Metro Manila BRT Line 1 Project

Abstract*

The objective of Metro Manila Bus Rapid Transit (BRT) First Line Project for Philippines is to improve the efficiency, effectiveness and safety of the public transport system along the project corridor in Metro Manila in an environmentally sustainable manner. The project has six components. (1) BRT infrastructure component finances the development of BRT infrastructure along the project corridor, including, among others, construction of bus terminals...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective (PDO) is to improve the efficiency, effectiveness and safety of the public transport system alongthe Project Corridor in Metro Manila in an environmentally sustainable manner.

Key Details

Project Details

  • P132401

  • Closed

  • Fang Xu

  • Republic of the Philippines

  • Philippines

  • February 16, 2017

  • (as of board presentation)

    March 16, 2017

  • March 15, 2019

  • US$ 109.41 million

  • Department of Transportation

  • East Asia and Pacific

  • 2017

  • US$ 64.60 million

  • A

  • December 21, 2022

  • June 21, 2022

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 40.70
Clean Technology Fund 23.90
Borrower/Recipient 44.81

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 40.70
IDA Commitment N/A
IBRD + IDA Commitment 40.70
Lending Instrument
Grant Amount 23.90
Total Project Cost** 109.41

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 15, 2022 IBRD-87280 Int Charges 552.52
Mar 15, 2024 IBRD-87280 Int Charges 3,400.75
Sep 15, 2022 IBRD-87280 Int Charges 1,059.58
Sep 15, 2021 IBRD-87280 Int Charges 51,164.92
Sep 15, 2022 IBRD-87280 Int Charges 27,250.89
Sep 15, 2021 IBRD-87280 Int Charges 577.26
Mar 15, 2023 IBRD-87280 Int Charges 2,669.45
Sep 15, 2020 IBRD-87280 Int Charges 842.48
Sep 15, 2020 IBRD-87280 Int Charges 51,025.12
Mar 15, 2021 IBRD-87280 Int Charges 603.65
Mar 15, 2021 IBRD-87280 Int Charges 50,248.64
Mar 15, 2023 IBRD-87280 Int Charges 115.41
Mar 15, 2024 IBRD-87280 Int Charges 52.21
Mar 16, 2017 TF-A2129 Loan Commitment 23,900,000.00
Mar 16, 2017 IBRD-87280 Loan Commitment 40,700,000.00
Sep 15, 2023 IBRD-87280 Int Charges 3,073.69
Sep 15, 2023 IBRD-87280 Int Charges 38.86
Sep 15, 2019 IBRD-87280 Int Charges 1,861.78
Mar 15, 2020 IBRD-87280 Int Charges 1,512.34
Mar 15, 2020 IBRD-87280 Int Charges 50,552.57
Sep 15, 2019 IBRD-87280 Int Charges 42,544.74
Mar 15, 2019 IBRD-87280 Loan Disb 101,750.00
Mar 15, 2019 IBRD-87280 Fee Charges 101,750.00
Jun 21, 2022 IBRD-87280 Loan Cancel 40,598,248.00
Mar 15, 2022 IBRD-87280 Int Charges 50,330.71

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Unsatisfactory 2022-04-12
Procurement Moderately Unsatisfactory 2022-04-12
Overall Implementation Progress (IP) Unsatisfactory 2022-04-12
Financial Management Moderately Unsatisfactory 2022-04-12
Counterpart Funding Moderately Unsatisfactory 2022-04-12
Monitoring and Evaluation Moderately Satisfactory 2022-04-12
Project Management Unsatisfactory 2022-04-12

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Direct project beneficiariesValue0.000.00300000.00
    DateMay 4, 2015March 29, 2022June 30, 2022
    Comment
  • Female beneficiariesValue0.000.0050.00
    DateMay 4, 2015December 6, 2017June 30, 2022
    Comment
  • Average travel time for public transport users during AM peak from Manila City Hall to Quezon Memorial Circle StationValue90.00120.0043.00
    DateMay 4, 2015March 29, 2022June 30, 2022
    Comment
  • Beneficiaries satisfied with BRT servicesValue0.000.0070.00
    DateMay 4, 2015March 29, 2022June 30, 2022
    Comment
  • Of which are femaleValue0.000.0050.00
    DateMay 4, 2015March 29, 2022June 30, 2022
    Comment
  • Annual GHG emissions savings of transport along the project corridor (CO2e emissions per tons per year)Value0.000.008779.00
    DateMay 4, 2015March 29, 2022June 30, 2022
    Comment
  • Public and non-motorized transport user accidents along the project corridor (per vehicle km)Value3.403.400.20
    DateMay 4, 2015March 29, 2022June 30, 2022
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • BRT bus lane constructed along the project corridorValue0.000.0011.50
    DateMay 4, 2015March 29, 2022June 30, 2022
    Comment
  • New BRT line FS completedValueNoNoYes
    DateMay 5, 2015March 29, 2022June 30, 2022
    Comment
  • Specially designed high quality buses procuredValue0.000.00167.00
    DateMay 4, 2015March 29, 2022June 30, 2022
    Comment
  • Number of quarterly reports submitted on-timeValue0.000.0020.00
    DateMay 4, 2015March 29, 2022June 30, 2022
    Comment
  • Pedestrian access facilities improved or upgraded under the projectValue0.000.003200.00
    DateMay 4, 2015March 29, 2022June 30, 2022
    Comment
  • Junctions with improved traffic engineering under the projectValue0.000.0016.00
    DateMay 4, 2015March 29, 2022June 30, 2022
    Comment
  • Government staff and other transport stakeholders participated in BRT and other urban transport training supported by the projectValue0.000.00150.00
    DateMay 4, 2015March 29, 2022June 30, 2022
    Comment
  • Bus routes provided under performance-based contractValue0.000.001.00
    DateMay 4, 2015March 29, 2022November 30, 2021
    Comment
  • Annual surveys conductedValue0.000.004.00
    DateMay 4, 2015March 29, 2022June 30, 2022
    Comment
  • Functional BRT Operation Control Center in placeValueNoneNoneBRT Operational Control Center functioning.
    DateMay 4, 2015March 29, 2022June 30, 2022
    Comment
  • NPMO and PIU staff trained under the projectValue0.0010.0050.00
    DateMay 4, 2015March 29, 2022June 30, 2022
    Comment
  • Transport database developed and regularly updatedValueNoneNoneTransport database maintained and updated regularl
    DateMay 4, 2015March 29, 2022June 30, 2022
    Comment
  • BRT bus depots constructedValue0.000.002.00
    DateMay 4, 2015March 29, 2022June 30, 2022
    Comment