,223.55
May 13, 2024 IDA-62420 Loan Disb 168,182.47
Jun 27, 2024 IDA-62420 Loan Disb 2,079,972.00
Jun 20, 2024 IDA-62420 Loan Disb 115,096.42
May 17, 2024 IDA-62420 Loan Disb 1,456,777.00
Jul 15, 2024 IDA-62420 Loan Repay 2,108,949.80
Jul 15, 2024 IDA-62420 Int Charges 182,198.16
Jul 15, 2024 IDA-62420 Int Charges 182,198.16
Jul 15, 2024 IDA-62420 Int Charges 19,805.06
Oct 23, 2023 IDA-62420 Loan Disb 98,277.73
Jan 16, 2024 IDA-62420 Loan Disb 786,936.00
Jan 10, 2024 IDA-62420 Loan Disb 2,618,177.00
Dec 8, 2023 IDA-62420 Loan Disb 55,944.40
Dec 18, 2023 IDA-62420 Loan Disb 62,905.53
Dec 26, 2023 IDA-62420 Loan Disb 849,392.00
Oct 3, 2023 IDA-62420 Loan Disb 245,950.00
Mar 18, 2024 IDA-62420 Loan Disb 2,043,118.00
Aug 9, 2024 IDA-62420 Loan Disb 10,000,000.00
Aug 15, 2024 IDA-62420 Loan Disb 1,150,875.00
Feb 22, 2024 IDA-62420 Loan Disb 10,000,000.00
Mar 21, 2024 IDA-62420 Loan Disb 3,042.38
Jan 15, 2024 IDA-62420 Int Charges 24,721.07
Jan 15, 2024 IDA-62420 Loan Repay 2,122,916.80
Jan 15, 2024 IDA-62420 Int Charges 130,546.82
Mar 15, 2023 IDA-56840 Int Charges 405,962.38
Mar 15, 2023 IDA-56840 Loan Repay 1,148,321.90
Mar 15, 2023 IDA-56840 Loan Repay 19,787.84
Jan 15, 2022 IDA-62420 Int Charges 19,173.74
Jan 15, 2022 IDA-62420 Int Charges 31,884.94
Aug 18, 2022 IDA-62420 Loan Disb 14,672,804.00
Nov 28, 2022 IDA-62420 Loan Disb 248,998.50
Sep 28, 2022 IDA-62420 Loan Disb 75,166.08
Dec 20, 2021 IDA-62420 Loan Disb 341,701.30
Dec 22, 2021 IDA-56840 Loan Cancel 78,468,584.00
Sep 2, 2022 IDA-62420 Loan Disb 649,999.50
Jan 18, 2022 IDA-62420 Loan Disb 140,580.00
Jan 15, 2022 IDA-62420 Int Charges 309.58
Sep 23, 2022 IDA-62420 Loan Disb 127,406.43
Aug 9, 2021 IDA-62420 Loan Disb 1,300,000.00
Sep 15, 2021 IDA-56840 Loan Repay 31,620.00
Sep 15, 2021 IDA-56840 Int Charges 380,007.70
Sep 15, 2021 IDA-56840 Loan Repay 2,609,426.50
Sep 15, 2021 IDA-56840 Int Charges 245,659.80
Sep 15, 2021 IDA-56840 Int Charges 245,659.80
Mar 15, 2022 IDA-56840 Int Charges 435,556.75
Mar 15, 2022 IDA-56840 Int Charges 28,462.28
Mar 15, 2022 IDA-56840 Loan Repay 1,210,306.80
Mar 15, 2022 IDA-56840 Int Charges 261,334.05
Mar 15, 2022 IDA-56840 Int Charges 261,334.05
Apr 20, 2021 IDA-56840 Loan Disb 200,007.00
May 25, 2021 IDA-56840 Loan Cancel 30,000,000.00
Apr 15, 2021 IDA-56840 Loan Disb 10,000,000.00
Jul 15, 2021 IDA-62420 Int Charges 304.45
Jul 15, 2021 IDA-62420 Int Charges 11,598.62
Jul 15, 2021 IDA-62420 Int Charges 11,598.62
Jul 15, 2021 IDA-62420 Int Charges 19,331.02
Nov 12, 2021 IDA-56840 Loan Disb 102,635.38
Mar 15, 2021 IDA-56840 Int Charges 213,800.44
Mar 15, 2021 IDA-56840 Int Charges 213,800.44
Mar 15, 2021 IDA-56840 Int Charges 356,334.10
Mar 15, 2021 IDA-56840 Int Charges 67,872.54
Mar 15, 2021 IDA-56840 Loan Repay 3,151,298.20
Jan 15, 2021 IDA-62420 Int Charges 12,863.25
Jan 15, 2021 IDA-62420 Int Charges 471.00
Jan 15, 2021 IDA-62420 Int Charges 7,902.61
Jan 15, 2021 IDA-62420 Int Charges 7,902.61
Jul 28, 2021 IDA-56840 Loan Disb 10,000,000.00
Mar 15, 2023 IDA-56840 Int Charges 243,577.40
Mar 15, 2023 IDA-56840 Int Charges 243,577.40
Jan 15, 2023 IDA-62420 Int Charges 68,628.62
Jan 15, 2023 IDA-62420 Int Charges 68,628.62
Jan 26, 2023 IDA-62420 Loan Disb 58,430.86
Jan 15, 2023 IDA-62420 Int Charges 893.44
Jan 15, 2023 IDA-62420 Int Charges 893.44
Jan 15, 2023 IDA-62420 Int Charges 110,616.88
Sep 15, 2023 IDA-56840 Loan Repay 23,443.58
Sep 15, 2023 IDA-56840 Int Charges 394,908.97
Jul 14, 2023 IDA-56840 Loan Disb -6.49
Aug 14, 2023 IDA-62420 Loan Disb 10,000,000.00
Sep 15, 2023 IDA-56840 Int Charges 236,945.38
Sep 15, 2023 IDA-56840 Int Charges 236,945.38
Jul 14, 2023 IDA-56840 Loan Disb -1,630.50
Aug 25, 2023 IDA-62420 Loan Disb 94,990.55
Jul 15, 2023 IDA-62420 Int Charges 5,277.01
Jul 15, 2023 IDA-62420 Loan Repay 2,152,248.80
Jul 15, 2023 IDA-62420 Int Charges 95,234.93
Jul 15, 2023 IDA-62420 Int Charges 95,234.93
Jul 15, 2023 IDA-62420 Int Charges 133,662.22
Jul 14, 2023 IDA-56840 Loan Cancel 1,636.99
Sep 15, 2023 IDA-56840 Loan Repay 1,133,680.20
May 24, 2023 IDA-62420 Loan Disb 103,581.42
May 22, 2023 IDA-62420 Loan Disb 1,241,089.90
Dec 16, 2022 IDA-62420 Loan Disb 90,021.17
Sep 15, 2022 IDA-56840 Loan Repay 1,096,138.40
Sep 15, 2022 IDA-56840 Int Charges 241,191.00
Sep 15, 2022 IDA-56840 Int Charges 241,191.00
Sep 15, 2022 IDA-56840 Int Charges 401,984.94
Sep 15, 2022 IDA-56840 Loan Repay 40,093.24
Mar 29, 2023 IDA-62420 Loan Disb 5,000,000.00
Mar 31, 2023 IDA-62420 Loan Disb 102,670.85
Jul 15, 2022 IDA-62420 Int Charges 20,236.30
Jul 15, 2022 IDA-62420 Int Charges 20,236.30
Jul 15, 2022 IDA-62420 Int Charges 33,727.18
Jul 15, 2022 IDA-62420 Int Charges 546.14
Jan 15, 2022 IDA-62420 Int Charges 309.58
Jan 15, 2022 IDA-62420 Int Charges 19,173.74
Apr 14, 2021 IDA-62420 Loan Disb 2,000,000.00
Oct 8, 2020 IDA-56840 Loan Disb 5,000,000.00
Sep 15, 2020 IDA-56840 Loan Repay 3,124,062.80
Sep 15, 2020 IDA-56840 Int Charges 189,739.34
Sep 15, 2020 IDA-56840 Int Charges 189,739.34
Sep 15, 2020 IDA-56840 Loan Repay 1,115.87
Sep 15, 2020 IDA-56840 Int Charges 248,922.23
Jul 15, 2020 IDA-62420 Int Charges 12,259.05
Jul 15, 2020 IDA-62420 Int Charges 55.73
Jul 15, 2020 IDA-62420 Int Charges 7,628.18
Jul 15, 2020 IDA-62420 Int Charges 7,628.18
Jul 13, 2020 IDA-56840 Loan Disb 7,000,000.00
Sep 15, 2019 IDA-56840 Int Charges 702.12
Sep 15, 2019 IDA-56840 Int Charges 702.12
Jan 15, 2020 IDA-62420 Int Charges 4,126.48
Jan 15, 2020 IDA-62420 Int Charges 4,126.48
Jan 15, 2020 IDA-62420 Int Charges 6,822.12
Sep 15, 2019 IDA-56840 Int Charges 229,000.44
Oct 7, 2019 IDA-62420 Loan Disb 2,000,000.00
Sep 15, 2019 IDA-56840 Int Charges 136,698.12
Sep 15, 2019 IDA-56840 Int Charges 136,698.12
Sep 19, 2019 IDA-56840 Loan Disb 10,000,000.00
Mar 15, 2020 IDA-56840 Int Charges 3,087.22
Mar 15, 2020 IDA-56840 Int Charges 3,087.22
Mar 15, 2020 IDA-56840 Int Charges 171,667.02
Mar 15, 2020 IDA-56840 Int Charges 171,667.02
Mar 15, 2020 IDA-56840 Int Charges 291,257.03
Mar 15, 2019 IDA-56840 Int Charges 131.83
Mar 15, 2019 IDA-56840 Int Charges 123,802.87
Mar 15, 2019 IDA-56840 Int Charges 123,802.87
Mar 15, 2019 IDA-56840 Int Charges 206,338.16
Jun 12, 2018 IDA-56840 Loan Disb 3,000,000.00
Sep 15, 2018 IDA-56840 Int Charges 3,822.43
Sep 15, 2018 IDA-56840 Int Charges 96,959.31
Sep 15, 2018 IDA-56840 Int Charges 96,959.31
Sep 15, 2018 IDA-56840 Int Charges 161,466.06
Nov 29, 2018 IDA-56840 Loan Disb 10,000,000.00
Sep 15, 2017 IDA-56840 Int Charges 80,479.56
Jul 25, 2017 IDA-56840 Loan Disb 9,500,000.00
Sep 15, 2017 IDA-56840 Int Charges 66,302.85

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2025-01-01
Project Management Satisfactory 2025-01-01
Financial Management Satisfactory 2025-01-01
Overall Implementation Progress (IP) Satisfactory 2025-01-01
Procurement Moderately Satisfactory 2025-01-01
Monitoring and Evaluation Moderately Satisfactory 2025-01-01

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Annual pond level deviation from targeted normal pond levelValue0.540.950.10
    DateDecember 31, 2020October 31, 2023June 30, 2024
    Comment
  • Increased design flood passage capacity for Sukkur Barrage (cusec)Value900000.00900000.001300000.00
    DateFebruary 1, 2018October 31, 2023June 30, 2024
    Comment
  • Progress in implementing improved O&M plans at three barragesValue0.000.00100.00
    DateApril 20, 2015October 31, 2023June 30, 2024
    Comment
  • Increased design flood passage capacity for Guddu Barrage (cusec)Value900000.00930769.001100000.00
    DateApril 20, 2015October 31, 2023June 30, 2024
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Percentage of planned rehabilitation and modernization works for Guddu and Sukkur Barrages completedValue0.0037.97100.00
    DateNovember 22, 2017October 31, 2023June 30, 2024
    Comment
  • Barrage Management Unit established and functionalValueNoYesYes
    DateJune 30, 2015October 31, 2023June 30, 2024
    Comment
  • Grievances registered related to delivery of project benefits addressed (%)Value0.00100.0090.00
    DateMarch 26, 2015October 31, 2023June 30, 2024
    Comment
  • Number of person-days of training delivered on Barrages O&MValue0.00206.001000.00
    DateJune 30, 2015October 31, 2023June 30, 2024
    Comment
  • Number of studies completedValue0.000.003.00
    DateJune 30, 2015October 31, 2023June 30, 2024
    Comment
  • Number of community stakeholders participating in water management and other project-related consultationsValue0.00455.00800.00
    DateNovember 16, 2017October 31, 2023June 30, 2024
    Comment
  • Number of gates replacedValue0.0035.00201.00
    DateJune 30, 2015October 31, 2023June 30, 2024
    Comment
  • Number of canal head regulators calibratedValue0.000.0014.00
    DateJune 30, 2015October 31, 2023June 30, 2024
    Comment
  • % of which femaleValue0.000.0030.00
    DateNovember 16, 2017March 31, 2018June 30, 2024
    Comment
  • Share of annual maintenance budget outsourced to maintenance contractorsValue0.0035.0030.00
    DateJune 30, 2015October 31, 2023June 30, 2024
    Comment
  • Emergency Preparedness Plan finalizedValue0.000.003.00
    DateApril 20, 2015October 31, 2023June 30, 2024
    Comment
  • Ratio of dolphin rescues over dolphin stranded in canalsValue0.00100.0090.00
    DateJune 30, 2015October 31, 2023June 30, 2024
    Comment