Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 40.70 |
Clean Technology Fund | 23.90 |
Borrower/Recipient | 44.81 |
P132401
Closed
Fang Xu
Republic of the Philippines
February 16, 2017
(as of board presentation)
March 16, 2017
March 15, 2019
US$ 109.41 million
Department of Transportation
2017
US$ 64.60 million
A
December 21, 2022
June 21, 2022
Yes
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 40.70 |
Clean Technology Fund | 23.90 |
Borrower/Recipient | 44.81 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 40.70 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 40.70 |
Lending Instrument | |
---|---|
Grant Amount | 23.90 |
Total Project Cost** | 109.41 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 15, 2022 | IBRD-87280 | Int Charges | 552.52 |
Mar 15, 2024 | IBRD-87280 | Int Charges | 3,400.75 |
Sep 15, 2022 | IBRD-87280 | Int Charges | 1,059.58 |
Sep 15, 2021 | IBRD-87280 | Int Charges | 51,164.92 |
Sep 15, 2022 | IBRD-87280 | Int Charges | 27,250.89 |
Sep 15, 2021 | IBRD-87280 | Int Charges | 577.26 |
Mar 15, 2023 | IBRD-87280 | Int Charges | 2,669.45 |
Sep 15, 2020 | IBRD-87280 | Int Charges | 842.48 |
Sep 15, 2020 | IBRD-87280 | Int Charges | 51,025.12 |
Mar 15, 2021 | IBRD-87280 | Int Charges | 603.65 |
Mar 15, 2021 | IBRD-87280 | Int Charges | 50,248.64 |
Mar 15, 2023 | IBRD-87280 | Int Charges | 115.41 |
Mar 15, 2024 | IBRD-87280 | Int Charges | 52.21 |
Mar 16, 2017 | TF-A2129 | Loan Commitment | 23,900,000.00 |
Mar 16, 2017 | IBRD-87280 | Loan Commitment | 40,700,000.00 |
Sep 15, 2023 | IBRD-87280 | Int Charges | 3,073.69 |
Sep 15, 2023 | IBRD-87280 | Int Charges | 38.86 |
Sep 15, 2019 | IBRD-87280 | Int Charges | 1,861.78 |
Mar 15, 2020 | IBRD-87280 | Int Charges | 1,512.34 |
Mar 15, 2020 | IBRD-87280 | Int Charges | 50,552.57 |
Sep 15, 2019 | IBRD-87280 | Int Charges | 42,544.74 |
Mar 15, 2019 | IBRD-87280 | Loan Disb | 101,750.00 |
Mar 15, 2019 | IBRD-87280 | Fee Charges | 101,750.00 |
Jun 21, 2022 | IBRD-87280 | Loan Cancel | 40,598,248.00 |
Mar 15, 2022 | IBRD-87280 | Int Charges | 50,330.71 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Unsatisfactory | 2022-04-12 |
Procurement | Moderately Unsatisfactory | 2022-04-12 |
Overall Implementation Progress (IP) | Unsatisfactory | 2022-04-12 |
Financial Management | Moderately Unsatisfactory | 2022-04-12 |
Counterpart Funding | Moderately Unsatisfactory | 2022-04-12 |
Monitoring and Evaluation | Moderately Satisfactory | 2022-04-12 |
Project Management | Unsatisfactory | 2022-04-12 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Direct project beneficiaries | Value | 0.00 | 0.00 | 300000.00 |
Date | May 4, 2015 | March 29, 2022 | June 30, 2022 | |
Comment |
Female beneficiaries | Value | 0.00 | 0.00 | 50.00 |
Date | May 4, 2015 | December 6, 2017 | June 30, 2022 | |
Comment |
Average travel time for public transport users during AM peak from Manila City Hall to Quezon Memorial Circle Station | Value | 90.00 | 120.00 | 43.00 |
Date | May 4, 2015 | March 29, 2022 | June 30, 2022 | |
Comment |
Beneficiaries satisfied with BRT services | Value | 0.00 | 0.00 | 70.00 |
Date | May 4, 2015 | March 29, 2022 | June 30, 2022 | |
Comment |
Of which are female | Value | 0.00 | 0.00 | 50.00 |
Date | May 4, 2015 | March 29, 2022 | June 30, 2022 | |
Comment |
Annual GHG emissions savings of transport along the project corridor (CO2e emissions per tons per year) | Value | 0.00 | 0.00 | 8779.00 |
Date | May 4, 2015 | March 29, 2022 | June 30, 2022 | |
Comment |
Public and non-motorized transport user accidents along the project corridor (per vehicle km) | Value | 3.40 | 3.40 | 0.20 |
Date | May 4, 2015 | March 29, 2022 | June 30, 2022 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
BRT bus lane constructed along the project corridor | Value | 0.00 | 0.00 | 11.50 |
Date | May 4, 2015 | March 29, 2022 | June 30, 2022 | |
Comment |
New BRT line FS completed | Value | No | No | Yes |
Date | May 5, 2015 | March 29, 2022 | June 30, 2022 | |
Comment |
Specially designed high quality buses procured | Value | 0.00 | 0.00 | 167.00 |
Date | May 4, 2015 | March 29, 2022 | June 30, 2022 | |
Comment |
Number of quarterly reports submitted on-time | Value | 0.00 | 0.00 | 20.00 |
Date | May 4, 2015 | March 29, 2022 | June 30, 2022 | |
Comment |
Pedestrian access facilities improved or upgraded under the project | Value | 0.00 | 0.00 | 3200.00 |
Date | May 4, 2015 | March 29, 2022 | June 30, 2022 | |
Comment |
Junctions with improved traffic engineering under the project | Value | 0.00 | 0.00 | 16.00 |
Date | May 4, 2015 | March 29, 2022 | June 30, 2022 | |
Comment |
Government staff and other transport stakeholders participated in BRT and other urban transport training supported by the project | Value | 0.00 | 0.00 | 150.00 |
Date | May 4, 2015 | March 29, 2022 | June 30, 2022 | |
Comment |
Bus routes provided under performance-based contract | Value | 0.00 | 0.00 | 1.00 |
Date | May 4, 2015 | March 29, 2022 | November 30, 2021 | |
Comment |
Annual surveys conducted | Value | 0.00 | 0.00 | 4.00 |
Date | May 4, 2015 | March 29, 2022 | June 30, 2022 | |
Comment |
Functional BRT Operation Control Center in place | Value | None | None | BRT Operational Control Center functioning. |
Date | May 4, 2015 | March 29, 2022 | June 30, 2022 | |
Comment |
NPMO and PIU staff trained under the project | Value | 0.00 | 10.00 | 50.00 |
Date | May 4, 2015 | March 29, 2022 | June 30, 2022 | |
Comment |
Transport database developed and regularly updated | Value | None | None | Transport database maintained and updated regularl |
Date | May 4, 2015 | March 29, 2022 | June 30, 2022 | |
Comment |
BRT bus depots constructed | Value | 0.00 | 0.00 | 2.00 |
Date | May 4, 2015 | March 29, 2022 | June 30, 2022 | |
Comment |