Neeranchal National Watershed Project

Abstract*

The development objective of the Neeranchal National Watershed Project for India is to support integrated watershed management program (IWMP) through technical assistance to improve incremental conservation outcomes and agricultural yields for communities in selected sites, and adoption of more effective processes and technologies into the broader IWMP in participating states. The project comprises of four components. The first component, central...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective (PDO) is to support the watershed development component of PMKSY through technical assistance to improve incremental conservation outcomes and agricultural yields for communities in selected sites, and adoption of more effective processes and technologies in participating states.

Key Details

Project Details

  • P132739

  • Closed

  • Grant Milne , Priti Kumar, Amos Abu

  • Republic of India

  • India

  • October 23, 2012

  • (as of board presentation)

    July 17, 2014

  • February 8, 2016

  • US$ 357.00 million

  • Department of Land Resources

  • South Asia

  • 2015

  • US$ 178.50 million

  • B

  • Not Applicable

  • July 22, 2019

  • Yes

  • BANK APPROVED

  • March 8, 2022

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 178.50
IDA Credit 178.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 178.50
IBRD + IDA Commitment 178.50
Lending Instrument
Grant Amount N/A
Total Project Cost** 357.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 15, 2024 IDA-55240 Loan Repay 29,923.65
Jan 6, 2017 IDA-55240 Loan Disb 35,633.37
Jul 17, 2014 IDA-55240 Loan Commitment 178,500,000.00
May 15, 2023 IDA-55240 Loan Repay 29,923.65
May 15, 2023 IDA-55240 Int Charges 30,484.06
Nov 15, 2023 IDA-55240 Loan Repay 29,923.65
Nov 15, 2023 IDA-55240 Int Charges 31,371.70
May 15, 2022 IDA-55240 Loan Repay 29,923.65
May 15, 2022 IDA-55240 Int Charges 6,792.81
Nov 15, 2022 IDA-55240 Loan Repay 29,923.65
Nov 15, 2022 IDA-55240 Int Charges 15,704.20
Nov 15, 2020 IDA-55240 Loan Repay 29,923.65
Nov 15, 2020 IDA-55240 Int Charges 10,112.60
May 15, 2021 IDA-55240 Loan Repay 29,923.65
May 15, 2021 IDA-55240 Int Charges 7,292.27
Nov 15, 2021 IDA-55240 Loan Repay 29,923.65
Nov 15, 2021 IDA-55240 Int Charges 6,882.43
Nov 22, 2019 IDA-55240 Loan Cancel 22,477.63
May 15, 2020 IDA-55240 Loan Repay 29,923.65
May 15, 2020 IDA-55240 Int Charges 17,526.69
May 15, 2019 IDA-55240 Int Charges 4,577.79
Jun 25, 2019 IDA-55240 Loan Disb 831,977.80
Nov 15, 2019 IDA-55240 Loan Repay 30,500.00
Nov 15, 2019 IDA-55240 Int Charges 16,395.66
Nov 20, 2019 IDA-55240 Loan Disb 133,273.27
Jul 22, 2019 IDA-55240 Loan Cancel 177,280,000.00
Nov 15, 2018 IDA-55240 Int Charges 4,250.04
Nov 15, 2018 IDA-55240 Int Charges 55.00
Sep 15, 2017 IDA-55240 Loan Disb 28,899.12
Nov 15, 2017 IDA-55240 Int Charges 902.51
Nov 15, 2017 IDA-55240 Int Charges 0.01
Feb 16, 2018 IDA-55240 Loan Disb 92,685.60
Jan 17, 2018 IDA-55240 Loan Disb 36,837.59
May 15, 2018 IDA-55240 Int Charges 122.41
May 15, 2018 IDA-55240 Int Charges 2,260.26
Jan 6, 2017 IDA-55240 Loan Disb 24,451.96
May 15, 2017 IDA-55240 Int Charges 499.50
Jun 27, 2017 IDA-55240 Loan Disb 13,763.67
May 15, 2024 IDA-55240 Int Charges 32,075.04

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Unsatisfactory 2019-06-25
Progress towards achievement of PDO Unsatisfactory 2019-06-25
Counterpart Funding Satisfactory 2019-06-25
Monitoring and Evaluation Unsatisfactory 2019-06-25
Project Management Unsatisfactory 2019-06-25
Financial Management Moderately Unsatisfactory 2019-06-25
Overall Implementation Progress (IP) Unsatisfactory 2019-06-25

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Conservation outcomes in Selected micro-watersheds (MWS)Value0.100.000.00
    DateNovember 1, 2013June 3, 2019March 31, 2022
    Comment
  • PDO 1-a. Average incremental reduction in soil loss (t/ha/year) selected sites to be treated in medium rainfall areas 700 -1,000 mm/yr (baseline and end targets measured in tons/ha/year)Value3.300.005.00
    DateNovember 1, 2013June 3, 2019March 31, 2022
    Comment
  • PDO 1-b. Average incremental changes in overall watershed biomass (NDVI values) in selected sitesValue0.200.000.50
    DateNovember 1, 2013June 3, 2019March 31, 2022
    Comment
  • Increased average % gain in incremental productivity of arable lands in selected MWSs above baselineValue0.000.000.00
    DateNovember 1, 2013June 3, 2019March 31, 2022
    Comment
  • PDO 2-a. Milk (baseline and end target measured in litres/ lacation)Value4.100.005.10
    DateNovember 1, 2013June 3, 2019March 31, 2022
    Comment
  • PDO 2-b. Vegetables (baseline and end target measured in tons/ha)Value15.300.0019.90
    DateNovember 1, 2013June 3, 2019March 31, 2022
    Comment
  • PDO 2-c. Oilseeds (baseline and end target measured in tons/ha)Value561.000.00701.30
    DateNovember 1, 2013June 3, 2019March 31, 2022
    Comment
  • PDO 2-d. Pulses (baseline and end target measured in tons/ha)Value659.000.00790.80
    DateNovember 1, 2013June 3, 2019March 31, 2022
    Comment
  • PDO 2-e. Cereals (baseline and end target measured tons/ha)Value1202.000.001502.50
    DateNovember 1, 2013June 3, 2019March 31, 2022
    Comment
  • Number of new approaches, developed under the project, that are integrated into National watershed guidelines.Value0.000.003.00
    DateNovember 1, 2013June 3, 2019March 31, 2022
    Comment
  • Direct project beneficiariesValue0.000.002400000.00
    DateNovember 1, 2013June 3, 2019March 31, 2022
    Comment
  • Female beneficiariesValue0.000.0030.00
    DateNovember 1, 2013March 9, 2018March 31, 2022
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Component 1 - Strengthen the institutions and human resources of key stakeholders to improve effective implementation of watershed managementValue0.000.000.00
    DateNovember 1, 2013June 3, 2019March 31, 2022
    Comment
  • Component 2: Establish a coordinated approach to provide practical knowledge and tools to support integrated watershed managementValue0.000.000.00
    DateNovember 1, 2013June 3, 2019March 31, 2022
    Comment
  • Component 3: Demonstrate successful implementation of rainfed agriculture and watershed development programs, with a science-basedapproachValue0.000.000.00
    DateNovember 1, 2013June 3, 2019March 31, 2022
    Comment
  • Component 4: Ensure effective, efficient and responsive project managementValue0.000.000.00
    DateNovember 1, 2013June 3, 2019March 31, 2022
    Comment
  • 3-a. Changes in average groundwater levels (post monsoon) in project sites in meters below ground level depth in selected sites (measured in no. of meters below ground level)Value1.000.000.50
    DateNovember 30, 2013June 3, 2019March 31, 2022
    Comment
  • 1-a. Web based knowledge sharing system established at central level for integrated WSD and fully functional, measured by number of visitors (no. of visitors)Value0.000.0020000.00
    DateNovember 1, 2013June 3, 2019March 31, 2022
    Comment
  • 2-a. MET stations and systems in place in selected SWSs, and data flowing to communities on a regular basis (no. of SWSs covered)Value0.000.00300.00
    DateNovember 1, 2013June 3, 2019March 31, 2022
    Comment
  • 4-a. IWMP disbursement ratio in participating project states increases over baselineValue46.000.0060.00
    DateNovember 1, 2013June 3, 2019March 31, 2022
    Comment
  • 3-b. Changes in average groundwater levels (pre-moonson) in project sites in meters below ground level depth in selected sites (measured in no. of meters below ground level)Value3.000.001.10
    DateNovember 30, 2013June 3, 2019March 31, 2022
    Comment
  • 1-b. Functioning M&E cells in State Level Nodal Agencies in participating project states (no. of states)Value0.000.008.00
    DateNovember 1, 2013June 3, 2019March 31, 2022
    Comment
  • 2-b. Basic hydrological monitoring systems installed and functional at community level in maximum of 400 selected sub-watersheds (no. of SWSs covered)Value0.000.00200.00
    DateNovember 1, 2013June 3, 2019March 31, 2022
    Comment
  • 4-b. Effective project management (% of concurrent monitoring recommendations each year, acted upon during implementation)Value0.000.0090.00
    DateNovember 1, 2013June 3, 2019March 31, 2022
    Comment
  • 3-c. DSS models used to support for IWMP planning (no. of states)Value0.000.008.00
    DateNovember 30, 2013June 3, 2019March 31, 2022
    Comment
  • 3-d. Hydrological assessment used by states as part of watershed planning (no. of sites)Value0.000.00400.00
    DateNovember 1, 2013June 3, 2019March 31, 2022
    Comment
  • 3-e. Digitized database fully operational in project states (no. of states)Value0.000.008.00
    DateNovember 1, 2013June 3, 2019March 31, 2022
    Comment
  • 3-f. Operational water user associations created and/or strengthened (number)Value0.000.00200.00
    DateNovember 1, 2013June 3, 2019March 31, 2022
    Comment
  • 3-g. % of farmers adopting improved soil moisture conservation and production technologies in selected sitesValue0.000.0060.00
    DateNovember 1, 2013June 3, 2019March 31, 2022
    Comment