Burkina Faso Public Sector Modernization Program

Abstract*

The objective of the Public Sector Modernization Program Project for Burkina Faso is to improve selected service standards in targeted regions of the ministries responsible for primary education, justice, labor and civil service. The project has five pillars. (1) Improving the efficiency and the quality of public service delivery pillar is to enhance public administration performance for sustainable development and streamline the decision-making processes...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The program development objective is to improve selected service standards in targeted regions of the ministries responsible for primary education, justice, labor and civil service.

Key Details

Project Details

  • P132216

  • Closed

  • Kolie Megnan , Sandrine Egoue Ngasseu

  • Ministry of Economy, Finance and Development

  • Burkina Faso

  • April 8, 2015

  • (as of board presentation)

    July 9, 2015

  • February 1, 2016

  • US$ 50.00 million

  • Ministère de la Fonction Publique du Travail et de la Sécurité Sociale

  • Western and Central Africa

  • 2016

  • US$ 40.00 million

  • N/A

  • Not Applicable

  • December 31, 2020

  • TBD

  • BANK APPROVED

  • June 25, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 5.35
IDA Grant 40.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 40.00
IBRD + IDA Commitment 40.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 50.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Aug 1, 2022 IDA-56830 Int Charges 23.90
Aug 1, 2022 IDA-56830 Int Charges 133,320.14
Apr 29, 2020 IDA-56830 Loan Disb 1,163,225.00
Feb 4, 2020 IDA-56830 Int Charges 116,676.83
Feb 4, 2020 IDA-56830 Int Charges 116,676.83
Dec 14, 2020 IDA-56830 Loan Disb 1,464,906.80
Aug 1, 2020 IDA-56830 Int Charges 59.25
Aug 1, 2020 IDA-56830 Int Charges 59.25
Aug 1, 2020 IDA-56830 Int Charges 127,578.16
Aug 1, 2020 IDA-56830 Int Charges 127,578.16
Sep 21, 2020 IDA-56830 Loan Disb 6,319,547.00
Aug 1, 2019 IDA-56830 Int Charges 116,515.61
Aug 1, 2019 IDA-56830 Int Charges 116,515.61
Feb 2, 2018 IDA-56830 Int Charges 64,588.88
Feb 2, 2018 IDA-56830 Int Charges 64,588.88
Aug 1, 2018 IDA-56830 Int Charges 89,122.27
Aug 1, 2018 IDA-56830 Int Charges 89,122.27
May 9, 2018 IDA-56830 Loan Disb 17,066,282.00
Feb 4, 2019 IDA-56830 Int Charges 120,935.04
Feb 4, 2019 IDA-56830 Int Charges 120,935.04
Aug 1, 2017 IDA-56830 Int Charges 58,827.19
Aug 1, 2017 IDA-56830 Int Charges 58,827.19
May 27, 2016 IDA-56830 Loan Disb 6,815,689.50
Jun 28, 2016 IDA-56830 Loan Disb 1,362,177.00
Jun 29, 2016 IDA-56830 Loan Disb 405,666.10
Aug 24, 2016 IDA-56830 Int Charges 9,171.32
Aug 24, 2016 IDA-56830 Int Charges 9,171.32
Feb 16, 2017 IDA-56830 Loan Disb 103,410.37
Feb 7, 2017 IDA-56830 Int Charges 1,161.52
Feb 7, 2017 IDA-56830 Int Charges 1,161.52
Feb 7, 2017 IDA-56830 Int Charges 30,782.77
Feb 7, 2017 IDA-56830 Int Charges 30,782.77
Feb 16, 2017 IDA-56830 Loan Disb 6,380,700.00
Feb 9, 2024 IDA-56830 Loan Repay 602,504.94
Feb 9, 2024 IDA-56830 Int Charges 133,304.23
Feb 9, 2024 IDA-56830 Int Charges 133,304.23
Feb 1, 2024 IDA-56830 Int Charges -17.24
Feb 1, 2024 IDA-56830 Int Charges 17.24
Aug 1, 2024 IDA-56830 Loan Repay 131,309.60
Jul 9, 2015 IDA-56830 Loan Commitment 40,000,000.00
Aug 22, 2024 IDA-56830 Int Charges 102,199.60
Aug 22, 2024 IDA-56830 Int Charges 102,199.60
Aug 19, 2024 IDA-56830 Loan Repay 482,977.97
Aug 19, 2024 IDA-56830 Int Charges 102.90
Aug 19, 2024 IDA-56830 Int Charges 102.90
Aug 19, 2024 IDA-56830 Int Charges 33,070.14
Aug 19, 2024 IDA-56830 Int Charges 33,070.14
Feb 3, 2022 IDA-56830 Int Charges 149,075.10
Feb 3, 2022 IDA-56830 Int Charges 149,075.10
Feb 3, 2022 IDA-56830 Loan Repay 631,030.94
Apr 30, 2021 IDA-56830 Loan Cancel 1,709.55
Aug 1, 2023 IDA-56830 Loan Repay 476,088.75
Aug 1, 2023 IDA-56830 Int Charges 25.60
Aug 1, 2023 IDA-56830 Int Charges 25.60
Aug 1, 2023 IDA-56830 Int Charges 138,219.23
Aug 1, 2023 IDA-56830 Int Charges 138,219.23
Aug 1, 2023 IDA-56830 Loan Repay 138,244.84
Feb 3, 2023 IDA-56830 Loan Repay 611,368.94
Feb 6, 2023 IDA-56830 Int Charges 137,759.23
Feb 6, 2023 IDA-56830 Int Charges 137,759.23
Feb 1, 2021 IDA-56830 Int Charges 149,987.20
Feb 1, 2021 IDA-56830 Int Charges 149,987.20
Aug 1, 2021 IDA-56830 Int Charges 159,778.06
Aug 1, 2021 IDA-56830 Int Charges 1,404.50
Aug 1, 2021 IDA-56830 Int Charges 1,404.50
Aug 1, 2021 IDA-56830 Loan Repay 159,778.06
Aug 1, 2021 IDA-56830 Loan Repay 505,990.06
Aug 1, 2021 IDA-56830 Int Charges 159,778.06
Aug 1, 2022 IDA-56830 Int Charges 133,320.14
Aug 1, 2022 IDA-56830 Loan Repay 440,099.25
Aug 1, 2022 IDA-56830 Loan Repay 133,344.05
Aug 1, 2022 IDA-56830 Int Charges 23.90

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Monitoring and Evaluation Satisfactory 2020-12-22
Overall Implementation Progress (IP) Satisfactory 2020-12-22
Progress towards achievement of PDO Satisfactory 2020-12-22

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-28-2021
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • PDO Indicator 1: Share of HR transactions completed in the civil service within a certain period: hiring and promotion within 28 calendar days (disaggregated by recruitment and promotion)Value4.6050.0050.00
    DateOctober 12, 2015December 31, 2020March 31, 2020
    Comment
  • Recruitment/HiringValue4.3850.000.00
    DateOctober 12, 2015December 31, 2020
    Comment
  • PDO Indicator 2: Workers registered with the Social Security Fund (Caisse Nationale de Securité Sociale - CNSS)Value298000.00400000.000.00
    DateOctober 12, 2015December 31, 2020
    Comment
  • PDO Indicator 3: Share of classes with at least 700 annual hours of instruction in public primary schools in the Sahel, Upper Basinand East regionsValue0.0080.000.00
    DateOctober 12, 2015December 31, 2020
    Comment
  • PDO Indicator 4: Share of judgments issued by administrative tribunals in a 12 month period (75% of which through a written judgment) in Ouagadougou, Tenkodogo, Dedougou and Bobo-DioulassoValue29.0060.000.00
    DateOctober 12, 2015December 31, 2020
    Comment
  • PDO Indicator 4: Share of judgments that are delivered in Ouagadougou, Tenkodogo, Dédougou and Bobo-Dioulasso regions with respect to contentious matters by the 50-pilot departmentsValue0.0070.000.00
    DateOctober 12, 2015December 31, 2020
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Beneficiaries of job-focused interventionsValue138000.00207483.000.00
    DateDecember 30, 2016December 31, 2019
    Comment
  • IR Indicator 1.1: SIGASPE updated to meet user needsValueNoYes
    DateOctober 12, 2015December 31, 2020
    Comment
  • IR Indicator 2.1: Share of DRT satisfying defined criteria in the Centre, Centre-West, Cascades and Upper Basin regionsValue0.00100.000.00
    DateOctober 12, 2015December 31, 2020
    Comment
  • IR Indicator 3.1: Rate of execution of the PSDMA Second Action Plan.Value0.0060.000.00
    DateOctober 12, 2015December 31, 2020
    Comment
  • IR Indicator 1.2: Share of newly hired primary teachers made available to MENA by 31 AugustValue0.0090.000.00
    DateOctober 12, 2015December 31, 2020
    Comment
  • Beneficiaries of job-focused interventions - FemaleValue138000.0066600.000.00
    DateDecember 30, 2016March 26, 2020
    Comment
  • IR Indicator 2.2: Monitoring mechanism of instructional time in public primary schools established in the Sahel, Upper Basin and East regionsValueNoYes
    DateOctober 12, 2015December 31, 2020
    Comment
  • IR Indicator 3.2: Publication of annual performance reports in conformity with WAEMU Directive 7ValueNoYes
    DateOctober 12, 2015December 31, 2020
    Comment
  • IR Indicator 1.3: Share of DRFP offices satisfying defined criteriaValue0.0080.000.00
    DateOctober 12, 2015December 31, 2020
    Comment
  • IR Indicator 2.3: Share of CEB, DPENA and DRENA satisfying defined criteria in the regions Sahel, Upper Basin and EastValue60.0090.000.00
    DateOctober 12, 2015December 31, 2020
    Comment
  • IR Indicator 3.3: Rate of execution of the risk-based audit of the ASCE in MENA, MFPTSS and MJPDHCValue0.0065.000.00
    DateOctober 12, 2015December 31, 2020
    Comment
  • IR Indicator 1.4: Share of civil servants in selected ministries with an updated employment record in SIGASPEValue0.0075.000.00
    DateOctober 12, 2015December 31, 2020
    Comment
  • IR Indicator 3.4: Rate of execution of the internal ministerial technical inspectorates’ recommendations in the MENA, MFPTSS and MJPDHCValue20.0060.000.00
    DateOctober 12, 2015December 31, 2020
    Comment
  • IR Indicator 2.4: Share of new teachers assigned to schools in the Sahel, Upper Basin and East regions on or before 25 SeptemberValue0.0080.000.00
    DateOctober 12, 2015December 31, 2020
    Comment
  • IR Indicator 2.5: Share of public primary schools having at least two visits per academic year by circuit supervisor (CCEB) in the Sahel, Upper Basin and East regionsValue25.0080.000.00
    DateOctober 12, 2015December 31, 2020
    Comment
  • IR Indicator 3.5: Grievances responded by the Ombudsman in compliance with the Operational Manual of the ProgramValue0.0070.000.00
    DateOctober 12, 2015December 31, 2020
    Comment
  • IR Indicator 1.5: Share of civil servants in the civil service on-line access to administrative and personnel HR informationValue0.00100.000.00
    DateOctober 12, 2015December 31, 2020
    Comment
  • IR Indicator 2.6: Share of written judgments handed down in the pilot jurisdictions in Ouagadougou, Tenkodogo, Dédougou and Bobo-Dioulasso regions for which the case management process is automatedValue0.0080.000.00
    DateOctober 12, 2015December 31, 2020
    Comment
  • IR Indicator 3.6: Direct project beneficiaries (of which female)Value138000.00180000.000.00
    DateOctober 12, 2015December 31, 2020
    Comment
  • IR Indicator 1.6: Share of civil servants in the selected ministries with Individual Employee File system (Dossier Individuel Normalisé --DIN) updated and available on-lineValue0.0070.000.00
    DateOctober 12, 2015December 31, 2020
    Comment
  • IR Indicator 2.7: Share of pilot jurisdictions in Ouagadougou, Tenkodogo, Dédougou and Bobo-Dioulasso regions that satisfy 80 percent of the defined criteria (TGI/Tadmin)Value0.00100.000.00
    DateOctober 12, 2015December 31, 2020
    Comment
  • IR Indicator 1.7: Share of civil servants in the three selected ministries with job description, performance contracts and annual performance evaluation.Value0.0070.000.00
    DateOctober 12, 2015December 31, 2020
    Comment
  • IR Indicator 2.8: Share of 115 most frequently used laws and jurisprudence publicly accessible onlineValue0.00100.000.00
    DateOctober 12, 2015December 31, 2020
    Comment
  • IR Indicator 1.8: Share of transactions in the civil service carried out within a certain period: retirement completed two (60 calendar days) months before the retirement dateValue12.0060.000.00
    DateOctober 12, 2015December 31, 2020
    Comment
  • IR Indicator 2.9: Share of 50-pilot local departmental and district courts in in the Ouagadougou, Tenkodogo, Dédougou and Bobo-Dioulasso regions that satisfy 80 percent of the defined criteriaValue0.00100.000.00
    DateOctober 12, 2015December 31, 2020
    Comment
  • IR Indicator 2.10: Share of 50-pilot local departmental and district courts in the Ouagadougou, Tenkodogo, Dédougou and Bobo-Dioulasso regions that have presidents, secretaries and assessors trainedValue0.00100.000.00
    DateOctober 12, 2015December 31, 2020
    Comment
  • IR Indicator 2.11: Uniform case tracking system established in the selected 50 local departmental and district courtsValueNoYes
    DateOctober 12, 2015December 31, 2020
    Comment
  • IR Indicator 2.12: Share of female teachers hired each yearValue40.0050.000.00
    DateOctober 12, 2015December 31, 2020
    Comment