Enhancing Education Development Project

Abstract*

The development objective of the Enhancing Education Development Project (EEDP) for Maldives is to enhance and strengthen strategic dimensions of education access and quality. The project has three components. The first component is national level education development. The objective of this component is to promote strategic initiatives at the country level to strengthen and develop the education system. The following key sub-components will be supported...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objective is to enhance and strengthen strategic dimensions of education access and quality.

Key Details

Project Details

  • P131331

  • Closed

  • Harsha Aturupane , Mari Shojo

  • Ministry of Finance and Treasury

  • Maldives

  • October 18, 2012

  • (as of board presentation)

    April 30, 2013

  • July 26, 2013

  • US$ 11.00 million

  • Ministry of Education

  • South Asia

  • 2013

  • US$ 10.00 million

  • B

  • Not Applicable

  • June 30, 2018

  • Yes

  • BANK APPROVED

  • September 6, 2022

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 1.00
IDA Grant 10.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 10.00
IBRD + IDA Commitment 10.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 11.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jan 20, 2015 IDA-H8410 Loan Disb 163,747.02
May 22, 2014 IDA-H8410 Loan Disb 314,389.12
Nov 15, 2018 IDA-H8410 Loan Disb -0.01
Apr 30, 2013 IDA-H8410 Loan Commitment 10,000,000.00
May 26, 2015 IDA-H8410 Loan Disb 273,302.88
Nov 15, 2018 IDA-H8410 Loan Disb -870.52
Aug 7, 2018 IDA-H8410 Loan Disb 118,412.88
Nov 15, 2018 IDA-H8410 Loan Cancel 430,596.97
Mar 22, 2017 IDA-H8410 Loan Disb 642,171.75
Aug 28, 2017 IDA-H8410 Loan Disb 863,564.44
Feb 16, 2018 IDA-H8410 Loan Disb 1,718,851.10
Dec 18, 2017 IDA-H8410 Loan Disb 296,685.40
Feb 7, 2017 IDA-H8410 Loan Disb 568,990.44
Oct 17, 2016 IDA-H8410 Loan Disb 138,137.36
May 25, 2017 IDA-H8410 Loan Disb 267,392.40
Jun 13, 2016 IDA-H8410 Loan Disb 264,936.60
Jan 4, 2016 IDA-H8410 Loan Disb 112,139.20
Sep 10, 2015 IDA-H8410 Loan Disb 184,785.80
Feb 23, 2016 IDA-H8410 Loan Disb 1,555,321.50
Sep 26, 2013 IDA-H8410 Loan Disb 500,000.00
Mar 4, 2014 IDA-H8410 Loan Disb 1,177,171.20

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Satisfactory 2018-05-17
Progress towards achievement of PDO Satisfactory 2018-05-17
Project Management Satisfactory 2018-05-17
Financial Management Satisfactory 2018-05-17
Monitoring and Evaluation Satisfactory 2018-05-17
Counterpart Funding Satisfactory 2018-05-17
Overall Implementation Progress (IP) Satisfactory 2018-05-17

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-24-2018
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 04-12-2019PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Increased survival rates through higher secondary education(grades 1-12)Value17.0027.0032.00
    DateMarch 1, 2013June 30, 2018June 30, 2018
    Comment
  • Proportion of atolls in which a system of quality assurance self-evaluations are established and findings incorporated in the implementation of school improvement plansValue0.0080.00100.00
    DateMarch 1, 2013June 30, 2018June 30, 2018
    Comment
  • Direct project beneficiariesValue0.0050000.0066600.00
    DateMarch 1, 2013June 30, 2018June 30, 2018
    Comment
  • System for learning assessment at the primary levelValueNoYesYes
    DateMarch 1, 2013June 30, 2018June 30, 2018
    Comment
  • Female beneficiariesValue0.0048.0049.00
    DateMarch 1, 2013June 30, 2018June 30, 2018
    Comment
  • Utility of the learning assessment systemValue1.004.004.00
    DateMarch 1, 2013June 30, 2018June 30, 2018
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of targeted education sector staff progressively completing short courses, diplomas degrees, and postgraduate degreesValue0.00100.00132.00
    DateMarch 1, 2013June 30, 2018June 30, 2018
    Comment
  • Physical Learning Environment Improved in Schools (number)Value0.0045.0057.00
    DateMarch 1, 2013June 30, 2018June 30, 2018
    Comment
  • Proportion of atolls implementing School-Professional Development Programs (SBPD) informed by and related to QA reviewsValue0.0080.00100.00
    DateFebruary 1, 2013June 30, 2018June 30, 2018
    Comment