Development Objective

The objective of the Project is to support: (i) enrollment of students in select non-public primary schools in disadvantagedareas;(ii) student attendance in select public and non-public primary schools in disadvantaged areas; and (iii) strengthened management of the Recipient's primary education sector.

Key Details

Project Details

  • P132756

  • Closed

  • Juan Baron , Axelle Latortue

  • N/A

  • Haiti

  • July 29, 2014

  • (as of board presentation)

    June 29, 2013

  • N/A

  • US$ 0.00 million

  • B

  • Not Applicable

  • June 30, 2018

  • Yes

  • BANK APPROVED

  • P124134

  • July 30, 2019

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount N/A
Total Project Cost** N/A

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2018-03-26
Project Management Moderately Satisfactory 2018-03-26
Financial Management Moderately Satisfactory 2018-03-26
Monitoring and Evaluation Satisfactory 2018-03-26
Procurement Moderately Satisfactory 2018-03-26
Overall Implementation Progress (IP) Satisfactory 2018-03-26

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Enrollment of students in select non-public primary schools in disadvantaged areas: Number of children enrolled through the provision of tuition waiversValue80000.00150800.00423000.00
    DateOctober 3, 2011November 14, 2013June 30, 2017
    CommentThis is the final number for 2013-2014 school year.
  • Student attendance in select public and non-public primary schools in disadvantaged areas: Attendance rate is maintained in schoolsbenefiting from the school health and nutrition programValue0.0016.000.00
    DateOctober 3, 2011November 14, 2013June 30, 2017
    CommentTo be established prior to the 2014-15 school yearThe project is still recruiting the firm to administer the test.
  • Strengthened management of the Recipient’s primary education sector: Percentage of schools registered in the school accreditation databaseValue29.000.0070.00
    DateOctober 3, 2011June 30, 2014June 30, 2017
    CommentNot applicableAt least 70%
  • Capacity: Percentage of schools inspected at least once per year by the MENFPValue0.0075.0075.00
    DateOctober 3, 2011April 11, 2014June 30, 2015
    CommentThis is the percentage of project schools inspected.

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of additional classrooms built or rehabilitated at the primary level resulting from project interventions.Value0.000.00160.00
    DateOctober 3, 2011November 14, 2013June 30, 2017
    Comment70 communities where classrooms will be built, have been selected. 63 school are open in temporary shelter, and 10 schools areunder construction.
  • Communities receiving GrantsValue0.0063.0080.00
    DateOctober 3, 2011November 14, 2013June 30, 2017
    Comment63 communities received grants.
  • Textbooks per pupil in tuition waiver schoolsValue3.003.003.00
    DateOctober 3, 2011November 14, 2013June 30, 2017
    CommentAbout eighty-one per cent of the participating schools in the tuition waiver program provided 3 books per student.
  • Percentage of TWP schools publicly posting annual expenditure reportsValue0.0019.0095.00
    DateOctober 3, 2011November 14, 2013June 30, 2017
    CommentThis is the most recent data calculated by the Ministry for the preparation of the Priority Operational Plan 2014-2016
  • Children participating in the integrated nutrition/health programValue70000.0079711.000.00
    DateOctober 3, 2011November 14, 2013June 30, 2017
    CommentThis is the revised total number of children for 2012-2013.[not cumulative]
  • Direct project beneficiariesValue150000.00230511.000.00
    DateOctober 3, 2011November 14, 2013June 30, 2017
    CommentThis is the total number of students in the tuition waiver, community schools and the school health and nutrition program.[not cumulative]
  • Number of additional qualified primary teachers resulting from project interventions.Value0.002669.003700.00
    DateOctober 3, 2011November 14, 2013June 30, 2017
    CommentIt is the number of graduated teachers to date.
  • Teacher’s Guide Developed by MENFPValuenot developednot printedGrade 1 and Grade 2 Teacher’s Guides are in use in
    DateOctober 3, 2011November 14, 2013June 30, 2017
    Comment
  • Percentage of school support visits conducted at least once per year by the MENFPValue0.000.0095.00
    DateOctober 3, 2011November 14, 2013June 30, 2017
    CommentSurvey not yet carried out.
  • Students benefiting from improved reading instruction approach (M ap Li Net Ale)Value0.000.000.00
    DateOctober 3, 2011November 14, 2013June 30, 2017
    CommentLekti se Lavni activities have been postponed and will not be offered for 2013-2014.[not cumulative]
  • The school accreditation system is restructuredValuenot applicablePartially completedMENFP enforces new school licensing standards
    DateOctober 3, 2011November 14, 2013June 30, 2017
    CommentFor 2013-2014 the Ministry of Education prepared a joint annual work plan. It still needs some improvements.
  • Impact evaluations completedValue0.000.002.00
    DateOctober 3, 2011November 14, 2013June 30, 2017
    CommentThe MoE is preparing an integrated action plan to support the EMIS and to determine the activities to be financed by the project.
  • Female beneficiariesValue50.0050.0050.00
    DateOctober 3, 2011November 14, 2013June 30, 2017
    Comment
  • Diagnostic sector study completed and student-mentoring program pilotedValueDiagnostic sector study not designed and student-mNot applicableDiagnostic study completed; Student-mentoring prog
    DateOctober 3, 2011September 30, 2017
    Comment
  • Education sector action plans are developed for 2014-15, 2015-16, and 2016-17ValueFive-year Operational Plan (OP) 2010-15 and three-Education Sector Action Plan 2016-17 is available
    DateOctober 3, 2011September 30, 2017
    Comment
  • System for learning assessment at the primary levelValueNoNoYes
    DateSeptember 30, 2017
    Comment(Stage 1) Not Cumulative(Stage 1) (No Stage 2)
  • Utility of the learning assessment systemValue0.000.000.00
    DateSeptember 30, 2017
    Comment