Huainan Mining Area Rehabilitation Project

Abstract*

The project development objective for the Huainan Mining Area Rehabilitation Project for China is to remediate and create a public space at the JiuDa mining site in Huainan city. The project will have three components. The project components and activities are selected based on detailed environmental site investigations, an environmental and geo-hazard risk assessment, and detailed feasibility studies. Component 1, environmental remediation and water...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objective is to remediate and create a public space at the JiuDa mining site in Huainan city.

Key Details

Project Details

  • P133000

  • Closed

  • Minghe Tao

  • People's Republic of China

  • China

  • September 5, 2013

  • (as of board presentation)

    May 11, 2015

  • September 16, 2015

  • US$ 168.40 million

  • Huainan Project Management Office

  • East Asia and Pacific

  • 2015

  • US$ 100.00 million

  • A

  • July 18, 2023

  • December 31, 2022

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 100.00
Borrower/Recipient 68.40

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 100.00
IDA Commitment N/A
IBRD + IDA Commitment 100.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 168.40

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Aug 18, 2020 IBRD-85120 Loan Cancel 37,000,000.00
Dec 15, 2020 IBRD-85120 Int Charges 247,636.94
Dec 30, 2020 IBRD-85120 Loan Disb 2,143,205.80
Dec 15, 2020 IBRD-85120 Loan Disb 51,737.38
Dec 15, 2020 IBRD-85120 Int Charges 51,737.38
Dec 15, 2020 IBRD-85120 Loan Disb 247,636.94
Feb 10, 2021 IBRD-85120 Loan Disb 7,895,051.00
Jun 15, 2021 IBRD-85120 Int Charges 266,922.84
Jun 15, 2021 IBRD-85120 Loan Repay 803,488.10
Jun 15, 2021 IBRD-85120 Loan Disb 25,872.10
Jun 15, 2021 IBRD-85120 Int Charges 25,872.10
Jun 15, 2021 IBRD-85120 Loan Disb 266,922.84
Mar 31, 2020 IBRD-85120 Loan Disb 3,918,575.20
Dec 15, 2019 IBRD-85120 Loan Disb 90,578.61
Dec 15, 2019 IBRD-85120 Int Charges 90,578.61
Dec 15, 2019 IBRD-85120 Loan Disb 468,076.20
Dec 15, 2019 IBRD-85120 Int Charges 468,076.20
Dec 15, 2018 IBRD-85120 Loan Disb 368,926.97
Dec 15, 2018 IBRD-85120 Int Charges 368,926.97
Dec 26, 2018 IBRD-85120 Loan Disb 3,259,550.50
Jun 15, 2019 IBRD-85120 Loan Disb 480,754.10
Jun 15, 2019 IBRD-85120 Int Charges 480,754.10
Jun 15, 2019 IBRD-85120 Loan Disb 94,183.99
Jun 15, 2019 IBRD-85120 Int Charges 94,183.99
Aug 30, 2019 IBRD-85120 Loan Disb 4,305,377.00
May 25, 2023 IBRD-85120 Loan Cancel 7,572,428.50
Jun 15, 2023 IBRD-85120 Int Charges 73,701.41
Jun 15, 2023 IBRD-85120 Int Charges 6,818.47
Jun 15, 2023 IBRD-85120 Int Charges 1,530,127.20
Jun 15, 2023 IBRD-85120 Loan Repay 1,029,112.40
Dec 15, 2023 IBRD-85120 Int Charges 22,531.54
Dec 15, 2023 IBRD-85120 Int Charges 1,663,856.50
Dec 15, 2023 IBRD-85120 Loan Repay 1,001,797.80
Dec 15, 2023 IBRD-85120 Int Charges 889.35
Apr 10, 2024 IBRD-85120 Loan Cancel 307,601.00
Jun 15, 2024 IBRD-85120 Loan Repay 1,001,797.80
Apr 10, 2024 IBRD-85120 Loan Disb -307,601.00
Jun 15, 2024 IBRD-85120 Int Charges 10,130.92
Jun 15, 2024 IBRD-85120 Int Charges 1,725,092.10
Nov 22, 2021 IBRD-85120 Loan Disb 3,164,925.20
Jun 15, 2022 IBRD-85120 Loan Disb 321,622.30
Jun 15, 2022 IBRD-85120 Int Charges 321,622.30
Jun 15, 2022 IBRD-85120 Loan Repay 873,086.25
Jun 15, 2022 IBRD-85120 Loan Disb 16,897.24
Jun 15, 2022 IBRD-85120 Int Charges 16,897.24
May 12, 2022 IBRD-85120 Loan Disb 4,332,408.00
Dec 15, 2021 IBRD-85120 Loan Disb 21,836.93
Dec 15, 2021 IBRD-85120 Int Charges 21,836.93
Dec 15, 2021 IBRD-85120 Loan Disb 268,573.50
Dec 15, 2021 IBRD-85120 Int Charges 268,573.50
Dec 15, 2021 IBRD-85120 Loan Repay 808,817.00
Nov 21, 2022 IBRD-85120 Loan Disb 2,537,635.20
Dec 15, 2022 IBRD-85120 Int Charges 59,834.45
Dec 15, 2022 IBRD-85120 Loan Repay 961,366.75
Dec 15, 2022 IBRD-85120 Loan Disb 11,732.71
Dec 15, 2022 IBRD-85120 Int Charges 11,732.71
Dec 15, 2022 IBRD-85120 Loan Disb 960,767.06
Dec 15, 2022 IBRD-85120 Int Charges 960,767.06
Jun 15, 2020 IBRD-85120 Loan Disb 464,222.34
Jun 15, 2020 IBRD-85120 Int Charges 464,222.34
Jun 15, 2020 IBRD-85120 Loan Disb 85,385.77
Jun 15, 2020 IBRD-85120 Int Charges 85,385.77
Dec 15, 2017 IBRD-85120 Loan Disb 173,276.66
Dec 15, 2017 IBRD-85120 Int Charges 173,276.66
Dec 15, 2017 IBRD-85120 Loan Disb 107,314.72
Dec 15, 2017 IBRD-85120 Int Charges 107,314.72
Jan 2, 2018 IBRD-85120 Loan Disb 5,720,705.50
Jun 15, 2018 IBRD-85120 Loan Disb 99,757.20
Jun 15, 2018 IBRD-85120 Int Charges 99,757.20
Jun 15, 2018 IBRD-85120 Loan Disb 274,678.38
Jun 15, 2018 IBRD-85120 Int Charges 274,678.38
Dec 15, 2018 IBRD-85120 Loan Disb 99,126.81
Dec 15, 2018 IBRD-85120 Int Charges 99,126.81
Jun 15, 2016 IBRD-85120 Loan Disb 124,619.94
Jun 15, 2016 IBRD-85120 Int Charges 124,619.94
Dec 21, 2016 IBRD-85120 Loan Disb 4,000,000.00
Jun 23, 2016 IBRD-85120 Loan Disb 1,000,000.00
Dec 15, 2016 IBRD-85120 Loan Disb 122,523.38
Dec 15, 2016 IBRD-85120 Int Charges 122,523.38
Dec 15, 2016 IBRD-85120 Loan Disb 18,229.58
Dec 15, 2016 IBRD-85120 Int Charges 18,229.58
Sep 2, 2016 IBRD-85120 Loan Disb 1,000,000.00
Jun 20, 2017 IBRD-85120 Loan Disb 5,735,002.00
Jun 15, 2017 IBRD-85120 Loan Disb 114,279.94
Jun 15, 2017 IBRD-85120 Int Charges 114,279.94
Jun 15, 2017 IBRD-85120 Loan Disb 92,742.51
Jun 15, 2017 IBRD-85120 Int Charges 92,742.51
Sep 16, 2015 IBRD-85120 Loan Disb 250,000.00
Sep 16, 2015 IBRD-85120 Fee Charges 250,000.00
Dec 15, 2015 IBRD-85120 Loan Disb 793.74
Dec 15, 2015 IBRD-85120 Int Charges 793.74
Dec 15, 2015 IBRD-85120 Loan Disb 78,613.03
Dec 15, 2015 IBRD-85120 Int Charges 78,613.03
Dec 30, 2016 IBRD-85120 Loan Disb 2,000,000.00
Jun 15, 2016 IBRD-85120 Loan Disb 2,679.17
Jun 15, 2016 IBRD-85120 Int Charges 2,679.17
May 11, 2015 IBRD-85120 Loan Commitment 100,000,000.00
May 25, 2023 IBRD-85120 Loan Disb -1,389,225.60

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Moderately Satisfactory 2022-06-30
Overall Safeguards Rating Satisfactory 2022-06-30
Procurement Satisfactory 2022-06-30
Progress towards achievement of PDO Satisfactory 2022-06-30
Monitoring and Evaluation Satisfactory 2022-06-30
Overall Implementation Progress (IP) Satisfactory 2022-06-30
Counterpart Funding Satisfactory 2022-06-30
Project Management Satisfactory 2022-06-30
Overall Safeguards Rating Satisfactory 2022-06-30

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 07-18-2023
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 11-08-2023PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • KPI #5 Direct project beneficiariesValue0.0055000.0020000.00
    DateSeptember 23, 2014December 31, 2022December 31, 2022
    Comment
  • KPI #1 Dump sites closed under the projectValue0.0094.9094.90
    DateSeptember 23, 2014December 31, 2022December 31, 2022
    Comment
  • KPI #3 Satisfaction of users of public space created under the projectValue0.0097.9375.00
    DateSeptember 23, 2014December 31, 2022December 31, 2022
    Comment
  • KPI #2 Improved water quality in the remediated area (water quality grade)ValueBelow Class VClass VClass V
    DateSeptember 23, 2014December 31, 2022December 31, 2022
    Comment
  • KPI #5.1 Female beneficiariesValue0.005200.0041.00
    DateSeptember 23, 2014
    Comment
  • KPI #3.1 Satisfaction of female usersValue0.0098.2975.00
    DateSeptember 23, 2014December 31, 2022December 31, 2022
    Comment
  • KPI #3.2 Satisfaction of male usersValue0.0097.4975.00
    DateSeptember 23, 2014December 31, 2022December 31, 2022
    Comment
  • KPI #4 Public space created (public park, tourist/exhibition centers and associated entertainment/ recreational facilities)Value0.00643.57379.67
    DateSeptember 23, 2014December 31, 2022December 31, 2022
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • IRI 1.1 Land area remediated with improved vegetation coverageValue0.00418.96350.00
    DateSeptember 23, 2014December 31, 2022December 31, 2022
    Comment
  • IRI 2.1 Length of road rehabilitated/constructedValue0.005.446.07
    DateSeptember 23, 2014December 31, 2022December 31, 2022
    Comment
  • IRI 3.1 Number of people trained at the skills training institutionsValue0.001157.00965.00
    DateSeptember 23, 2014December 31, 2022December 31, 2022
    Comment
  • IRI 1.2 Vegetation cover of the remediated areas (Percentage)Value20.0075.0575.00
    DateSeptember 23, 2014December 31, 2022December 31, 2022
    Comment
  • IRI 3.1.1 Number of women trained at the skills training institutionsValue0.000.000.00
    DateSeptember 23, 2014
    Comment
  • IRI 1.3 Leachate collected and treated for safe disposal annuallyValue0.00312.00350.00
    DateSeptember 23, 2014December 31, 2022December 31, 2022
    Comment
  • IRI 3.2 Technical Guidelines for mining subsidence area rehabilitation & redevelopmentValueNon-ExistentFinal reports disclosedfinal reports disclosed
    DateSeptember 23, 2014December 31, 2022December 31, 2022
    Comment
  • IRI 1.4 Area protected against 1/30 year floodsValue0.009.309.00
    DateSeptember 23, 2014December 31, 2022December 31, 2022
    Comment
  • IRI 2.2 Number of people employed through site utilization activitiesValue0.00495.00430.00
    DateSeptember 23, 2014December 31, 2022December 31, 2022
    Comment
  • IRI 3.3 Project site management entity established and operationalValueNoYesYes
    DateSeptember 23, 2014December 31, 2022December 31, 2022
    Comment
  • IRI 1.5 Length of green paths constructedValue0.0036.8528.82
    DateSeptember 23, 2014December 31, 2022December 31, 2022
    Comment
  • IRI 2.2.1 Number of women employed through site utilization activitiesValue0.000.000.00
    DateSeptember 23, 2014
    Comment
  • IRI 1.6 Length of the flood discharge canals rehabilitatedValue0.007.618.09
    DateSeptember 23, 2014December 31, 2022December 31, 2022
    Comment
  • IRI 2.3 Number of visitors to public space createdValue0.00110000.00100000.00
    DateSeptember 23, 2014December 31, 2022December 31, 2022
    Comment
  • IRI 2.3.1 Number of Women visitors to public space createdValue0.000.000.00
    DateSeptember 23, 2014July 30, 2018
    Comment
  • IRI 2.4 Total areas of tourist service center constructedValue0.004458.003998.00
    DateSeptember 23, 2014December 31, 2022December 31, 2022
    Comment
  • IRI 2.5 Number of Curbside Service Stations with Public Toilets ConstructedValue0.005.005.00
    DateSeptember 23, 2014December 31, 2022December 31, 2022
    Comment
  • IRI 2.6 Number of Irrigation Pumping Stations ConstructedValue0.002.002.00
    DateSeptember 23, 2014December 31, 2022December 31, 2022
    Comment